Jowers v. Dysard Construction Co.
This text of 100 S.E. 892 (Jowers v. Dysard Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
The opinion of the Court was delivered by
The respondent in his argument on appeal makes the following statement of the facts:
“J. M. Jowers made a contract with the Dysard Construction Company to build certain manholes and flush tanks in the city of Columbia. Dysard Construction Company had *86 a contract with the city of Columbia to build these things and hired Jowers to do certain parts of the work. The contract was in writing and specifically stated the price of the manholes and flush tanks as so much per foot. The testimony showed there were 84. manholes and 173 flush tanks to be built.
“Jowers commenced work on the contract and bought a mule, and wagon, cement, brick, and other material, and built four manholes and eleven tanks, when the defendant drove him off of the work and refused to allow him to finish the contract. The plaintiff then commenced this action, and demanded judgment for the sum of $1,674 damages for breach of the contract and $96.91 for work already done.
“He expressly sought damages for the profits he alleged he would have made on the work, basing his estimate on the amount he had made on the work already done.
“The answer of defendant was a general denial and an allegation that plaintiff had voluntarily abandoned the work and that it had paid him for the work already done.”
The judgment was for the plaintiff, and the defendant appealed upon eight exceptions.
The witness was the city engineer. The plaintiff, when on the stand, said: *87 I knew the work would have to come up to city specifications. My work was satisfactory to the city and its inspectors.”
*86 “I knew the work would be under the city engineer, and that his inspector would check me up and report to the city.
*87 The contract of the plaintiff and defendant was a subcontract, made in subservience to the contract between the defendant and the city. The testimony of the city engineer was competent. The fourth exception is sustained.
3. The appellant complains of error in the exclusion of a report of city inspector, J. W. Burdell. The report was excluded on the ground that the city was not a party to the action. The plaintiff had testified that his work was satisfactory to the city inspectors. We have seen that the city contract was in question and the testimony was competent to disprove his statement.
The last two exceptions complain of matters that are incident to the trial complained of, and, as a new trial must be ordered, these exceptions need not be considered.
Judgment is reversed and a new trial ordered. ¡
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
100 S.E. 892, 113 S.C. 84, 1919 S.C. LEXIS 179, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jowers-v-dysard-construction-co-sc-1919.