Jova Brick Works, Inc. v. City of New York

277 F. 180, 1921 U.S. App. LEXIS 1996
CourtCourt of Appeals for the Second Circuit
DecidedNovember 16, 1921
DocketNo. 15
StatusPublished
Cited by10 cases

This text of 277 F. 180 (Jova Brick Works, Inc. v. City of New York) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jova Brick Works, Inc. v. City of New York, 277 F. 180, 1921 U.S. App. LEXIS 1996 (2d Cir. 1921).

Opinion

ROGERS, Circuit Judge.

The libelant corporation on March 19, 1918, chartered to the city of New York, through its department of street cleaning, its brick barge, J. J. J. No. 6, to be used by it in the disposition of street sweepings and other refuse material gathered in the, streets of the municipality, to be carried from its dumping boards on the water front to its various disposal plants. The barge was delivered into the city’s possession, and was operated by it until March 27, 1918, when a collision occurred off the Port Ivory Fill, Staten Island, where the barge had been moored, which resulted in such serious damage that the barge sank. It is alleged that this was due to the negligence of the city of New York in leaving the scow in a dangerous and exposed position.

The city of New York, by petition under what was then the Fifty-Ninth rule in admiralty (33 Sup. Ct. xxxv), brought in the Shamrock Towing Company and the Director General of Railroads, operating the Philadelphia & Reading Railroad. We shall hereafter refer to the city of New York as the city, to the Shamrock Towing Company as the towing company, to the Director General of Railroads as the Director General, and to the barge as No. 6.

The charter was oral, and it provided, among other things, that the owner should deliver No. 6 to the city with one man on board, called a captain, and that it should receive therefor the sum of $15 per day, including the wages of the so-called “captain.” The city agreed on its part to return the No. 6 to the owner in the same good order and condition as when received, reasonable wear and tear excepted. By its charter the city became the owner of the scow pro hac vice.

The city engaged the towing company to do the towing. On March 25, 1918, the loading of No. 6 having been completed, the towing company, acting under its contract to perform the towage service, started [182]*182out with the No. 6 and three other loaded scows for the disposal plant at Port Ivory in charge of its tug, the Robert J. McGuirl. In a cove at Port Ivory the city had a row of spiles, at which it moored vessels while waiting to be discharged. In length the spiles provided berths for three scows, making it possible to make fast three tiers of scows. The city also had a dredge on fee shore between the spiles and the bridge, which it used in unloading' its scows. On the same day the towing company had taken down four other scows in charge of its tug Elizabeth McGuirl. At Elizabethport the tugs combined their two tows into one tow of eight barges, believing that by so doing they could handle and land them to better advantage.

When they reached Port Ivory they asked the representative of the city in charge of the plant where he wished the boats landed, and he told them to make fast alongside of the other scows, which were then lying at the spiles. One of the tugs then held the scows abreast of the spiles, and the other shoved the boats in, where they were made fast. The tugs then shifted the various scows and evened them up, so as to have the same number in each tier. As finally adjusted, the Jova was the outside boat in the middle tier. At the request of the city’s representative they also took out the scow Hannah E. W. and shoved her over to the digger, to be unloaded in the morning. After this had been done, the masters of the tugs asked the captains of the various vessels in the tow whether they were all right, and, on receiving an affirmative reply, they left and came back to New York.

The city, instead of proceeding with the unloading of the vessbls, did nothing during the day and night of the 26th, and on the morning of the 27th, while the Philadelphia & Reading tugs were coming through with a heavy tow of 28 loaded vessels, the tail of the tow got out of line and swung so far to starboard that it came into contact with the moored scows, and so damaged No. 6 that she filled and sank.

The evidence shows that the city had undertaken to make an improvement at its plant at Port Ivory. Among other things, it had dredged the channel into and in the vicinity of its digger, so as to permit the unloading of more than one vessel at a' The work had so far progressed by March 22d that the city contemplated having the dredging finished and its plant ready to operate by the morning of March 25th. On the latter date it had either four or seven loaded vessels lying at the spiles, - and in order to keep the plant busy it ordered the towing company to tow the eight loaded scows in question down to and leave them at the plant. The city, however, made a mistake in its calculations to the extent that it did not complete its dredging until the evening of March 26th. Although it was perfectly well aware of the situation, it did not countermand the order, but sent the scows to its plant on March 25th, and kept the scows at the mooring spiles from the evening of that day until the morning of the 27th, when the collision occurred.

[1] If it had discharged the cargoes on the morning of the 26th, as it had contemplated, the accident would not have occurred. It preferred, for its own convenience, to leave the boats where they were, and in doing so assumed the risk, and must be held in fault.

[183]*183[2, 3] It appears to be admitted that, at the time the. No. 6 was delivered to the city, she was in good condition. Under the terms of the charter the city was under obligations to return her in like condition, reasonable wear and tear only excepted. This obligation tire city did not till fill, and clearly it must respond in damages therefor, unless it can satisfy the court that it has a valid defense to this suit. It seeks now to find such a defense in the claim, advanced for the first time in the argument in this court, that the “captain” of the No. 6, who was the appointee of the libelant, should have shifted her position between the time she was moored and the time of the collision, and that his negligence in that particular is to be attributed to the libelant, his master. It is answer enough to this contention to say that the position thus taken has no support in the pleadings. Jn the city’s answer ro the libel, and in its petition to be permitted to bring in the towing company and the Director General, it alleges that the collision was caused solely by the fault and negligence of the towing company, and of the tugs Bern, Peueoyd, and Wyomissing, which tugs were owned and operated by the Port Reading Railroad Company.

The city subsequently filed an amended answer and amended petition and in both it again charged that the collision and damages resulted solely from flie fault and negligence of the towing company and its tugs Bern, Pencoyd, and Wyomissing. It not only did not plead the libelant’s negligence, but it made no suggestion, when the case was in the court below, that it in any way attributed negligence to the libel-ant. It certainly cannot be permitted, after it comes into this court, to introduce into the case an issue not raised by the pleadings, and not before the court below.

The evidence conclusively shows that the city, through its officials and employees, directed where the No. 6 should go, and on her arrival at her destination the city’s representatives in charge of the disposal plant directed where she should be placed.

[4] The allegation in the libel is that the libelant leased the No. 6 to the city. The city in its answer denies that allegation, and asserts that it chartered the scow from the lowing company.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barber v. Marina Sailing, Inc.
36 Cal. App. 4th 558 (California Court of Appeal, 1995)
Dunion v. Kaiser
124 F. Supp. 41 (E.D. Pennsylvania, 1954)
Hudson County v. The Chancellor
121 F. Supp. 29 (D. New Jersey, 1954)
The Stamford
35 F.2d 55 (S.D. New York, 1928)
O'Brien Bros., Inc. v. City of New York
9 F.2d 542 (Second Circuit, 1925)
The Lydia
1 F.2d 18 (Second Circuit, 1924)
Hugh D. MacKenzie Co. v. Lydia S. S. Co.
1 F.2d 18 (Second Circuit, 1924)
United States v. City of New York
8 F.2d 270 (S.D. New York, 1923)
McAllister v. Lambert Transp. Co.
2 F.2d 395 (S.D. New York, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
277 F. 180, 1921 U.S. App. LEXIS 1996, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jova-brick-works-inc-v-city-of-new-york-ca2-1921.