Joseph Wayne Suggs v. Suggs Carpet Installation and Hartford Casualty Insurance Company

Court of Appeals of Virginia·Decided March 28, 2006·No. 1459052·Unpublished

Opinion

COURT OF APPEALS OF VIRGINIA

Present: Judges Benton, McClanahan and Senior Judge Coleman Argued at Richmond, Virginia

JOSEPH WAYNE SUGGS MEMORANDUM OPINION* BY

v. Record No. 1459-05-2 JUDGE SAM W. COLEMAN III MARCH 28, 2006

SUGGS CARPET INSTALLATION AND HARTFORD CASUALTY INSURANCE COMPANY

FROM THE VIRGINIA WORKERS’ COMPENSATION COMMISSION

Jean M. McKeen (Fitzgerald, Tomlin & McKeen, on briefs), for appellant.

S. Vernon Priddy III (Sands, Anderson, Marks & Miller, on brief), for appellees.

Joseph Wayne Suggs (claimant) appeals a decision of the Workers’ Compensation Commission finding that (1) Suggs Carpet Installation and its insurer are entitled to reduce payments of claimant’s future compensation and medical benefits pursuant to Code § 65.2-313, until employer recoups $25,000 (the gross recovery obtained by claimant as a result of a third-party settlement); and (2) employer is not responsible for the cost of a hot tub installed at claimant’s residence. For the following reasons, we affirm the commission’s decision.

Background

On January 5, 1995, claimant sustained neck and back injuries resulting from a compensable motor vehicle accident. The commission awarded claimant temporary total disability benefits in the amount of $466 per week from January 5, 1995 through August 16, 1995, and beginning March 22, 1997 and continuing.

*

Pursuant to Code § 17.1-413, this opinion is not designated for publication.

On December 10, 1998, claimant settled a claim against a third party involved in the motor vehicle accident for $25,000. Claimant’s counsel in the third-party case and his previous counsel in this matter deposited on October 22, 2002, with the Henrico County Circuit Court $17,500, the funds from the third-party settlement less attorney’s fees and costs. Claimant then requested through interpleader that the circuit court determine the disbursement of the $17,500. The employer’s insurer was a party named in the interpleader. The insurer filed an answer and a cross-bill seeking the entire $17,500, based on its subrogation rights. As of December 2003, the insurer had paid claimant compensation benefits of $167,036 and medical expenses of $27,749.

At a hearing in the circuit court, the insurer admitted that it had not perfected its subrogation lien pursuant to Code § 65.2-310. The circuit court entered an order dismissing the insurer’s cross-bill for failure to perfect its lien under Code § 65.2-310. In so ruling, the circuit court relied upon Yellow Freight, Sys., Inc. v. Courtaulds Performance Films, Inc., 266 Va. 57, 580 S.E.2d 812 (2003). The circuit court ordered payment of another party’s lien and disbursement of the remaining funds to claimant.

Employer then filed an application with the commission seeking termination of claimant’s outstanding award based upon his recovery from the third-party settlement. When a senior claims examiner found probable cause to refer the matter to the docket, claimant requested review of that finding. The commission affirmed the senior claims examiner’s decision to refer employer’s application to the docket. The commission ruled that although the circuit court found that the insurer failed to perfect its subrogation lien on the settlement proceeds from the third-party action, the doctrine of res judicata did not bar the employer’s application because it sought a reduction of future benefits under Code § 65.2-313, a remedy separate from that provided in Code §§ 65.2-309 and 65.2-310.

Following an evidentiary hearing, the deputy commissioner ruled that while employer did not preserve its subrogation lien under Code § 65.2-310, it did have the right of incremental recovery from future benefits under Code § 65.2-313, which provides the formula for determining the percentage of attorney’s fees and costs to be borne by claimant and employer from the third-party recovery. The deputy commissioner found that the appropriate ratio to be applied to future compensation and medical benefits was total attorney’s fees and costs divided by gross recovery ($7,500.00/$25,000.00), or thirty percent.

The deputy commissioner also rejected claimant’s claim that a hot tub installed at his residence constituted reasonable, necessary, and causally related medical treatment. He ruled that employer was not responsible for the cost of the hot tub installed at claimant’s home in 1998.

In affirming in part and reversing in part the deputy commissioner’s decision, the commission ruled that in Hawkins v. Southside Virginia Training Ctr., 255 Va. 261, 497 S.E.2d 839 (1998), the Supreme Court implied that “Code § 65.2-313 creates the right to the offset and dictates the calculation of the credit.” The commission also relied upon our holding in McKnight v. Work Env’t Assocs., Inc., 43 Va. App. 189, 596 S.E.2d 573 (2004), and it suggested we “reasoned that because the employee received a recovery from the settlement and received benefits from the workers’ compensation insurer, the employer . . . was entitled to an offset to prevent a double recovery.” The commission concluded that the requirements of Code § 65.2-313 had been met in this case and that

to prevent a double recovery, and consistent with McKnight, the employer is entitled to reduce the amount paid toward further entitlement:

“equal to the ratio the total attorney’s fees and costs bear to the total third-party recovery until such time as the accrued post-recovery entitlement equals the sum which is the difference

between the gross recovery and the employer’s compensation lien.”

(Quoting Code § 65.2-313.) The commission ruled “that the right to a reduction of future entitlements is not dependent on the employer’s perfection of its lien, and exists separately as an additional measure to prevent a double recovery.”

With respect to the calculation of the reduction, the commission found that employer had paid claimant $167,036 in disability benefits and $27,749 for medical expenses as of the date of the circuit court hearing. The commission noted employer received nothing from the total proceeds of the settlement of $25,000 because it failed to perfect its lien and, therefore, the “total recovery” under Code § 65.2-313 equaled $25,000 ($25,000 – 0). The commission found that employer’s responsibility for claimant’s attorney’s fees was limited to $7,500, the amount expended to obtain the settlement. Thus, the commission ruled as follows:

[T]he employer’s lien exceeds the $25,000.00 total recovery from the third-party settlement and further . . . that employer is entitled to pay 30 percent ($7500/$25000 = 0.30) of the claimant’s future entitlements until such a time when the employer has paid 30 percent towards $25,000 in future entitlements. At that time, claimant will become entitled to full benefits.

* * * * * * *

Based on the plain language of [Code § 65.2-313], we find the reduction of future entitlements includes reduction of future medical benefits.

Based upon these findings, the commission entered the following award:

Beginning May 20, 2004, the day after compensation was last paid, the employer shall pay weekly to the claimant $139.80 [$7,500 divided by $25,000, multiplied by $466],1 representing the claimant’s portion of the attorney’s fees related to the third-party recovery. These payments shall continue for each week of temporary total disability benefits payable under the open award, until that award is terminated or suspended or the employer

1 Claimant’s temporary total disability rate based upon his November 28, 2001 award is $466 per week.

recovers $25,000, the total recovery from the third-party settlement, through offsets to disability and medical benefits.

As of May 20, 2004, the claimant remains entitled to medical benefits pursuant to Code § 65.2-603. However, he is entitled to 30 percent of his causally related medical expenses until the employer effects a recovery of the $25,000 settlement.

(Footnote added.)

The commission also denied claimant’s claim for the cost of the hot tub installed at his home.

Free access — add to your briefcase to read the full text and ask questions with AI

Joseph Wayne Suggs v. Suggs Carpet Installation and Hartford Casualty Insurance Company, (Va. Ct. App. 2006).

Joseph Wayne Suggs v. Suggs Carpet Installation and Hartford Casualty Insurance Company (Joseph Wayne Suggs v. Suggs Carpet Installation and Hartford Casualty Insurance Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Yellow Freight Systems, Inc. v. Courtaulds Performance Films, Inc.
580 S.E.2d 812 (Supreme Court of Virginia, 2003)
Hawkins v. COM./SOUTHSIDE VA. TRAINING
497 S.E.2d 839 (Supreme Court of Virginia, 1998)
Willie Carl Emberton, Sr. v. White Supply & Glass Company
598 S.E.2d 772 (Court of Appeals of Virginia, 2004)
McKnight v. Work Environment Associates & Travelers
596 S.E.2d 573 (Court of Appeals of Virginia, 2004)
Rusty's Welding Service, Inc. v. Gibson
510 S.E.2d 255 (Court of Appeals of Virginia, 1999)
Tomko v. Michael's Plastering Co.
173 S.E.2d 833 (Supreme Court of Virginia, 1970)
Gartman v. Allied Towing Corp.
467 F. Supp. 439 (E.D. Virginia, 1979)