Joseph Hankins and Theresa Hankins v. Mark C. Burnett and B.J. Burnett
Opinion
In The
Court of Appeals
Seventh District of Texas at Amarillo
No. 07-24-00351-CV
JOSEPH HANKINS AND THERESA HANKINS, APPELLANTS V.
MARK C. BURNETT AND B.J. BURNETT, APPELLEES
On Appeal from the 27th District Court Lampasas County, Texas
Trial Court No. 22589, Honorable John Gauntt, Presiding
April 28, 2025
MEMORANDUM OPINION 1
Before QUINN, C.J., and DOSS and YARBROUGH, JJ.
Covid and its pandemic allegedly rendered it impossible for Mark and B.J. Burnett (Burnett) to fulfill their contract with Joseph and Theresa Hankins (Hankins). The trial court agreed. We reverse.
1 Because this matter was transferred from the Third Court of Appeals, we apply its precedent when it conflicts with that of the Seventh Court of Appeals. TEX. R. APP. P. 41.3.
Background The contract involved the completion and conveyance of a home in Lometa, Texas, by Burnett to Hankins. The home in question was to be identical to that Burnett constructed next door. Burnett had begun building the home when the parties contracted, in November 2021, for its conveyance. Documents were signed and deposits made. Additionally, the parties selected March 15, 2022, as the closing, completion, and conveyance date.
During the interim, various material costs rose, allegedly due to the pandemic.
That delayed the acquisition of those materials and impeded Burnett’s ability to meet the March 15 deadline, or so indicated Mark Burnett. In response, Burnett, through their respective realtors, sought more money from Hankins. Though the contract price was $194,000, the increased amount ranged from an additional $6,000 to $20,000, depending on the witness testifying. Irrespective of the amount, the parties extended the closing date to April 29, 2022.
April 29 came and went. The Hankins appeared at the title company and signed the requisite closing papers. Burnett did not. Burnett viewed his appearance as a futile act since the house had yet to be finished. Instead, Burnett moved into the abode. That resulted in the Hankins’ suing for breach of contract, damages, and specific performance.
The court convened a bench trial, whereat Hankins appeared with counsel.
Burnett appeared pro se. At its conclusion, the trial court entered judgment awarding Hankins $2,500 as discovery sanctions against Burnett but denying other recovery. It also executed findings of fact and conclusions of law revealing the basis for its decision. Among other things, the trial court found 1) “Defendants failed to complete the
construction because the cost of materials more than doubled during the construction and shipments were delayed”; 2) “[t]he issu[es] of impossibility of performance, and the performance of conditions precedent, were tried by consent”; 3) “[t]he contract was vague, had no plans and specifications, and was unenforceable”; and 4) “[t]he unenforceable contract was also not completed because of intervening market conditions brought about by Covid, which prevented performance of the contract.”
Impossibility of Performance The Hankins initially contend that the trial court erred in relieving Burnett from performing due to impossibility. Allegedly, the defense was neither affirmatively pleaded by Burnett, tried by consent, nor proven. We sustain the issues.
Contending that a provision in a contract is void, unenforceable, or unconscionable is a matter in the nature of avoidance which must be affirmatively pleaded. Upshaw v. Lacado, LLC, 650 S.W.3d 61, 79 (Tex. App.—Fort Worth 2021, pet. denied). Failing to plead such an affirmative defense results in its waiver. Id. Defenses of this ilk include the unenforceability of a contract due to vagueness, id., and impossibility of performance. Grayson v. Grayson Armature Large Motor Div., Inc., No. 14-09-00748-CV, 2010 Tex. App. LEXIS 4465, at *12 (Tex. App.—Houston [14th Dist.] June 15, 2010, pet. denied) (mem. op.).
Allegedly, Burnett failed to plead impossibility. We disagree, given our obligation to liberally construe pleadings of a pro se litigant. Delgado v. Combs, No. 07-11-00273- CV, 2012 Tex. App. LEXIS 8610, at *5 (Tex. App.—Amarillo Oct. 15, 2012, no pet.) (mem. op.) (obligating the court to liberally construe pro se pleadings). We arrive at this by reviewing the document utilized by Burnett to join issue.
Neither Burnett filed a formal answer but rather a signed letter dated May 30, 2022.
The document included their address and the proceeding’s cause number. Within it, one finds the statement: “I want to deeply apologize to Mr. & Mrs. Hankins, I am not an extortionist. The windows took over 7 months to receive, and in that time every building product doubled, in some cases tripled.” Mark Burnett’s testimony at trial followed that theme, i.e., costs rose thereby impeding performance.
We treat the May 30 letter as an answer. See Cox v. Nat’l Collegiate Student Loan Trust 2006-2, No. 07-14-00253-CV, 2014 Tex. App. LEXIS 12730, at *2-3 (Tex. App.— Amarillo Nov. 24, 2014, no pet.) (mem. op.) (stating that “[a]n answer does not necessarily have to follow a standard form, and a letter that is signed with the name of the parties, the cause number, and an address constitutes an answer which prevents the taking of a default judgment”). So too do we conclude it provided fair notice of the contention that Burnett’s performance was rendered impossible due to higher costs and delays. Our finding the defense adequately pleaded under the circumstances before us does not mean Burnett proved it, though. The Hankins aver that they did not. So, we now address that matter.
In Texas, impossibility consists of impossibility of performance, commercial impracticability, and frustration of purpose. Imperial Charters, LLC v. Redwood Fire & Cas. Ins. Co., No. 02-24-00237-CV, 2025 Tex. App. LEXIS 2283, at *8-9 (Tex. App.— Fort Worth Apr. 3, 2025, no pet.) (mem. op.) (quoting Key Energy Servs., Inc. v. Eustace, 290 S.W.3d 332 (Tex. App.—Eastland 2009, no pet.)). The trial court at bar found “impossibility of performance,” given its finding that the parties allegedly tried it by consent.
Impossibility of performance may excuse contractual performance when an event occurs, and the contract was made on the basic assumption that the event would not occur. Id. Or as said by our sister court in Austin, “‘[w]here, after a contract is made, a party’s performance is made impractical without his fault by the occurrence of an event the non-occurrence of which was a basic assumption on which the contract was made, his duty to render that performance is discharged, unless the language or the circumstances indicate the contrary.’” Hollis v. Gallagher, No. 03-11-00278-CV, 2012 Tex. App. LEXIS 7547, at *12-13 (Tex. App.—Austin Aug. 28, 2012, no pet.) (mem. op.) (quoting RESTATEMENT (SECOND) OF CONTRACTS § 261 (1981)). Many factors may excuse performance. Id. (quoting Centex Corp. v. Dalton, 840 S.W.2d 952, 955 (Tex. 1992)). Yet, “a contract [being] more burdensome to perform than initially anticipated does not . . . .” Imperial Charters, 2025 Tex. App. LEXIS 2283, at *11; EM Bldg. Contrs. Servs., LLC v. Byrd Bldg. Servs., LLC, No. 05-19-00153-CV, 2020 Tex. App. LEXIS 6342, at *35- 36 (Tex. App.—Dallas Aug.11, 2020, no pet.) (mem. op.). “[M]ere market shifts or financial inability do not usually effect discharge” because they are not a type of basic assumption alluded to in Hollis and on which both parties made the contract. See RESTATEMENT (SECOND) CONTRACTS § 261 comment b (stating that “mere market shifts or financial inability do not usually effect discharge” because such are not assumptions on which both parties made the contract).
Free access — add to your briefcase to read the full text and ask questions with AI
Joseph Hankins and Theresa Hankins v. Mark C. Burnett and B.J. Burnett (Joseph Hankins and Theresa Hankins v. Mark C. Burnett and B.J. Burnett) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.