Joseph D Fail Engineering Co Inc v. Crystal Automation Systems Inc

CourtMichigan Court of Appeals
DecidedJuly 13, 2026
Docket367301
StatusUnpublished

This text of Joseph D Fail Engineering Co Inc v. Crystal Automation Systems Inc (Joseph D Fail Engineering Co Inc v. Crystal Automation Systems Inc) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph D Fail Engineering Co Inc v. Crystal Automation Systems Inc, (Mich. Ct. App. 2026).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

JOSEPH D. FAIL ENGINEERING COMPANY, UNPUBLISHED INC., July 13, 2026 8:56 AM Plaintiff/Counterdefendant-Appellant,

v No. 367301 Montcalm Circuit Court CRYSTAL AUTOMATION SYSTEMS, INC., LC No. 2019-025889-CK doing business as CASAIR, INC.,

Defendant/Counterplaintiff-Appellee.

Before: ACKERMAN, P.J., and REDFORD and FEENEY, JJ.

PER CURIAM.

Plaintiff/counterdefendant Joseph D. Fail Engineering Company, Inc. (JDF) sued defendant/counterplaintiff Crystal Automation Systems, Inc. (Casair) for payment following an engineering project. Casair countersued because of purported issues with the project. A jury rejected Casair’s claim for breach of contract but found that JDF was liable for professional negligence and awarded $1.5 million in damages. The trial court, however, granted judgment notwithstanding the verdict and reformed the verdict to ascribe the damage award to Casair’s breach of contract claim. On appeal, JDF argues that the trial court erred by failing to bar Casair’s claims under the statute of limitations, by granting Casair’s motions for partial summary disposition and for judgment notwithstanding the verdict, and by denying JDF’s motion for new trial on the basis of the damages award. We reverse the trial court’s reform of the jury verdict and otherwise affirm.

I. BACKGROUND

Under the American Recovery and Reinvestment Act, PL 111-5; 123 Stat 115, the federal government appropriated funds for the U.S. Department of Agriculture’s Rural Utilities Service (RUS) to subsidize the deployment of improved internet service in rural areas. Casair, an internet service provider headquartered in Stanton, received funds from this program to finance an approximately 400-mile fiber-optic cable project in central Michigan. After receiving that money, Casair initially hired Midstate Engineering to design the project but became dissatisfied with its

-1- services. Casair entered into a “Post Loan Engineering Services Contract” with JDF in 2012 for JDF to take over from Midstate as the professional engineer on the project. JDF, in turn, hired FiberSmith to act as resident engineers, inspecting the work completed by construction crews from hired contractors.

There were various issues with the project, including contractors not working on the Big Rapids portion of the project, cleanup throughout the project, and failure to obtain permits. The parties also faced significant pressure from the federal government to have the service operational by July 31, 2015—a deadline they met. In the years that followed, the parties continued to communicate about the project and whether they could close out the Contract. In 2016, Casair ultimately hired a third-party engineering firm, Geotech, to review the project. That investigation found many instances of incomplete cleanup, such as exposed infrastructure, including open trenches and fiber-optic cable sticking out of the ground. In April 2017, JDF gave Casair a credit against its fee in recognition of not having properly supervised a contractor. In March 2018, JDF sent an invoice to Casair for work JDF had completed from March to May 2017 involving the review of work performed by a contractor on the project. Steve Meinhardt, president of Casair, sent an e-mail to Robert Fenlason, president of JDF, in July 2019, explaining that Casair would not consider closing out the Contract until Casair had the necessary permits. Fenlason responded, explaining that JDF had contacted municipalities about the permits and had spent significant time reviewing the issues that Geotech had raised. Casair and JDF never closed out their contract.

JDF sued Casair in September 2019, claiming that JDF had completed all of the contracted work and that Casair owed JDF for the work. Casair counterclaimed, alleging, in part, that JDF breached the parties’ contract and was liable for professional negligence.

JDF moved for summary disposition in January 2020, arguing that the two-year statutory period of limitations for professional negligence barred Casair’s claims because JDF’s work on the project ended in 2015. Casair argued in response that JDF was still involved in the project after 2015 and that the parties’ contract was not closed, so the statutory period of limitations had not begun to run. The trial court denied JDF’s motion. JDF applied for leave to appeal the trial court’s denial of its motion, and this Court denied the application.1

Casair moved for partial summary disposition in May 2020, arguing that the parties’ contract clearly provided that JDF could not charge Casair for an engineering fee that was more than 20% above the estimated cost without a formal contract amendment agreed to by Casair and approved by the USDA. The parties had amended the contract one time, and, considering the maximum value of the contract, payments that Casair had already made to JDF, a credit that JDF issued to Casair, and the available 20% increases, JDF’s maximum possible recovery was

1 Joseph D Fail Engineering Co, Inc v Crystal Automation Sys, Inc, unpublished order of the Court of Appeals, entered October 6, 2020 (Docket No. 353919).

-2- $38,992.19. The trial court granted Casair’s motion. JDF applied for leave to appeal the trial court’s order, and this Court denied the application.2

JDF renewed its motion for summary disposition in October 2021, arguing that Casair’s professional-negligence claims subsumed Casair’s remaining claims. The trial court denied JDF’s motion.

The jury trial began in November 2022. During the trial, JDF moved for a directed verdict, arguing that the two-year limitations period barred Casair’s negligence claim because there was no evidence that JDF was involved in the project after 2016. The trial court denied JDF’s motion. The jury found that JDF was liable for professional negligence or malpractice but had not breached the parties’ contract, and it awarded Casair $1.5 million in damages.

After trial, Casair moved for judgment notwithstanding the verdict regarding its breach-of- contract claim, arguing that a reasonable person could not disagree that JDF breached its contractual obligations. JDF also moved for judgment notwithstanding the verdict or a new trial, arguing that the two-year statutory period of limitations barred Casair’s professional-negligence claim and that the evidence did not support the damages award. During a hearing on the motions, the trial court explained that there was evidence about damages at trial, and the trial court could understand how the jury “could have combined certain arguments” to reach the specific amount that it awarded. Further, the trial court thought that the jury “essentially” found a breach of contract and that there was testimony to support that claim. The trial court denied JDF’s motion and granted Casair’s motion to reform the verdict to reflect that JDF had breached the Contract. JDF now appeals.

II. ANALYSIS

A. CASAIR’S MOTION FOR JUDGMENT NOTWITHSTANDING THE VERDICT

JDF argues that the trial court erred by granting Casair’s motion for judgment notwithstanding the verdict. We review de novo a trial court’s decision on a motion for judgment notwithstanding the verdict. Sniecinski v Blue Cross & Blue Shield of Mich, 469 Mich 124, 131; 666 NW2d 186 (2003). We must view the evidence, and all legitimate inferences from it, in the light most favorable to the nonmoving party. Id. If reasonable jurors could have honestly reached different conclusions, then the jury verdict must stand. Genna v Jackson, 286 Mich App 413, 417; 781 NW2d 124 (2009).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kevin Krohn v. Home-Owners Ins Co
802 N.W.2d 281 (Michigan Supreme Court, 2011)
Sniecinski v. Blue Cross & Blue Shield of Michigan
666 N.W.2d 186 (Michigan Supreme Court, 2003)
Kelly v. Builders Square, Inc
632 N.W.2d 912 (Michigan Supreme Court, 2001)
Young v. Sellers
657 N.W.2d 555 (Michigan Court of Appeals, 2003)
Severn v. Sperry Corp.
538 N.W.2d 50 (Michigan Court of Appeals, 1995)
Maddox v. Burlingame
517 N.W.2d 816 (Michigan Court of Appeals, 1994)
Tempo, Inc v. Rapid Electric Sales & Service, Inc
347 N.W.2d 728 (Michigan Court of Appeals, 1984)
Genna v. Jackson
781 N.W.2d 124 (Michigan Court of Appeals, 2009)
Taylor v. Mobley
760 N.W.2d 234 (Michigan Court of Appeals, 2008)
Maiden v. Rozwood
597 N.W.2d 817 (Michigan Supreme Court, 1999)
Silberstein v. Pro-Golf of America, Inc
750 N.W.2d 615 (Michigan Court of Appeals, 2008)
Badalamenti v. William Beaumont Hospital-Troy
602 N.W.2d 854 (Michigan Court of Appeals, 1999)
King v. Reed
751 N.W.2d 525 (Michigan Court of Appeals, 2008)
Ensink v. Mecosta County General Hospital
687 N.W.2d 143 (Michigan Court of Appeals, 2004)
Leavitt v. Monaco Coach Corp.
616 N.W.2d 175 (Michigan Court of Appeals, 2000)
Jackson County Hog Producers v. Consumers Power Company
592 N.W.2d 112 (Michigan Court of Appeals, 1999)
Bauer v. Ferriby & Houston, PC
599 N.W.2d 493 (Michigan Court of Appeals, 1999)
Gebhardt v. O'ROURKE
510 N.W.2d 900 (Michigan Supreme Court, 1994)
Bank of America Na v. First American Title Insurance Company
878 N.W.2d 816 (Michigan Supreme Court, 2016)
Abdul Nahshal v. Fremont Insurance Company
922 N.W.2d 662 (Michigan Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Joseph D Fail Engineering Co Inc v. Crystal Automation Systems Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-d-fail-engineering-co-inc-v-crystal-automation-systems-inc-michctapp-2026.