JOSEPH D. COGLIANO, JR., & Others v. PLANNING BOARD OF NORTON & Others (And a Consolidated Case).

Massachusetts Appeals Court·Decided February 28, 2025·No. 23-P-1450·Unpublished

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

23-P-1450

JOSEPH D. COGLIANO, JR.,1 & others2

vs.

PLANNING BOARD OF NORTON & others3 (and a consolidated case).4

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

This is the second appeal brought by Joseph D. Cogliano,

Jr., and four other abutters (collectively, abutters) in this

litigation involving a large solar photovoltaic installation

(solar installation) that NextSun Energy LLC (NextSun) has

proposed locating in the town of Norton. The proposed

installation includes approximately 10,540 tracking solar panels

and a lithium-ion battery energy storage system and will be built on approximately twenty-three acres of upland cranberry bogs. The installation was also the subject of a prior appeal by the abutters. In an unpublished memorandum and order issued in their first appeal, a different panel of this court upheld certain amendments to the town's zoning bylaw that make it easier to obtain approval of solar installations, including on cranberry bogs. See Cogliano v. Planning Bd. of Norton, 101 Mass. App. Ct. 1114 (2022) (Cogliano I). In this second appeal, the abutters challenge several rulings issued by the Land Court judge at different points in the litigation, including his 2021 summary judgment order directing the planning board of the town of Norton (board) to issue NextSun a floodplain special permit, his decision following trial in 2023 that the energy storage system is a necessary and integral part of the solar installation and therefore within the scope of uses allowed under the amended zoning bylaw, and his removal of two conditions of the board's site plan decision relating to water quantity and quality testing. In its cross-appeal, NextSun contends that the abutters do not have standing to challenge the planning board's decisions based on the risk of fire in the energy storage system, and that the judge abused his discretion in allowing into evidence a diagram prepared by the abutters'

hydrology expert. We affirm the amended judgment in all respects.

Background. In 2018, NextSun applied to the board for site plan approval and a floodplain special permit to build its proposed solar installation. As we summarized in our earlier decision, the board initially denied NextSun's requests for site plan approval and a floodplain special permit. In May 2019, NextSun initiated the first of the Land Court actions by appealing the denial under G. L. c. 40A, § 17, and G. L. c. 240, § 14A. In June 2019, the abutters moved to intervene in the action, arguing that the municipal entities sued by NextSun would not adequately represent their interests. The judge denied the abutters' motion. After NextSun reduced the size of the solar panel installation, the parties agreed to a remand so that the board could consider the amended plan. On remand, the board granted site plan approval subject to sixty-four conditions, but again denied the floodplain special permit. NextSun amended its complaint to add a count challenging the board's remand decision. In June 2019, the abutters filed the second lawsuit in the Land Court challenging Norton's solar bylaw amendments and the notice provided for the board hearing. The abutters then filed a third lawsuit in November 2019 appealing the board's approval of the amended site plan.

In 2020, NextSun and the municipal parties cross-moved for summary judgment in all three cases. In February 2021, the judge issued a summary judgment order that, in part, dismissed the abutters' challenge to the amended zoning bylaw and concluded that the board erred in denying the floodplain special permit. The judge reserved for trial whether NextSun's inclusion of battery storage in the installation was within the scope of uses allowed under the amended zoning bylaw. Following his summary judgment order, the judge issued a separate and final judgment under Mass. R. Civ. P. 54 (b), 365 Mass. 820 (1974), ordering the board to issue the special permit, and stating that "[t]his will allow the issuance of the floodplain special permit . . . , while at the same time allowing the [abutters] to appeal the judgment . . . so that all the questions decided in [the summary judgment decision] can be addressed at once." The abutters appealed from this judgment as well as the judge's order denying their motion to intervene in the first action, and this court affirmed both. See Cogliano I, 101 Mass. App. Ct. 1114.

In April 2021, while the abutters' first appeal was pending, the board granted NextSun a floodplain special permit, and the abutters amended their complaint to challenge it. After a trial in May 2022, the judge issued a thoughtful and detailed

decision setting forth his findings and conclusions. The judge concluded that the abutters are "aggrieved" persons within the meaning of G. L. c. 40A, § 17, and the floodplain special permit was properly issued. The judge further concluded that the board's site plan approval satisfies the requirements of the zoning bylaw, but remanded two of the conditions imposed by the board for further consideration. The judge initially upheld two other conditions involving the surveying and monitoring of water impacts, conditions 19 and 56, but reconsidered after NextSun moved to alter or amend the judgment under Mass. R. Civ. P. 59 (e), 365 Mass. 827 (1974). In an amended judgment, the judge remanded conditions 19 and 56 for reconsideration by the board also.

Discussion. 1. Waiver of the abutters' challenges to the 2021 summary judgment decision. In the present appeal, the abutters make various arguments challenging the judge's decision in 2021 to order the planning board to issue a floodplain special permit. They argue, for example, that the judge erred by purportedly applying the Dover Amendment, G. L. c. 40A, § 3, to override the planning board's decision, and that the board acted within its authority by denying the floodplain special permit in order to protect the public health, safety, and welfare. The abutters waived these issues, however, by failing

to raise them in their first appeal. See Gutierrez v. Massachusetts Bay Transp. Auth., 442 Mass. 1041, 1042-1043 (2004); City Coal Co. of Springfield v. Noonan, 424 Mass. 693, 695 (1997) (City Coal Co.). In City Coal Co., the defendant argued for the first time in his second appeal that prejudgment interest on an award of damages in the judgment should have been calculated at a lower rate. City Coal Co., supra. The Supreme Judicial Court held that, "[w]hatever the merits of that argument, it is too late to make it. The point could have been raised, but was not, on [the defendant's] appeal to the Appeals Court because the issue was apparent on the face of the judgment." Id., citing Frank D. Wayne Assocs., Inc. v. Lussier, 394 Mass. 619, 621-623 (1985). See Levenson v. Brockton Taunton Gas Co., 5 Mass. App. Ct. 883, 884 (1977) (noting "a regrettable tendency to attempt belated or successive bites at the appellate apple").

Free access — add to your briefcase to read the full text and ask questions with AI

JOSEPH D. COGLIANO, JR., & Others v. PLANNING BOARD OF NORTON & Others (And a Consolidated Case)., (Mass. Ct. App. 2025).

JOSEPH D. COGLIANO, JR., & Others v. PLANNING BOARD OF NORTON & Others (And a Consolidated Case). (JOSEPH D. COGLIANO, JR., & Others v. PLANNING BOARD OF NORTON & Others (And a Consolidated Case).) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gulf Oil Corp. v. Board of Appeals of Framingham
244 N.E.2d 311 (Massachusetts Supreme Judicial Court, 1969)
Subaru of New England v. BD. OF APPEALS, CANTON
395 N.E.2d 880 (Massachusetts Appeals Court, 1979)
Frank D. Wayne Associates, Inc. v. Lussier
477 N.E.2d 124 (Massachusetts Supreme Judicial Court, 1985)
Barvenik v. Board of Aldermen of Newton
597 N.E.2d 48 (Massachusetts Appeals Court, 1992)
Kenner v. Zoning Board of Appeals of Chatham
944 N.E.2d 163 (Massachusetts Supreme Judicial Court, 2011)
Buccaneer Development, Inc. v. Zoning Board of Appeals of Lenox
35 N.E.3d 737 (Massachusetts Appeals Court, 2015)
Marashlian v. Zoning Board of Appeals
421 Mass. 719 (Massachusetts Supreme Judicial Court, 1996)
City Coal Co. of Springfield, Inc. v. Noonan
677 N.E.2d 1141 (Massachusetts Supreme Judicial Court, 1997)
Marinelli v. Board of Appeals
797 N.E.2d 893 (Massachusetts Supreme Judicial Court, 2003)
Gutierrez v. Massachusetts Bay Transportation Authority
817 N.E.2d 738 (Massachusetts Supreme Judicial Court, 2004)
81 Spooner Road, LLC v. Zoning Board of Appeals of Brookline
964 N.E.2d 318 (Massachusetts Supreme Judicial Court, 2012)
Grady v. Zoning Board of Appeals
465 Mass. 725 (Massachusetts Supreme Judicial Court, 2013)
N.E. Physical Therapy Plus, Inc. v. Liberty Mutual Insurance
995 N.E.2d 57 (Massachusetts Supreme Judicial Court, 2013)
Levenson v. Brockton Taunton Gas Co.
368 N.E.2d 831 (Massachusetts Appeals Court, 1977)
Monks v. Zoning Board of Appeals
642 N.E.2d 314 (Massachusetts Appeals Court, 1994)
Denneny v. Zoning Board of Appeals
794 N.E.2d 1269 (Massachusetts Appeals Court, 2003)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)