Jorgenson v. Northern States Power Co.

208 N.W.2d 323, 60 Wis. 2d 29, 1973 Wisc. LEXIS 1315
CourtWisconsin Supreme Court
DecidedJune 29, 1973
Docket354
StatusPublished
Cited by9 cases

This text of 208 N.W.2d 323 (Jorgenson v. Northern States Power Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jorgenson v. Northern States Power Co., 208 N.W.2d 323, 60 Wis. 2d 29, 1973 Wisc. LEXIS 1315 (Wis. 1973).

Opinion

Robert W. Hansen, J.

We begin by holding that the acts of both city and power company causally contributed to the personal injuries sustained by the plaintiff and both were properly found negligent. This we do not do to reward those who begin at the beginning in reading appellate court opinions, nor to puzzle those who turn first to the final paragraphs of the opinion to determine what result was reached. We do so to make clear that, as to the appeal of the city and notice *34 of review of the power company, we apply the substantial-factor concept of causation, under which there may be several substantial factors contributing to the same result. 1 We agree with the jury and trial court in this case that acts and failures to act on the part of the city and on the part of the power company were exactly such substantial contributing factors to the light pole’s falling on the plaintiff. Affirmance follows but, nonetheless, we will deal with each of the points raised by each of the defendants in this action.

Duty of the city.

Basically, the city contends that it should not have been held negligent because it had no “duty” to authorize the removal of the pole by the power company. It is true that no provision of the contract between the city and the power company provided for city approval being required for the removal of a light pole. However, the trial court found that “over the years there had developed the practice and understanding between the City and Northern States that it [the power company] did not temporarily remove any of the poles unless it was authorized by the City Engineer.” Additionally, the trial court held that “force and effect must be given to *35 the custom and understanding which had arisen over the years in carrying out this contract.”

The trial court correctly located and applied the basic rule of law that “‘There is no surer way to find out what parties meant, than to see what they have done. . . .’ ” 2 The intention of the parties to any particular transaction “ ‘. . . may be gathered from their acts and deeds, in connection with surrounding circumstances, as well as from their words. . . .’ ” 3 Another Way of stating the same rule is that, when the language of a contract is not clear and is ambiguous, “. . . the practical construction given to it by the acts of the parties is of ‘great force’ or ‘entitled to great weight,’ ” 4 and, under such circumstances, “. . . the court ordinarily will place the interpretation upon the terms of the contract which the parties in the course of their dealings have adopted. . . .” 5 It is not the written words of the contract (for they are silent on the question), but rather the acts and dealings between the city and the power company that make cléar that the permission of the city engineer was required for the power company’s removal of the pole that fell. It is as clear that the failure to respond or give permission for such removal was the sole reason the power company did not remove it prior to the accident. Such failure to act on the part of the *36 city certainly was a substantial factor in the plaintiff’s being injured, and for such failure to act the city was properly held to have been causally negligent.

Governmental immunity.

Secondarily, the city contends that even if it was causally negligent in failing to give permission for the removal of the light pole, it cannot be held liable for the reason that such inaction falls within the realm of legislative or judicial discretion to which governmental immunity from liability still applies. When the doctrine of governmental immunity in this state was abrogated, both as to acts of commission and omission, 6 this court made clear that its decision was not to be interpreted “as imposing liability on a governmental body in the exercise of its legislative or judicial or quasi-legislative or quasi-judicial functions.” 7 So the question is presented as to whether the city engineer’s failure to act on the power company’s request to remove the pole was an exercise of a legislative or judicial function, or quasi-so.

Since Holytz, this court has several times dealt with the issue of whether a particular claim against a municipality fell within the rule of liability, or the exception to it of continued immunity for exercise of legislative or judicial functions. In the first such, governmental immunity was held not to bar an action against a town for negligently failing to replace a stop sign removed by vandals even though the town had no duty to erect the sign in the first place. 8 In the second, governmental *37 immunity was held to bar an action based on claim of error in a city’s programming of a traffic signal. 9 In the third, a failure to erect a warning signal on a highway was held to be an exercise of a legislative function to which governmental immunity applied. 10 In the most recent, it was held that while an action based on a decision to place or not place a warning sign near an intersection was barred, by governmental immunity, if the sign was placed in such a manner that it did not comply with the highway commission directive, a claim of negligence against the city was not barred. 11 For our purposes here, it is enough to note that these cases deal with whether or not the placing of warning or traffic control signals on highways is or is not an exercise of a legislative or quasi-legislative function.

The issue in the case before us relates to the control of the light pole as between the city and the power company. If this had been a city light pole, and notice was given to the city engineer that unless it was temporarily removed it might topple and kill one of the workmen digging the ditch for the city near its base, it is difficult to see what would be legislative or quasi-legislative about the city’s failing to remove its pole so that its excavating project could proceed without danger to the workmen involved. The agreement between the city and power company, whereby the company maintained the pole and needed city permission to remove it, adds nothing either legislative or judicial to the situation. We find no relatedness to a legislative or judicial function in the city’s failure to authorize removal of a light pole temporarily while a trench was being dug alongside it. Governmental immunity for the exercise of a legislative or judicial *38 function cannot be stretched to reach the act of omission here involved.

Negligence of power company.

The notice of review challenges the jury finding that the power company was causally negligent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bostco LLC v. Milwaukee Metropolitan Sewerage District
2013 WI 78 (Wisconsin Supreme Court, 2013)
Wisconsin Natural Gas Co. v. Gabe's Construction Co.
582 N.W.2d 118 (Court of Appeals of Wisconsin, 1998)
Pure Milk Products Cooperative v. National Farmers Organization
280 N.W.2d 691 (Wisconsin Supreme Court, 1979)
Stradinger v. City of Whitewater
277 N.W.2d 827 (Wisconsin Supreme Court, 1979)
Foss v. Town of Kronenwetter
273 N.W.2d 801 (Court of Appeals of Wisconsin, 1978)
Lange v. Town of Norway
253 N.W.2d 240 (Wisconsin Supreme Court, 1977)
Franklin Mutual Insurance v. Meeme Town Mutual Fire Insurance
228 N.W.2d 165 (Wisconsin Supreme Court, 1975)
Sampson v. Laskin
224 N.W.2d 594 (Wisconsin Supreme Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
208 N.W.2d 323, 60 Wis. 2d 29, 1973 Wisc. LEXIS 1315, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jorgenson-v-northern-states-power-co-wis-1973.