Jones v. Pinellas County

88 So. 388, 81 Fla. 613
CourtSupreme Court of Florida
DecidedApril 25, 1921
StatusPublished
Cited by7 cases

This text of 88 So. 388 (Jones v. Pinellas County) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jones v. Pinellas County, 88 So. 388, 81 Fla. 613 (Fla. 1921).

Opinion

Ellis, J.

A writ of error was taken to a judgment of the Circuit Court in favor of the defendant in a cause wherein I. F. Jones, hereinafter referred to as the plaintiff, sued Pinellas County, hereinafter referred to as the county.

The case was tried upon an agreed statement of facts which in substance was as follows: In October, 1914, the county, acting by its Board of County Commissioners, entered into a written contract with the plaintiff for the construction of a county jail upon the county’s property in the town of Clearwater. The contract provided among other things that the plaintiff would supply all labor and material; that the architect’s approval of the work and his acceptance should be taken as a complete performance of the contract by the plaintiff; that the county would pay for the building the sum of $19,865.00, payable on the 15th of each month to the extent of 80% of the value of labor performed and materials furnished upon the certificate of the architect. The payments were to be made in “County Jail Building Warrants” in sums of not less than twenty, nor more than one thousand dollars, in “such form as to meet the wishes” of the plaintiff. It was agreed that the plaintiff in compliance with the contract on his part began the construction of the building upon the lot designated, that he laid and builded the foundations of the building and erected the walls to a height of eight feet and was then notified by the [615]*615County Commissioners not to proceed any further with the construction of t'he building as the Board of County Commissioners had cancelled the contract because it was illegal; that the plaintiff ceased “operation” on the building and has done no more work; that before the County-Commissioners cancelled the contract the plaintiff rendered his bill to the County Commissioners for work done and materials furnished, which bill amounted to $7,628.75, which was approved by the architect, accepted by the Board of County Commissioners, and by it ordered to be paid; that the bill has never been paid, nor any part' of it been paid; that the contract entered into between the county and the plaintiff was illegal because of the reasons given in the case of Bell v. Coachman et al., reported in 69 Fla. 295, 68 South. Rep. 173. The contract having been made under the same resolution as was involved in the above mentioned case and because the resolution of the Board of County Commissioners failed t'o state “that it was necessary” that a new jail should be erected; that the county did not complete the building begun by the plaintiff, but erected a jail on other property. A statement of the labor performed and material furnished by the plaintiff was attached to the agreed statement of facts and admitted to be correct.

The declaration of the plaintiff consisted of five paragraphs, each constituting one count, except the fifth, under which was embraced five common counts as follows : goods bargained and sold; money lent; money paid by the plaintiff for use of the defendant; money received by the defendant for use of the plaintiff, and account stated. That paragraph concluded with an allegation that the several sums of money were to be paid on request, but the defendant had • refused to pay them although requested. That the claims were filed within six months [616]*616after they became due and payment demanded. The first count declared specially upon the contract, the second count was a slightly amplified form of the common count for labor performer and materials furnished, the third count was in substance the same, and the fourth was the common count for work done and materials furnished. A judgment by default was entered for failure to plead or demur, but the default on motion was opened and the county pleaded the general issue to the first count and three special pleas. To the third count the general issue was pleaded and two special pleas. The general issue was pleaded to the fourth count and special pleas averring the same facts as were pleaded to the third count. The second paragraph of the declaration was ignored. So was the fifth paragraph which contained five counts. The plaintiff demurred to the second and third pleas to the first count and second plea to the third count. A motion was made to strike the first and fourth pleas to the first count, the first and third pleas to the third count, and the second and third pleas to the fourth count. The motion to strike was overruled except as to the-second plea to the fourth count as to which it was granted. The demurrer was overruled. In its order overruling the demurrer the court suggested that the pleas should be reframed for the purpose of simplifying them.

Several months later an order was entered sustaining a demurrer to the second count of the declaration and overruling it as to all other counts. Following that order the county after several months interposed an amended second plea to the fourth count and then the pla,intiff joined issue upon the pleas to the third and fourth counts of the declaration. A trial by jury was waived and on the same day the plaintiff moved for a default because [617]*617the county had failed to plead to the fifth, sixth, seventh, eighth and ninth counts of the declaration.

At the time this motion was made the pleadings stood as follows: The declaration consisting of the first count' declaring on the contract; the third count for labor performed and materials furnished, and which alleged that the sum demanded was due by the county for the labor and materials which the county had accepted and had ordered to be paid; the fourth count for work done and materials furnished, and the fifth, sixth, seventh, eighth, and ninth counts embraced in the fifth paragraph. The plaintiff then withdrew the first count. So the plaintiff’s case rested upon a declaration containing merely the common counts for work done and materials furnished, goods bargained and sold, money lent by the plaintiff to defendant, money paid by plaintiff for defendant’s use; money received by the defendant for the plaintiff’s use, and account' stated. The third count was nothing more in its last analysis but a common count for work done and materials furnished combined with an account stated.

So far as the questions involved in the case are concerned, they could have been presented by one count, declaring either upon the contract or for work done, and materials furnished or an account stated and a plea averring the illegality of the contract and the lack of authority on the part of the County Commissioners to incur the obligation as a county obligation. This issue was at last reached and the case submitted to the judge without a jury upon the agreed statement of facts referred to above. The trial court found for the defendant and entered judgment for the county.

[618]*618The first assignment of error is that the court erred in refusing a judgment by default. The defendant failed to plead or demur to the counts numbered from five to nine Inclusive, and the plaintiff argues that he was entitled to his default. The court denied the motion for default because the amended plea to the fourth count by its very words shows that it was intended to apply to the count following the fourth as well as to that count, and was seemingly so treated by counsel until the trial, and for the further reason that under the evidence submitted there could have been no recovry for the plaintiff if there had been no pleas to any of the counts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Santa Rosa County v. Gulf Power Co.
635 So. 2d 96 (District Court of Appeal of Florida, 1994)
Ago
Florida Attorney General Reports, 1978
Robinson's, Inc. v. Short
146 So. 2d 108 (District Court of Appeal of Florida, 1962)
Grady v. City of Livingston
141 P.2d 346 (Montana Supreme Court, 1943)
Board of Public Instruction v. Cooey
175 So. 219 (Supreme Court of Florida, 1937)
Town of Boca Raton v. Moore
165 So. 279 (Supreme Court of Florida, 1936)
Robert G. Lassiter & Co. v. Taylor
128 So. 14 (Supreme Court of Florida, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
88 So. 388, 81 Fla. 613, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-v-pinellas-county-fla-1921.