Jones v. National Printing Co.

13 Daly 92
CourtNew York Court of Common Pleas
DecidedMarch 13, 1885
StatusPublished

This text of 13 Daly 92 (Jones v. National Printing Co.) is published on Counsel Stack Legal Research, covering New York Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jones v. National Printing Co., 13 Daly 92 (N.Y. Super. Ct. 1885).

Opinions

Charles P. Daly, Chief Justice.

This judgment cannot be sustained. When the contract was made, the broker told the plaintiffs that they could not get the order, unless they would guarantee to have the paper on or before the 1st of December, as the defendants then would be “ out of what they were running on, and their presses would be left idle.” The plaintiffs, consequently, when they agreed to furnish the paper by the 1st of December, were advised of' what the effect would be if they failed to do so, and which was what took place; so that, within the rule relied upon by the court below for their judgment, the damages arising from the delay were such as may fairly be presumed to have [95]*95been in the contemplation of both parties at the time of entering into the contract (Hobbs v. London & S. W. R. Co., Eng. L. R. 10 Q. B. 111; Griffin v. Colver, 16 N. Y. 493; Parsons v. Sutton, 66 N. Y. 98). That is, it must be presumed, upon this statement of the broker, that it was in the contemplation of both parties that damages to the defendants would be the result, if the paper was not delivered on the 1st of December; that their presses must lie idle after that time, until the paper was sent or they could elsewhere obtain it.

The judge who delivered the opinion of the General Term, says that the witnesses Colgan and McMullen both concur in stating that any notice that their presses would be idle if the paper was not sent, was given between the 1st and 11th of December, and “ I think,” he adds, “ that a careful examination of the testimony will undoubtedly establish that such is the fact.” On the contrary, an examination of the testimony shows that such was not the fact. Bonny, the broker, Avho made the contract, swore expressly that he said to the plaintiffs, in -placing the contract, that he “ could not give it to them, unless they would guarantee to have it (the paper) on December 1st, or before, as the presses would be idle.”

There is nothing in the case in any way in conflict Avith this. McMullen says nothing in his testimony about giving any notice to the plaintiffs that the defendants’ presses would be idle, and the testimony of Colgan is, that one of the plaintiffs, Skinner, called upon him between the 1st and 11th of December in relation to two letters Colgan had written to him, and that he then told Skinner that the defendants would have to hold the plaintiffs responsible for the damages occurring from the stoppage of the defendants’ presses, and the first of these letters, dated December the 2d, advises the plaintiffs that the non-delivery of the paper involved “quite a heaAy loss;” that the defendants had three presses lying idle in consequence of it, making a daily loss of at least $40 per diem.” There was nothing in tins conflicting Avith the broker’s statement of what he [96]*96said to the plaintiffs in “ placing the contract,” which was previous to the contract, for it was entered into by the letter of the plaintiffs of November 16th, 1882, accepting the order, and the interview with the plaintiffs, to which Bonny testifies, was on the preceding day, November 15th, 1882. If there was anything in the evidence in any way conflicting with this testimony of Bonny, which, I think, there was not, then the question was one for the jury.

It further appeared that the kind of paper which the defendants ordered was of a peculiar size, which the defendants could not readily get in the market—a fact which, as it was not contradicted, it must be assumed that the plaintiffs knew when the contract was made, as they were agents of the mill where this kind of paper was manufactured. It was shown that the defendants tried to get it, or even paper of a larger size, which might, at some expense, have been reduced to a proper size; but it could not be found. So far, therefore, it must be assumed, on this evidence, to have been in contemplation of the parties that the defendants would be out of the paper on the 1st of December, and if none was delivered to them on or before that time, and they could not get it at once in the market, or any that could be made to answer, that they would suffer a loss until they could procure it, or the plaintiffs should deliver it, which the plaintiffs did on December 11th, ten days after the time they had stipulated to deliver it.

The court below cited the ease of Parsons v. Sutton (66 N. Y. 92) as one “ almost identical ” with the present one, which was a case where there was a failure to deliver a quantity of paper at a stipulated time. Judge Hunt, who delivered the opinion of the court in that case, said that the ordinary measure of damages in such a case was the difference between the contract price and the market price at the time and place of delivery; but that this was not the only measure; that if there is no market for the article where it is to be delivered, and if it cannot be had there with reasonable diligence, and the buyer suffers damages because of the seller’s failure to deliver, which is the proximate and [97]*97natural consequence of such failure, then, as a consequence, damages can be recovered; but that the party who suffers from a breach of contract must so act as to make his damages as small and reasonable as he can; that he must not, by inattention, want of care, or inexcusable negligence, permit liis damage to grow, and then charge it all to the other party.

The special damages claimed in that case, by reason of the failure to deliver the paper, was that the defendants could not go into the market after the plaintiff's failure to deliver, for the reason that they could find no such paper in the market. In that case only a small quantity was required; and it was held that it was not sufficient evidence of due diligence on their part that they, a day or two after, went to dealers to try to buy paper like that which the plaintiffs were to deliver, and could find none; they did not, said the court, make any further efforts, and no reason was given, said the court, why they did not try more than once to find the paper; that it did not appear that they could not find paper that would answer substantially the purpose; that they heard plaintiffs were getting ready to deliver it, and, five days after the time when it was to be delivered, they countermanded their order ; that it was proved that they could have had the paper the day after they countermanded it, and that there was no proof that it would not have been just as useful to them on that day as at an earlier day; nor any proof of the damage they suffered by the delay, from the 2d to the 8th day of June; that they had a right to refuse to take the paper after the 2d of June, but could not refuse to take it, and then claim special damages because they could not get it.”

So far from this case being almost identical with the present one, it is, in the most material particulars, essentially different. Here it was not a small quantity of paper that was required, but the order was for a very large quantity. The paper, here, was to be taken when it arrived, by the defendants, because their presses were then lying idle for the want of it; and because the defendants could not, [98]*98after inquiring in the City of New York, which was the place of delivery, and the one where the inquiry in the market was to be made (Parsons v. Sutton, supra, p. 98), procure paper of the kind, or even larger, that might be cut down and adapted to the purpose required.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parsons v. . Sutton
66 N.Y. 92 (New York Court of Appeals, 1876)
Duckworth v. Roach
8 Daly 159 (New York Court of Common Pleas, 1878)

Cite This Page — Counsel Stack

Bluebook (online)
13 Daly 92, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-v-national-printing-co-nyctcompl-1885.