Jones v. Gambill

241 S.W. 1067, 1922 Tex. App. LEXIS 953
CourtCourt of Appeals of Texas
DecidedApril 12, 1922
DocketNo. 1951.
StatusPublished
Cited by4 cases

This text of 241 S.W. 1067 (Jones v. Gambill) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jones v. Gambill, 241 S.W. 1067, 1922 Tex. App. LEXIS 953 (Tex. Ct. App. 1922).

Opinion

HUFF, C. J.

Jones & Lane, contractors, entered into a contract with Geo. B. Ray, Levi Gambill, and W. B. Chauncey to erect a two-story brick building on lot 3, block 151, in the city of Wichita Falls, according to certain plans and specifications prepared by W. Roberts, architect. “Said plans and specifications, together with this contract, of which they are deemed a part, are to be construed together,’’ etc.

The general specifications called for in the contract stipulate, among other things:

“All estimates or orders, or charges, entries and credits, extensions of time, and other matters of record, pertaining to the building, must be executed on regular forms and by the architect.
*1068 “Changes of plans. — The owners reserve the right to make changes during its progress, without affecting the contract or bond. All such changes to he on regular forms of the architect and duplicate copies to be attached to the contract and bond. No changes shall be recognized in final settlement unless ordered in writing by the architect or indorsed in writing by the owner, with the costs or credits stipulated thereon.
“The owners agree to pay the contractors in semi annual payments, the total sum of $19,-740.00, and upon completion, and before final settlement, the contractors, if required by the owners, were to furnish evidence as to the freedom from all liens for debts due or claimed to be due.”

The Massachusetts Bonding & Insurance Company executed a bond as surety for the contractors, payable to the owners, in the sum of $9,870, or persons who may furnish material or perform labor on the building-contemplated. The condition of the bond is that, if the contractors shall keep and perform the covenants, conditions, stipulations, or agreements to be kept and faithfully fulfilled by them as set forth in the contract above mentioned, dated the 30th day of September, 1919, for the construction of the work, building, or improvements mentioned in the contract, and pay the sums as provided therein, and any and all damages or forfeitures, etc., under the terms of the contract by reason of malfeasance or nonperformance on the part of the contractors, and if the contractors shall properly make payments to all persons, supplying them labor and material in the prosecution of the work provided for in the contract, then the bond shall be null and void, etc. The bond: bears date October 1, 1919.

A supplemental contract bearing date September 30, 1919, the date of the original contract above referred to, made between the owners and contractors, in which it is recited it should be construed in connection with and as an addition thereto, the owners stipulating therein they would purchase and have installed am elevator in the building and furnish the feed wires therefor, and the contractors should prepare elevator shaft and do all work in the construction and in connection therewith for the installation of the elevator, and, if necessary, prepare a pit and penthouse for the elevator, should it require the same, and the compensation mentioned in the contract above referred to should cover the compensation of the contractors in the contract then executed. This additional contract was signed by the owners and the contractors. On the 15th day of October, 1919, an instrument was executed reciting the making of the contract of September 30th, and that it was the desire of the pwners. and contractors to make certain changes, providing therein “to change all joists as set forth in plans from a transverse position to a longitudinal position, as fully set forth in the drawing,” giving the specifications for constructing the transverse beam, the owners agreeing to pay the additional sum of $707.05 on account of the change. This instrument was signed by the owners and contractors, and indorsed by W. Roberts, architect.

On February 3, 1920, the owners, the appel-lees herein, instituted suit on the contract and bond above set out, and by amendment filed December 13, 1920, alleged: That on February 3, 1920, Jones & Dane refused to erect the building in compliance with the terms of the contract, and refused to prepare a pit and penthouse for the installation of the elevator, and that the owners notified the appellant bonding company of the failure and refusal of the contractors; that the bonding company refused to complete the building, ignoring appellee’s request for it to do so; that the contractor would neither complete the building nor permit appellees to do so, and thereupon appellees filed suit and procured the issuance of an injunction against appellant contractors from interfering with appellees in completing the building, and upon the issuance of the writ the appellees entered upon the premises and completed: the building at an actual cost above the contract price of $779.41. At the filing of the suit there was unpaid on the contract due by appellees tire sum of $5,-657.05, which the appellees then filed with the clerk of the court. They also alleged, by reason of the failure of the appellants to complete- the building on December 10, 1919, the date fixed by the contract for its completion, appellees sustained damages in the sum of $1,375, or at the rate of $25 per day from December 10, 1919, to February 4, 1920. They allege that the sum of $779.41 was the reasonable and necessary sum expended in completing the building in accordance with the plans and specifications. It was also alleged that appellees, before entering into the contract with appellants, had entered into a contract with one Cochran for the rental of the building after it was completed, at a price of $25 per day, and that Cochran stood ready and willing at all times to take possession of the building as soon as it was completed. It was also alleged by the amendment that the intervener Alfalfa Lumber Company, was making a claim that it furnished material to the contractors for-the building in the total sum or price of $5,175, and that the Wichita Builders’ Supply Company was claiming it had furnished the sum of $619.57. The prayer was for judgment for the two items above set out, and that the amount be deducted from the sum of $5,657.05 held by the clerk, and unpaid on the contract price, and prorated among the interveners.

The case was tried before the court with *1069 out a jury. In the judgment the court recites his findings of fact. He finds: On September 30, 1919, the execution of the building contract to build the structure described in the petition, at the contract price of $20,457.05. That appellees paid on the contract the suns of $14,800. Before the building was completed the contractors refused to complete the building in accordance with the contract, and thereupon appellees filed suit and obtained a temporary writ of injunction to prevent the contractors from interfering with the appellees in the completion of the building. That appellees deposited with the clerk $5,657, the balance due on the contract price. Upon the failure of the contractors to complete the building ap-pellees notified the appellant bonding company of such refusal, and that the bonding company refused to complete the • building. The appellees thereupon took the building in charge, and expended the reasonable and necessary' sum of $760 in completing the building according to the terms of the contract. That appellees were further damaged in the sum of $1,375 on account of the appellants’' failure tot complete the building by December 10, 1919.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas v. Mullins
127 S.W.2d 559 (Court of Appeals of Texas, 1939)
Bradshaw v. Wolfe City
3 S.W.2d 527 (Court of Appeals of Texas, 1927)
Employers' Casualty Co. v. Irene Independent School Dist.
286 S.W. 539 (Court of Appeals of Texas, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
241 S.W. 1067, 1922 Tex. App. LEXIS 953, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-v-gambill-texapp-1922.