Jones v. Atkins

494 S.W.2d 448, 254 Ark. 472, 12 U.C.C. Rep. Serv. (West) 685, 1973 Ark. LEXIS 1537
CourtSupreme Court of Arkansas
DecidedMay 14, 1973
Docket5-6242
StatusPublished
Cited by3 cases

This text of 494 S.W.2d 448 (Jones v. Atkins) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jones v. Atkins, 494 S.W.2d 448, 254 Ark. 472, 12 U.C.C. Rep. Serv. (West) 685, 1973 Ark. LEXIS 1537 (Ark. 1973).

Opinion

Conley Byrd, Justice.

This litigation arises out of some hog paneling manufactured by Balhan Manufacturing Company. The appellee Glen Atkins being desirous of going into the hog business, looked at a number of installations in other states and decided to install what he describes as the “Cargill system.” He had learned that he needed a heavy duty Balhan panel 16 ft. in length and 35 inches high and that he could acquire them in Missouri at a cost of $8.75 per panel. When appellee got ready to order his wire panels he talked to Larry Johnson an employee of appellant, David Jones D/B/A Wickes Lumber & Building Supply Center, and told him that he would order the heavy duty panels from him if the price was right. When Johnson asked him what price he was talking about, he told Johnson that he could get the panels in Missouri for $8.75 per panel. Johnson later called back and informed appellee that he could deliver the panels for $8.77 per panel. Appellee ordered 228 panels at that time and paid for the same either upon delivery or shortly thereafter. During the construction, appellee determined that he needed an additional 57 panels and upon calling appellant found that Johnson’s employment had been terminated. However, he placed the order with appellant for the 57 panels. Those panels arrived on April 5, 1970, on a truck loaded with some additional panels. At that time appellee discovered that the wire in the other panels loaded on the truck was of a heavier gauge than what he was receiving. He had installed only a few panels of the first order at that time. Because of his breeding and farrowing schedule appellee used the 57 panels to complete his “Cargill system.” Appellee testified that he did not make an earlier complaint after delivery of the second order, because he desperately needed these additional panels to bring his operation up to schedule and it took him some time to see that the wire was unsuitable for his purposes. When appellant refused to make any adjustment, appellee refused to pay for the 57 panels. At the trial appellee testified that because of small difference between the gauge of the wire in the heavy duty panels and the gauge in the light weight panels, it was impossible for him, without a comparison, to determine that the 228 panel shipment did not conform to his heavy duty order. Other testimony on his part showed that Balhan Manufacturing Company regularly retailed the heavy duty panel for $8.75 and the light weight panel for $6.75. The difficulty with the light weight panel arose because the welds broke loose permitting the hogs to go from one pen to another.

Appellant brought this suit to recover the price of the 57 panels. Appellee counterclaimed for damages for the non-conformity between the heavy duty panels he had ordered and the light weight panels he had received. At the close of the evidence appellant moved for a directed verdict under two provisions of the Uniform Commercial Code. — i.e. Ark. Stat. Ann. § 85-2-602 and § 85-2-606. Those sections provide:

“85-2-602. Manner and effect of rightful rejection.—
(1) Rejection of goods must be within a reasonable time after their delivery or tender. It is ineffective unless the buyer seasonably notifies the seller.
(2) Subject to the provisions of the two [2] following sections on rejected goods (Sections 2-603 and 2-604 [§§ 85-2-603, 85-2-604]),
(a) after rejection any exercise of ownership by the buyer with respect to any commercial unit is wrongful as against the seller; and
(b) if the buyer has before rejection taken physical possession of goods in which he does not have a security interest under the provisions of this Article (Subsection (3) of Section 2-711 [§ 85-2-711]), he is under a duty after rejection to hold them with reasonable care at the seller’s disposition for a time sufficient to permit the seller to remove them; but
(c) the buyer has no further obligations with regard to the goods rightfully rejected.
(3) The seller’s rights with respect to goods wrongfully rejected are governed by the provisions of this Article on Seller’s remedies in general (Section 2-703 [§ 85-2-703]). [Acts 1961, No. 185, § 2-602.]
“85-2-606. What constitutes acceptance of goods.—
(1) Acceptance of goods occurs when the buyer
(a) after a reasonable opportunity to inspect the goods signifies to the seller that the goods are conforming or that he will take or retain them in spite of their non-conformity; or
(b) fails to make an effective rejection (subsection (1) of Section 2-602 [§ 85-2-602]), but such acceptance does not occur until the buyer has had a reasonable opportunity to inspect them; or
(c) does any act inconsistent with the seller’s ownership; but if such act is wrongful as against the seller it is an acceptance only if ratified by him.
(2) Acceptance of a part of any commercial unit is acceptance of that entire unit. [Acts 1961, No. 185, § 2-606]”

The trial court ruled that “the facts in this case, in the Court’s opinion, don’t fit into the statutes that you have quoted, Mr. Switzer” and dismissed both the complaint and counterclaim with prejudice. For reversal appellant contends that the trial court erred in failing to direct a verdict on the basis that the Uniform Commercial Code did not apply and because appellee’s counsel admitted that he was entitled to a directed verdict.

We do not agree with appellant’s argument that the trial court refused to apply the Uniform Commercial Code. Rather it appears to us that he only held inapplicable to the facts of this case the two sections upon which appellant relied. As we view this record a fact issue, particularly as to the 228 panels, was made under Ark. Stat. Ann. § 85-2-608 which provides:

“85-2-608. Revocation of acceptance in whole or in part. — (1) The buyer may revoke his acceptance of a lot or commercial unit whose non-conformity substantially impairs its value to him if he has accepted it.
(a) on the reasonable assumption that its non-conformity would be cured and it has not been seasonably cured; or
(b) without discovery of such non-conformity if his acceptance was reasonably induced either by the difficulty of discovery before acceptance or by the ■seller’s assurances.
(2) Revocation of acceptance must occur within a reasonable time after the buyer discovers or should have discovered the ground for it and before any substantial change in condition of the goods which is not caused by their own defects. It is not effective until the buyer notifies the seller of it.
(3) A buyer who so revokes has the same rights and duties with regard to the goods involved as if he had rejected them. [Acts 1961, No. 185, § 2-608.]”

In speaking of the rights of a buyer to recover damages for breach in regard to accepted goods, the American Law Institute pamphlet on Sales and Bulk Sales by William D. Hawkland, contains this language:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Microsize, Inc. v. Arkansas Microfilm, Inc.
780 S.W.2d 574 (Court of Appeals of Arkansas, 1989)
HANNA LUMBER COMPANY v. Neff
579 S.W.2d 95 (Supreme Court of Arkansas, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
494 S.W.2d 448, 254 Ark. 472, 12 U.C.C. Rep. Serv. (West) 685, 1973 Ark. LEXIS 1537, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-v-atkins-ark-1973.