Jones & Laughlin Steel Corporation v. Vang

73 F.2d 88, 1934 U.S. App. LEXIS 2603, 1934 A.M.C. 1303
CourtCourt of Appeals for the Third Circuit
DecidedSeptember 27, 1934
Docket5466
StatusPublished
Cited by12 cases

This text of 73 F.2d 88 (Jones & Laughlin Steel Corporation v. Vang) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jones & Laughlin Steel Corporation v. Vang, 73 F.2d 88, 1934 U.S. App. LEXIS 2603, 1934 A.M.C. 1303 (3d Cir. 1934).

Opinion

WOOLLEY, Circuit Judge.

Receivers of Iron City Sand & Gravel Company and sundry persons and corporations filed in the District Court of the United States for the Western District of Pennsylvania a libel in personam against the Jones & Laughlin Steel Corporation seeking damages for injuries to their marine properties occasioned by the alleged negligence of the respondent in handling a barge and allowing her to break away and drift downstream. The respondent by answer denied liability and by petition prayed that, if liable, its liability be limited to the barge and her pending freight. From an interlocutory decree holding it at fault and denying limitation of liability, the respondent steel corporation appealed.

The story of the ease as told by the undisputed facts is briefly as follows:

The respondent purchased coal from the Vesta Coal Company under a contract which called for delivery in barges at its South Side plant on the Monongahela river in the city of Pittsburgh. The coal company loaded its barges with coal at its mines upstream, caused them to be towed in flotillas downstream by a river steamer, made deliveries by leaving barges singly or in groups with the respondent’s fleet at its plant, there to be manned, supplied with lines, moved and unloaded by the respondent how and when it chose.

On March 11, 1933, the coal company’s steamer placed Barge 698, laden with coal, in the respondent's fleet of barges at its South Side plant. In consequence of heavy rains in the region upstream, the Monongahela river had on that day (as shown by river gauges read at eight o’clock in the morning) begun to rise at Pittsburgh. It was about four feet above normal. Readings at the same time on March 12 showed a rescission of about a foot and on March 13 of a few inches. Early in the morning of March 13, a heavy rain, amounting almost to a cloudburst in the upper reaches of the river, set in and continued most of the day, so that on the morning of March 14 the river gauges at Pittsburgh showed 20.01 feet, a rise of 6 feet during the preceding twenty-four hours. On that day there was a further rise of 3.3 feet. During the thirteenth and fourteenth the rise of water up the river, with which rivermen at Pitts *89 burgh keep themselves posted, was even more marked.

The barge in question was a steel craft, square-ended, without a deck, 208 feet in length, 26 feet beam and 9 feet in depth, laden with nine hundred tons of coal. In the afternoon of March 13 she was warped out of her position in the fleet and placed in a slip beneath a coal hoist (astride the slip) for the purpose of unloading. The slip is a waterway in the river, a little wider than the beam of the barge, made between work-barges lashed to piers supporting one end of the coal hoist ashore and a work-barge and, a flat-barge made fast to a pier supporting the other end of the coal hoist in the stream. As only about seventy-five tons of coal had been removed that afternoon, the barge was left in the slip over-night. On the morning of the fourteenth, however, the men in charge of the fleet, observing the greatly increased rise in the river, set about to make everything fast. They ran lines from the abutments and across the barges tying them together. Finally they had everything secure. The barge in question was still in the slip. No more of her ear-, go had been hoisted.

On returning from lunch shortly after noon, the respondent’s men at the landing observed that a gorge, comprising an accumulation of river drift, logs, trees, posts and brush, had formed in the slip- against the upstream end of the barge, that it had “jammed solid,” and liad readied such proportions both as to solidity and area that it was deemed necessary for the protection, of the rest of the fleet to afford it an outlet by moving tlie barge from the slip-, “digging out tho drift”, and lot-ting the current carry it away. It was, however, not until about three o’clock that tho work of shifting the barge was actually begun. By means of cables on tlie shore barges, operated by electric winches, the barge in question was pulled downstream away from the gorge about 50 feet, which was as far as tho length of the cables would permit. The gorge held fast. The cables were then east off and three hemp lines from the work-barge and flat-ba rge on the opposite side were made fast to her, the intention being, while the three hemp lines were being slacked out by hand, to let the current carry the barge some 80 feet farther downstream and away from the gorge until she had reached a point where she could be breasted into the fleet at a position made vacant for her. At the moment the seeond operation (that of slacking out the hand lines) was begun, the drift which had accumulated at tho head of the slip suddenly broke, and was carried through the fifty feet of open water to the barge with such force that when it struck her it caused the first of tho three lines to break, the seeond line to break the mooring post to which it was secured, and tho third to slip off the mooring post to which it had been fastened. The barge, with no one aboard, and being' then out of control and still heavily laden, was carried away on the swift current of the swollen water downstream where it swept into the fleet of the Iron City Sand & Gravel Company, tore away the lashings of a number of barges and other flotilla which in turn spread upon the river, drifted at random and inflicted damage to the craft of still another fleet farther down.

Out of these facts three issues arose:

(a) "Whether or not the respondent, through its servants, was negligent or at fault in moving the barge in the manner and at the time it did; (b) whether or not the respondent held the barge as bailee or under charter and, according to a finding of bailment or charter, (c) whether liability for negligence, if negligence be found, is for all damages or for damages limited to the value of the barge and her pending freight.

These issues bring into view the disputed facts of the ease which are many.

(a) On the issue of negligence or fault, tho testimony is directed first to a question whether the respondent’s servants acted as good rivermen — that is, men on the Monongahela river at Pittsburgh conversant with the habits of that waterway when swollen by heavy rains and with the hazards to craft upon its surface — in lashing tho barges to one another by cross lines and leaving the barge in question in' the slip on the morning of Mareh 14. It seems to us this is not an important question, at least not the decisive one, for assuming, as some of the testimony indicates, that this was good watermanship, tho question of fault centers in what was done afterward when, having made the fleet snug, the men changed their minds when later in the day tho gorge formed at the head of the barge in the slip. Knowing the river and knowing that currents in that stretch set drift on swollen waters in the direction of the slip, they were hound to anticipate drift, which apparently they did, for they prepared for it by lashing the fleet. But when the drift solidified into a gorge at the head of the slip, the men saw it, walked upon it, and were bound within reason to anticipate its behavior if relieved of the support of the barge which was held in the slip by moorings. They *90 knew that the drift was working under the barge an,d raising her at that end, and that in consequence the pressure was not static but active.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re the Complaint of Anheuser-Busch, Inc.
742 F. Supp. 1143 (S.D. Florida, 1990)
Lancaster v. Ohio River Co.
446 F. Supp. 199 (N.D. Illinois, 1978)
Complaint of B.F.T. No. Two Corp.
433 F. Supp. 854 (E.D. Pennsylvania, 1977)
Atlantic Banana Company v. MV" CALANCA"
342 F. Supp. 447 (S.D. New York, 1972)
Trexler v. Tug Raven
290 F. Supp. 429 (E.D. Virginia, 1968)
In re the United States
259 F.2d 608 (Third Circuit, 1958)
In re United States
155 F. Supp. 714 (D. Delaware, 1957)
Crain Bros. v. Wieman & Ward Co.
126 F. Supp. 675 (W.D. Pennsylvania, 1954)
The Severance
152 F.2d 916 (Fourth Circuit, 1945)
Segrave v. McLain Line, Inc.
41 F. Supp. 326 (E.D. New York, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
73 F.2d 88, 1934 U.S. App. LEXIS 2603, 1934 A.M.C. 1303, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-laughlin-steel-corporation-v-vang-ca3-1934.