Jones Co. Custom Homes of Tennessee v. Commerce Bank, N.A.

116 S.W.3d 653, 2003 Mo. App. LEXIS 1266, 2003 WL 21909568
CourtMissouri Court of Appeals
DecidedAugust 12, 2003
DocketED 81633
StatusPublished
Cited by3 cases

This text of 116 S.W.3d 653 (Jones Co. Custom Homes of Tennessee v. Commerce Bank, N.A.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jones Co. Custom Homes of Tennessee v. Commerce Bank, N.A., 116 S.W.3d 653, 2003 Mo. App. LEXIS 1266, 2003 WL 21909568 (Mo. Ct. App. 2003).

Opinion

LAWRENCE G. CRAHAN, Judge.

The Carothers Development Partnership (“Seller”) appeals the judgment enjoining payment of a letter of credit in its favor. We reverse and remand.

Seller owned a 143 acre tract in Franklin, Tennessee. Seller held the property as a land speculator with the intention of ultimately selling it to a third party for development. Jones Company Custom Homes of Tennessee, Inc., (“Buyer”) owned an adjacent parcel of land on which it was constructing a residential community known as McKay’s Mill. On July 24, 2000, Buyer and Seller entered into a Land Purchase Agreement (“Agreement”) pursuant to which Buyer agreed to construct on Seller’s property a road known as the New Liberty Pike Extension and to install sewer, water, electric, and gas lines and conduit. In exchange, Seller agreed to convey to Buyer a portion of its property. The amount of property to be conveyed was to be determined based on the cost Buyer incurred in constructing the improvements. Construction of the road provided Buyer with better access to its residential community and would make Seller’s remaining property more desirable to potential developers. The agreement called for a closing no later than October 15, 2000.

Prior to the scheduled closing, one of the partners who owned Seller learned that the City of Franklin had put a hold on additional sewer connections because the existing main sewer line that served the area was at or near capacity. The partner so informed Dan Crunk, Buyer’s engineer. The parties then negotiated and signed an amendment to the Agreement dated October 10, 2000 (“Amendment”). In pertinent part, the Amendment provided:

WHEREAS, after the Agreement was executed the parties learned that the City of Franklin (“the City”) will not permit the sewer lines to be installed until the sewer main (the “Sewer Main”) that would serve the Sewer Lines is enlarged and upgraded by the City; and
WHEREAS, the parties nevertheless wish to proceed with the transaction contemplated by the Agreement,
NOW, THEREFORE, the parties agree as follows:
1. Purchaser will construct the Road without installing the Sewer Lines.
2. Seller will be solely responsible for installing the Sewer Line.

The Amendment extended the closing date until November 1, 2000, and provided *656 that Buyer would “deposit $300,000 in cash or by an irrevocable letter of credit reasonably satisfactory to Seller (the ‘Sewer Deposit’) with Lawyers Title Insurance Corporation.” Lawyers Title was directed to hold the Sewer Deposit until the first to occur of the following events:

(i) The City’s permitting Seller to install the Sewer Lines and to connect the Sewer Lines to the Sewer Main; or
(ii) March 31,2002.

Pursuant to the Amendment, if the City’s permission to install and connect the Sewer Lines occurred before March 31, 2002, and the parties so certified to Lawyers Title, Lawyers Title was to return the Sewer Deposit to Buyer. Conversely, if Seller certified to Lawyers Title that such permission was not received by March 31, 2002, Lawyers Title was directed to deliver the proceeds of the letter of credit to Seller. In all other respects, the Agreement remained in full force and effect.

After the parties executed the Amendment on October 10, 2000, they learned that the City had imposed a formal moratorium on grants of new sewer availability. On July 10, 2001, the City’s Mayor and Board of Alderman (“Board”) approved a motion that no new sewer availability would be granted for the Watson Branch Interceptor Sewer Line serving the area in question until a new gravity flow line was installed next to it, expanding the capacity. Later, on October 9, 2001, the Board adopted a more formal, written resolution, clarifying the policy adopted on July 10, 2001. According to the October 9, 2001 resolution, after its action on July 10, 2001, the City had received a number of requests for sewer service on the Watson Branch Line from residents or contractors who claimed a prior contractual or other vested right to sewer service and/or that there was sufficient capacity within the line to accommodate their developments, or both. The resolution reconfirmed the Board’s previous finding that the Watson Branch Line was flowing at or near capacity and its policy that no new sewer connections would be granted until completion of the new line, which was anticipated to be June 1, 2003. However, the Board adopted limited exceptions to the policy to accommodate those claiming to have acquired a vested right prior to July 10, 2001. Specifically, new sewer installations could be completed if: (1) The City water and wastewater Director and the City of Engineer agreed that the development would not materially add to the flow of the Watson Branch Line; and (2) either a written request or site plan had been submitted or availability had been granted prior to July 10, 2001.

Seller had neither requested nor been granted sewer availability prior to July 10, 2001. Nor had it submitted a site plan-prior to that date. To do so, Seller would have had to have submitted a statement regarding the expected sewer discharge capacity for the project in question and a site plan. Inasmuch as Seller did not intend to develop the property itself and had not yet found a buyer from which it could ascertain its plans for development, Seller was not in a position to do either. No representative of Buyer ever requested that Seller apply for a permit and Seller did not do so. On April 9, 2002, the Assistant Director of City’s Waste and Waste-water Department wrote to Seller confirming the resolution and stating that construction of the sewer main expansion had a scheduled start date of March 1, 2002. The contact called for completion of the expansion within 18 months.

On April 2, 2002, Seller certified to Lawyers Title that “the City of Franklin, Tennessee did not permit [Seller] to install and connect the Sewer Lines (as defined in Land Purchase Agreement, as amended, *657 between the above referenced parties) to the City’s sewer main prior to March 31, 2002.” The following day, Buyer filed the instant suit seeking to enjoin Seller, Lawyers Title and Commerce Bank, which issued the letter of credit, from drawing on or paying out the letter of credit. Buyer claimed that Seller had breached the agreement by failing to make a good faith effort to procure the City’s permission to connect the sewer line to the sewer main and therefore was not entitled to draw upon the letter of credit as provided in the amendment. The trial court issued a temporary restraining order and the hearings on the request for a temporary and permanent injunction were consolidated for trial. After post-hearing briefing, the trial court entered its judgment permanently enjoining Seller from drawing on the letter of credit, enjoining Lawyers Title and the bank from paying out or drawing on it, and ordering Lawyers Title to return the letter of credit to Buyer. The trial court held that, under the duty of good faith and fair dealing imposed by Tennessee law, Seller was required to at least attempt to obtain a permit from the City of Franklin. The trial court further found that Seller had suffered no damages because it had neither attempted to sell nor develop the property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Herd v. American Security Ins. Co.
501 F. Supp. 2d 1240 (W.D. Missouri, 2007)
Lobo Painting, Inc. v. Lamb Construction Co.
231 S.W.3d 256 (Missouri Court of Appeals, 2007)
BHA Group Holding, Inc. v. Pendergast
173 S.W.3d 373 (Missouri Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
116 S.W.3d 653, 2003 Mo. App. LEXIS 1266, 2003 WL 21909568, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-co-custom-homes-of-tennessee-v-commerce-bank-na-moctapp-2003.