Jonas v. City of West Palm Beach

79 So. 438, 76 Fla. 66
CourtSupreme Court of Florida
DecidedJuly 2, 1918
StatusPublished
Cited by6 cases

This text of 79 So. 438 (Jonas v. City of West Palm Beach) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jonas v. City of West Palm Beach, 79 So. 438, 76 Fla. 66 (Fla. 1918).

Opinion

Ellis, J.

The Plaintiffs in Error brought an action in the Circuit Court of Palm Beach County against the City of West Palm Beach for damages for breach of a contract.

A demurrer to the declaration was sustained and the plaintiffs refusing to amend', final judgment was entered in favor of the defendant. To that judgment a writ of error was taken. The only question presented is the sufficiency of the declaration as against the attack made upon it by the demurrer.

The litigation gre'w out of a contract entered into between the parties for the construction of certain public works in the City of West Palm Beach.

The City through its Council decided to construct a seawall, certain additional street paving and extensions of the sewerage system and to that end caused plans and specifications to be prepared for such work and advertised for bids or proposals for its construction.

[68]*68The declaration alleges that the plaintiffs submitted a bid for the work to be done according to the plans and specifications which were attached to the declaration and made a part of it; that the contract was awarded to the plaintiffs and a contract was entered into between the plaintiffs and the defendant for the execution of the work and the furnishing- of the necessary material according ho 'the “conditions, covenants, 'stipulations, terms and provisions contained in said specifications” for a sum to be paid by the City equal to the aggregate cost of the work executed and labor, material and supplies furnished at the prices respectively named therefor in the plaintiffs’ proposal; that the plaintiffs entered upon the performance of the 'work and continued in the performance thereof until they were notified by the defendant to “cease and discontinue all work under the said contract and during the course of the performance of the said contract the time specified therein for completion thereof was waived by the defendant and to-wit, on January 20, 1916, the defendant notified the plaintiffs in writing to cease work and to cease to hold further possession of the ground or any part thereof upon which said' work or any part thereof was being-done, whereupon the plaintiffs ceased further performance of work under the said contract.” The declaration also contained the following- allegations:

“That the plaintiffs had substantially completed all of the said work, so far as the same related to the sanitary sewers and street paving, at the time of receiving the said notice, and the street paving had been completed to the satisfaction of the engineers specified in the said contract to approve the same, and the sanitary sewers had also been completed to the satisfaction of the said engineers except for a few minor objections that could [69]*69have been removed in a few days and at a cost not exceeding Three Hundred ($300.00) Dollars.
“That the aforesaid action of the defendant in wrongfully terminating the said contract was based upon a claim of the defendant that plaintiffs were in default in carrying on work on the seawall mentioned, but at the time of the said notice and termination of the said contract by defendant, plaintiffs were not in default in any respect in carrying on work on the said seawall, and the plaintiffs had so notified the defendant in writing, and the defendant was in default at the said' time in performing the said contract on its part, of which the plaintiffs had likewise notified the defendant in writing, such, default of the defendant being that the defendant had not, nor had its engineer, placed stakes at the locations of the keystone piles of the seawall to indicate the locations thereof as required by the said specifications, but had only placed such stakes at each alternate location, so that only one-half of the said stakes had been placed and none of these consecutively; that the said default was material in that the rock to which the keystone piles were required to be driven is a jagged, irregular rock with an uneven surface, having pinnacles, declivities, cavities and irregularities, so that within a space of a few inches there are variations of many feet in the depth of said rock, and' it was essential to have each particular location accurately determined before ascertaining the depth to rock at that particular location, and the staking and marking of the said locations was a condition precedent to be performed by the defendant, which it did not perform; and the plaintiffs at the time of the wrongful termination of the contract by the defendant had manufactured keystone piles exceeding in number the locations staked by the defendant, and [70]*70had manufactured sheet piles sufficient to cover more than three-fourths of the entire seawall, all of which were in accordance with the plans and specifications and approved by the engineer appointed in the said contract to approve the same, and the plaintiffs had provided the necessary materials for the entire completion of the said seawall, and in no respect were in default.”

Then follows allegations as to the plaintiffs damage consisting of several items, such as an amount due on account of retained percentage on work and material which had been approved and allowed by the engineer appointed “in the said contract”; an amount due for work done and materials on hand “not included in any estimate allowed by the negineer”; an amount due for extra work done and materials furnished “not included in the contract, but done, performed and furnished at the request of the defendant”; an amount due on account of materials rendered worthless by the defendant’s breach of the contract and on account of loss of time by laborers which was occasioned by the defendant who at various times in the course of the performance of the contract by the plaintiffs stopped and delayed the work.

The City of West Palm Beach by its counsel interposed a demurrer to the declaration and set forth therein the following “substantial matters of law to be argued

“1. Said declaration does not set forth facts which would entitle the plaintiff to recover from this defendant.
“2. Said declaration sets forth conclusions of law and of fact.
“3. Said declaration alleges that ‘during the course of the performance of the said contract the time specified therein for completion thereof was waived by the defendant,’ without setting forth the manner of such waiver, and said allegation is a mere conclusion.
[71]*71“1. Said declaration alleges that ‘the plaintiffs had substantially completed all of said work so far as the same related to the sanitary sewers and street paving at the time of receiving’ the notice to cease work under said contract, without showing of what such substantial performance consisted; and said allegation is a mere conclusion.
“5l Said declaration alleges that ‘the street paving had been completed to the satisfaction of the Engineer specified in the said contract to approve the same,’ but does not allege that the same had been approved by said Engineer; and said allegation is a mere conclusion.
“6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Destín Sav. Bank v. Summerhouse of FWB, Inc.
579 So. 2d 232 (District Court of Appeal of Florida, 1991)
Garner v. Margery Lane, Inc.
242 So. 2d 776 (District Court of Appeal of Florida, 1970)
Hansen v. Fitzhugh
217 So. 2d 590 (District Court of Appeal of Florida, 1969)
City of Miami v. Kellum
147 So. 2d 147 (District Court of Appeal of Florida, 1962)
Hanson v. Fidelity Mutual Benefit Corp.
13 A.2d 456 (Superior Court of Delaware, 1940)
Jones v. Dawson Cotton Oil Co.
90 So. 817 (Supreme Court of Florida, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
79 So. 438, 76 Fla. 66, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jonas-v-city-of-west-palm-beach-fla-1918.