Johnston v. Felker

459 S.W.2d 923, 1970 Tex. App. LEXIS 2215
CourtCourt of Appeals of Texas
DecidedOctober 22, 1970
Docket7172
StatusPublished
Cited by2 cases

This text of 459 S.W.2d 923 (Johnston v. Felker) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnston v. Felker, 459 S.W.2d 923, 1970 Tex. App. LEXIS 2215 (Tex. Ct. App. 1970).

Opinion

KEITH, Justice.

Fidelity and Deposit Company of Maryland (hereinafter “F&D”) appeals from a judgment in favor of Felker, plaintiff below, upon the terms of a bond executed by F&D under the provisions of the Harde-man Act, Article 5472d, V.A.C.S. 1 (hereinafter “Act”). Johnston was sued as an “original contractor” and F&D was joined as the surety upon the bond filed under the Act. Upon findings by the jury favorable to the plaintiff, judgment was entered against Johnston and F&D, jointly and severally, for the amount of the indebtedness and attorney’s fees. There is no complaint as to the amount of either award.

Johnston duly perfected his appeal from the judgment, but filed no brief herein. Felker’s motion to dismiss Johnston’s appeal was carried with the case but is now sustained. Rule 415. We will consider Johnston’s activities in the case only insofar as they bear upon the controversy remaining between F&D and Felker. Fitch v. International Harvester Company, 163 Tex. 221, 354 S.W.2d 372, 373 (1962).

We note, sua sponte, that the judgment makes no disposition of the cross-action of F&D against Johnston upon the provisions of the indemnity agreement contained in his application for such bond. Nor does the judgment dispose of F&D’s third party action against one Robert Dam-rel who stipulated upon the trial that he entered into a “Joint Venture Agreement” with Johnston and that he had executed an agreement to indemnify and hold F&D harmless from any and all claims and expenses arising out of the execution of the bond involved in this suit. We consider the judgment to be a final and appealable judgment under the rationale of North *925 East Independent School District v. Aldridge, 400 S.W.2d 893, 897-898 (Tex.Sup., 1966).

The primary question presented by this appeal is whether or not Johnston was an “original” contractor, as that term is used in the Act; or to state it conversely, was Felker a subcontractor on the job, entitled to the protection of the bond which Johnston filed with F&D as surety? The jury found that Felker furnished the labor and materials used on the job at the “instance and request of Johnston”, by virtue of the instrument dated January 12, 1966; the value of the labor and materials; the reasonable attorney’s fees; and, failed to find that Felker was an “original contractor.” 2 By appropriate “no-evidence” points, F&D challenges the findings upon which liability is predicated, and our review of the evidence will be under the rule announced in the much-cited case of In re King’s Estate, 150 Tex. 662, 244 S.W.2d 660 (1952).

Center Enterprises, Inc. (hereinafter “Center”), contemplating the construction of a shopping center in Groves, Texas, sought bids from general contractors for the construction of said shopping center, but rejected all of such bids, including that of Johnston. Then, as we understand the record, it procured bids from various individuals and companies as subcontractors for work on particular parts of the overall job. One such bid was from Johnston for the concrete work and one was from Felker for the electrical work. Felker’s bid of slightly more than $33,000.00 was submitted to Center on December 10, 1965, and accepted by Center upon the same date. Johnston and Felker were not acquainted and had had no prior dealings. Center’s interim financing was limited to $204,000.00 and the land upon which the building was to be placed was already burdened by a lien held by the financing bank.

Johnston, at the urging of Center and the agent of the permanent financing agency, then worked out an arrangement whereby he submitted a proposal to Center to construct the proposed structure for precisely the sum available. This proposal (attached hereto as an exhibit) was basically a recapitulation of the several bids of the subcontractors, such as Felker, with the totals rounded off to even thousands of dollars so as to fit the exact amount available from the bank.

The parties then met in the office of the agent of F&D, where the bond now in issue was executed with Johnston described therein as the general contractor and Johnston’s proposal attached thereto. This instrument was filed for record on February 15, 1966, after the start of the construction upon the project. Johnston steadfastly maintained throughout the litigation that he was simply a “coordinator” on the job and that Center, in fact, was its own general contractor, 3 but the jury disagreed.

Felker began the electrical work upon the project some few weeks or a month after the execution of the bond and at a time *926 when he had no agreement of any kind with Johnston. During the course of the construction, Felker approached Johnston and procured his signature upon the original bid which had been submitted to and accepted by Center on December 10, 1965. 4 Before the financiál collapse of the project, Felker had received several payments for his work (with 10% of each estimate being retained) in the form of checks signed by an officer of Center and Johnston.

By its first point, F&D asserts that the evidence establishes, as a matter of law, that Felker was an original contractor on the project; consequently, it is argued, the trial court erred in overruling its motion for judgment non obstante veredicto. In addition to the evidence which we have set out herein, we find in our record a certified copy of a mechanic’s and ma-terialman’s lien filed by Johnston for rec-ordation in the County Clerk’s office several months before the filing of the suit below. In this affidavit attempting to affix a lien, Johnston swore that Center was the “owner or reputed owner of said land” and that “A. R. Johnston is the original contractor on the job.” This sworn statement, made before the commencement of the litigation, was a judicial admission on the part of Johnston inconsistent with the position which he now asserts Gevinson v. Manhattan Construction Company of Oklahoma, 449 S.W.2d 458, 466 (Tex.Sup., 1970). Cf. Morrison Supply Co. v. M. W. Hamilton & Co., 411 S.W.2d 790, 793 (Tex.Civ.App.—Amarillo, 1967, no writ), and Trinity Universal Insurance Company v. Palmer, 412 S.W.2d 691, 694 (Tex.Civ.App. — San Antonio, 1967, error ref., n. r. e.). Point one is overruled.

By its third point, F&D contends that there was no evidence of a valid contract between Johnston and Center, consequently, it claims, F&D was not liable to Felker. The basis of the point is to be found in the first sentence of the “contract” between Johnston and Center, reproduced as an exhibit hereto.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tellez v. Tellez
531 S.W.2d 368 (Court of Appeals of Texas, 1975)
Fidelity & Deposit Company of Maryland v. Felker
469 S.W.2d 389 (Texas Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
459 S.W.2d 923, 1970 Tex. App. LEXIS 2215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnston-v-felker-texapp-1970.