Johnston Truck Rental Co. v. Fowler-McKee Co.

422 A.2d 164, 281 Pa. Super. 271, 1980 Pa. Super. LEXIS 3194
CourtSuperior Court of Pennsylvania
DecidedOctober 3, 1980
Docket50 and 84
StatusPublished
Cited by6 cases

This text of 422 A.2d 164 (Johnston Truck Rental Co. v. Fowler-McKee Co.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnston Truck Rental Co. v. Fowler-McKee Co., 422 A.2d 164, 281 Pa. Super. 271, 1980 Pa. Super. LEXIS 3194 (Pa. Ct. App. 1980).

Opinion

SPAETH, Judge:

These appeals arise from an order dismissing exceptions and entering judgment on a verdict entered by a judge sitting without a jury in an action in assumpsit.

The plaintiff below was Johnston Truck Rental Company, a trucking company; the defendants were Fowler-McKee Company, Inc., an excavating company; Graziano Construction Company, Inc., a general contractor; and Aetna Casualty and Surety Company, Graziano’s surety. Graziano was general contractor for the construction of the Professional Quadrangle at the University of Pittsburgh; Fowler-McKee was one of Graziano’s subcontractors, and was to do the excavating and backfill. Fowler-McKee and Johnston entered into a written agreement under which Johnston was to remove dirt from the site. The present action is to enforce that agreement.

The lower court entered a verdict for $22,521 with interest from June 1, 1974, in favor of Johnston, and against Fowler-McKee, Graziano, and Aetna. Since Fowler-McKee had agreed to indemnify Graziano, the court entered a verdict in the same amount, plus counsel fees and expenses, in favor of Graziano and against Fowler-McKee. Fowler-McKee had *274 filed three counterclaims against Johnston. On two of the counterclaims, the court entered a verdict in favor of Johnston; on the third, it entered a verdict of $450 in favor of Fowler-McKee.

Fowler-McKee, Graziano, and Aetna filed exceptions to the lower court’s findings. On December 19,1978, the lower court sustained the exceptions to the finding that Fowler-McKee had breached its contract with Johnston on June 1, 1974, and modified the finding and the verdict based on the finding to correct the date to May 28, 1974. The court dismissed all other exceptions. Fowler-McKee, Graziano, and Aetna have now appealed. 1

It is settled that “[w]hen a trial judge sits without a jury his findings of fact . .. have the weight of a jury verdict and cannot be disturbed on appeal unless they lack sufficient and competent evidential support. In such case, the party favored by the finding is entitled to have the evidence viewed in the light most favorable to him and to have all conflicts in the testimony resolved in his favor.” Darlington Brick and Clay Products, Inc. v. Aino, 225 Pa.Super. 186, 187, 310 A.2d 401, 402 (1973). See also Courts v. Campbell, 245 Pa.Super. 326, 369 A.2d 425 (1976); Krobot v. Ganzak, 194 Pa.Super. 49, 166 A.2d 311 (1960). So viewed, the evidence in this case may be summarized as follows.

Johnston began hauling material from the construction site on March 5, 1974. Under its agreement with Fowler-McKee, 2 Johnston was to remove an estimated 53,976 cubic *275 yards of “excess material”. It appears that Fowler-McKee had sent a copy of the site plan to an engineering firm, N.T. at 218, 7/12/77, and the 53,976 figure represented the firm’s estimate of the amount to be removed, plus an additional estimate made by two officers of Fowler-McKee. N.T. at 218, 7/12/77. In addition, Johnston was to “accept excess materials in excess of the 53,976 cubic yards estimated if required by [Fowler-McKee] in order to complete its contract obligations,” and was to ensure that “mud, dirt or other such materials [were] not deposited in or about the public roadways leading from the excavation site to the disposal site.” Fowler-McKee agreed to pay Johnston $1.15 for each cubic yard of excess material removed. The agreement was to “continue in force until such time as the site preparations contemplated [were] complete and all excess materials [were] removed and hauled to the disposal site.”

On March 30, 1974, Johnston billed Fowler-McKee for $28,869 for work performed during March. Although the bill contained no estimate of the amount of excess material removed, Fowler-McKee paid it without questioning Johnston. On May 1, Johnston billed Fowler-McKee for $26,247 for work performed during April. Again, although the bill contained no estimate of the amount of excess material removed, Fowler-McKee paid it without questioning Johnston. On May 20, Fowler-McKee informed Johnston that the removal of excess material was, for the time being, complete, but that Johnston would be required to return to the site. 3 On May 21, Johnston and the independent truckers who had worked for it left the site. Soon after May 21, Johnston sold its small fleet of trucks. N.T. at 30, 7/12/77.

*276 On May 28, Johnston submitted a bill to Fowler-McKee for $19,505 as the balance owing at that point. The bill contained a total yardage figure equal to the estimate contained in the parties’ agreement, i.e., 53,976 cubic yards, plus an extra 6,000 cubic yards 4 reflecting Johnston’s removal of a muck pile that had not been included in the engineering firm’s original estimate. The balance due was calculated on the basis of a rate of $1.25 per. cubic yard, instead of $1.15 per yard, because Johnston’s bookkeeper, Mary Lau, thought there had been a verbal agreement between Johnston and Fowler-McKee to raise the price. N.T. at 184, 7/12/79. Fowler-McKee paid Johnston $15,000, which was all Fowler-McKee had at that point. N.T. at 25, 7/12/77.

During June, Fowler-McKee tried several times to get Johnston to return to the site. N.T. 279, 7/12/77. Johnston promised to “look the situation over,” N.T. at 280, 7/12/77, but never did, N.T. at 280, 7/12/77, and Fowler-McKee finally hired other truckers to remove the additional excess material. Fowler-McKee’s bookkeeper, Mary Cummings, testified that the expense of paying these truckers, who were employed at an hourly rate, was approximately $43,-000. N.T. at 386, 7/12/77.

On July 5, Johnston billed Fowler-McKee for an amount which was adjusted downward to $22,521 at the time of trial. The bill, which Fowler-McKee refused to pay, reflected Johnston’s claim that it had hauled a total of 83,206 cubic yards of excess material from the site. N.T. at 402, 7/12/77.

At trial, Johnston’s bookkeeper testified that she billed Fowler-McKee on the basis of the number of trucks used in a given period, and that she assumed that each tandem truck used on the job held 14 cubic yards of excess material, and each tri-axle truck, 18. She said that Johnston instructed *277 her to use these figures, N.T. at 170, 7/12/77, and several witnesses attested to their plausibility, N.T. at 85, 7/12/77; N.T. at 116, 7/12/77; N.T. 135, 7/12/77. Nevertheless, Fowler-McKee vigorously disputed the figures, suggesting that it was more likely that each tandem held 8 to 10 cubic yards, and each tri-axle, 12. N.T. at 199, 7/12/77; N.T. at 226, 7/12/77. One of Fowler-McKee’s witnesses was William Marlowe, who had made the estimate of yardage upon which the parties’ agreement was based. He testified that he regarded Johnston’s estimate as a “physical impossibility.” N.T. at 370, 7/12/77.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Linnet v. Hitchcock
471 A.2d 537 (Supreme Court of Pennsylvania, 1984)
Commonwealth v. Nicholson
454 A.2d 581 (Superior Court of Pennsylvania, 1982)
Watt v. East End Car Wash
28 Pa. D. & C.3d 208 (Lancaster County Court of Common Pleas, 1982)
Zvonik v. Zvonik
435 A.2d 1236 (Superior Court of Pennsylvania, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
422 A.2d 164, 281 Pa. Super. 271, 1980 Pa. Super. LEXIS 3194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnston-truck-rental-co-v-fowler-mckee-co-pasuperct-1980.