Johnson v. Utah-Idaho Concrete Pipe Co.

223 P.2d 418, 118 Utah 552, 1950 Utah LEXIS 198
CourtUtah Supreme Court
DecidedOctober 25, 1950
DocketNo. 7483
StatusPublished
Cited by2 cases

This text of 223 P.2d 418 (Johnson v. Utah-Idaho Concrete Pipe Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. Utah-Idaho Concrete Pipe Co., 223 P.2d 418, 118 Utah 552, 1950 Utah LEXIS 198 (Utah 1950).

Opinions

WADE, Justice.

This suit was brought by Henry B. Johnson and Rush C. Budge, on behalf of themselves and all other taxpayers of Logan City, Utah, to declare null and void an award and contract given to the Utah-Idaho Concrete Pipe Company by Logan City to replace a culinary water supply pipe line in Logan Canyon. From a judgment sustaining the award and contract but limiting the amount to be paid thereunder to the preliminary estimate of cost made by the city engineer, the Utah-Idaho Concrete Pipe Co. appeals. We shall hereinafter refer to the plaintiffs in the suit below as the respondents and the Utah-Idaho Pipe Co. as the appellant.

The facts are not in dispute. Early in 1949, Logan City determined that it would be necessary to make improvements in its water supply system. It contemplated (a) an additional reservoir for Logan City Culinary Water supply, (b) a replacement section of a portion of the hydroplant water supply line for the Logan City Power Plant, and (c) a replacement of the upper section of the culinary water supply pipe line in Logan Canyon. The contract awarded for this last item is the subject matter of this suit. Items (a) and (b) are not being questioned here.

The commissioners of Logan City having arrived at the conclusion that the above improvements were necessary, and it being apparent that a bond issue would have to be floated to pay for these, requested the city engineer to make an estimate of the costs of such improvements. The city engineer after a hasty survey of the situation estimated the cost of item (c) would be $257,000.00. The commission then passed an ordinance calling for a special election to submit to the voters the question of incurring a bonded indebtedness to pay for all the proposed improvements. At the special election held in pursuance to this [555]*555ordinance the vote was favorable for the incurring of such expenditures. The commission then employed a firm of private civil engineers who furnished the commission with plans and specifications for the proposed improvements, whereupon the city advertised for bids, requiring that a separate bid be made for the culinary water supply system. Five bids for this system were received. On July 6, the same day on which the bids were opened, the civil engineering firm employed, by the city, filed its estimate of the cost of construction of the culinary water line with the City Recorder of Logan City.

The bids were evaluated on a formula based on the annual cost to the city, using the sinking fund method, which cost was determined by computing the annual amount necessary to replace the improvement at the end of its economic life, the determination of the annual amount was based on the price stated in the proposal and the computation of an annual interest charge on this price. The sum of the sinking fund and interest was assumed to be the annual cost. The life of the various materials recommended to be used in the project were given the following rating for the purpose of determining the length of time such materials would be used before replacement would be necessary: Cast Iron, 100 years; Centrifugal Concrete, 100 years; Asbestos Cement, 100 years; and Steel, 50 years. After the bids submitted had been evaluated on the above formula, the commission had two bids which it had to consider seriously before the awarding of the contract. One was by the Utah-Idaho Concrete Pipe Company in the amount of $266,347.60, proposing to use centrifugal concrete pipe and the other by A. H. Palmer and Sons, in the amount of $233,228.50, using steel and evaluated under this formula-as being $266,041.00. The commission decided that it would be more advantageous to use centrifugal concrete pipe and awarded the contract to the Utah-Idaho Concrete Pipe Co. The Palmer bid had failed to- comply with a [556]*556specification that the work be completed within 180 calendar days. Its bid stated that the work would be completed in 400 days. The Palmer Co. informed some of ,the commissioners that this was an error due to a misunderstanding by them of the specifications and offered to amend their bid to read 180 calendar days. This the commission refused to allow them to do, although a mistake in the amount of about a thousand dollars in the bid of the Utah-Idaho Concrete Pipe Co. on an item was allowed to be amended.

Almost immediately upon the awarding of the contract to it, the Utah-Idaho Concrete Pipe Co. commenced work on the project and expended considerable sums of money on it before this suit was commenced in the latter part of July, 1949.

Respondents’ complaint alleged that the contract had been awarded fraudulently, arbritrarily and in bad faith, and that although the engineer’s estimate for the performance of the work called for in Item (c) was $257,000, and the bid accepted was in excess of this sum, the commission did not reject all bids and advertise anew. The court found that the city engineer had estimated the cost of Item (c) as $257,000 and that the city had been authorized at the special election to create a bonded indebtedness for the improvements sought in conformity with the estimates; that defendants Logan City and its officers did not act fraudlently or in bad faith, nor were they guilty of arbitrary or capricious action in awarding the contract to appellant, and appellant had in good faith already commenced to work on the project and had expended considerable sums on it; that the civil engineering firm employed by the city had filed a revised estimate of costs which raised the estimated costs over and above any of the bids submitted, but that this revised estimate was not filed in time for inspection by any of the bidders and taxpayers. It concluded from these facts that Logan City and its officers had failed to comply with the provisions of [557]*557Sec. 15 — 7—20, U. C. A. 1943, when it awarded the contract to appellant because all bids received by it were in excess of the estimated cost of the proposed improvement, which was $257,000 and not the purported revised estimate which was filed too late for consideration by any persons. However, in view of the fact that the work on the project had already been started in good faith by appellant and since Palmer & Sons, the only other bidder, could not perform the work in the time required, the court was of the opinion that the equity of the situation required that the contract should not be declared void in toto, but that it should be modified so as to provide that the full price should not exceed the price of the estimate, to-wit, $257,000.00.

Appellant contends that the court erred in decreeing a modification of the contract and in concluding that the estimate filed by the city engineer was the only estimate upon which the city could act in conforming with the law and the estimate filed by the civil engineers could not have been considered by the city because it was filed too late to be properly considered by any persons. The respondents in their cross appeal claim the court erred in finding that only two bids were made for the project in question here, and in concluding that the contract awarded was not totally void.

The evidence was uncontradicted that there were five bids entered for the work outlined in Item (c) and the court therefore erred in finding that there were only two bids. However, that error is not important. The determinative question is whether the city complied with the provisions of Sec. 15 — 7—20, U. C. A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Voogd v. JOINT DRAIN. DIST., KOSSUTH & WINNEBAGO COS.
188 N.W.2d 387 (Supreme Court of Iowa, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
223 P.2d 418, 118 Utah 552, 1950 Utah LEXIS 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-utah-idaho-concrete-pipe-co-utah-1950.