Johnson v. Reconstruction Finance Corp.

94 F. Supp. 214, 1950 U.S. Dist. LEXIS 2095
CourtDistrict Court, E.D. Tennessee
DecidedSeptember 2, 1950
DocketCiv. A. No. 1574
StatusPublished
Cited by2 cases

This text of 94 F. Supp. 214 (Johnson v. Reconstruction Finance Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. Reconstruction Finance Corp., 94 F. Supp. 214, 1950 U.S. Dist. LEXIS 2095 (E.D. Tenn. 1950).

Opinion

DARR, Chief Judge.

The defendant has interposed a motion to dismiss the complaint. The factual basis of the decision is upon the statements in the complaint and the admissions made by the plaintiff.

Plaintiff sues to recover from the defendant under Section 13 of the Contract Settlement Act of 1944, Public Law 395, 58 Stat. 649, 41 U.S.C.A. § 101 et seq. (herein called the Act), the sum of $136,878.52, claimed as the fair dollar settlement for the cancellation of a war contract between plaintiff and Metals Reserve Company, an authorized subsidiary of the defendant. The items composing the claim are not specified, except by stating that $116,878.52 is the amount of plaintiff’s unrecovered cost incident to the contract, and that $20,000 is amount claimed foi profits.

The contract was executed September 2, 1942 and called for a sale by the plaintiff and purchase by defendant of 1000 long tons of black manganese oxide ore, to be derived from a designated property in Bradley County, Tennessee. Delivery of the entire amount of ore was required to be completed “no' later than 4 months from the date of this contract”.

A provision in the contract was “Buyer may cancel all or any uncompleted portions of this contract if seller fails to deliver acceptable ore in accordance with * * then follows a specified schedule of deliveries during the four months period.

A further provision was that “notwithstanding any other provisions hereof, buyer in its sole discretion may cancel any or all incompleted portions of this contract if the entire contract quantity has not been delivered by February 15, 1943.”

During the life of the contract the plaintiff delivered only 70,000 pounds of ore, for which he was paid the sum of $916.48. The dates of delivery are not shown.

The contract was amended on February 22, 1943, at plaintiff’s request to extend the time of delivery to June 30, 1943, but no further deliveries are claimed.

On September 7, 1943, the defendant wrote the following letter bo plaintiff:

“Under the captioned contract dated September 2, 1942, covering the proposed purchase by this Company from you of 1,000 tons of manganese ore, the entire quantity was to be delivered no later than June 30, 1943.

“We shall appreciate your advising us promptly the reasons for your failure to complete deliveries within the specified time and whether or not you contemplate making further shipments. Unless we hear from you by September 25, 1943, in this regard we shall presume that you have abandoned the project and shall take such steps as may be necessary to cancel the contract.”

[216]*216•Not having heard from plaintiff within the time requested, defendant wrote the plaintiff on October 8, 1943, the following letter as notice of cancellation:

“Under the captioned contract dated September 2, 1942, covering the proposed purchase by this Company from you of 1,000 long tons of manganese ore, delivery was to be made by July 31, 1943.

“Because of your failure to complete deliveries within the time required the captioned contract is hereby cancelled as of the undelivered portion thereof.

“Kindly acknowledge receipt of this notice on the enclosed copy of this letter and return to this office.”

Thereafter, on October 17, 1943, plaintiff wrote the defendant that he would be ready to start shipping ore the first of the month, and that if the Government wanted the manganese ore, he would “be glad to have the contract renewed”.

The contract, however, was not renewed and nothing further appears to have been done until December 29, 1949, when the plaintiff submitted to defendant a claim “making demand for the reformation of his contract and the award of fair compensation” under the provisions of the Contract Settlement Act of 1944.

In denying the claim the defendant, after reciting the several steps taken in the case — the extension of time granted at plaintiff’s request, the plaintiff’s apparent indifference as to performance, his failure to answer inquiries implying an abandonment of the contract — the defendant concluded: “It is clear from the foregoing that this contract was terminated because of your default in performance, and consequently you do not have a termination claim under the Contract Settlement Act of 1944, which excludes contracts terminated for default. Your claim, therefore, is hereby denied in its entirety.” Thereafter on June 7, 1950, this action was begun.

Defendant’s motion to dismiss is upon these grounds:

1. The complaint fails to state a cause of action.

2. The action is barred by the six year statute of limitations of Tennessee.

3 and 4. The complaint shows on its face that plaintiff was in default in the performance of the contract, that the contract by its terms was subject to cancellation and was pursuant thereto canceled for defendant’s default, and that plaintiff is entitled to no relief under the Act of Congress relied on because the contract was not canceled or terminated by the government for its convenience or at its option, but for plaintiff’s default.

5. Plaintiff has been guilty of such delay and laches in the prosecution of his claim that he is barred or estopped now to assert the same.

6. The complaint does not aver any basis on which plaintiff’s claim of $136,-'878.52 can be supported; that the averments of the amount expended and the profit claimed are only bare assertions which have no reasonable relation to the cost of production as required by the Congressional Act.

1. The first ground of the motion is general and will be considered in connection with a discussion of the others.

2. The second ground of the motion to dismiss is overruled. The Tennessee Statute of Limitations relied on, Williams Code, section 8600, requires actions of this type to be commenced “within six years after the cause of action accrued.” Under sub-section (b) of section 13 of the Act, the action would not accrue until findings on and denial of the claim had been made by the contracting agency. The date of denial and findings was March 6, 1950, and the six year limitation is not applicable.

3 and 4. The third and fourth grounds of the motion to dismiss raise essentially the same question, vis., the propriety and legality of the defendant’s declining the plaintiff’s claim on the ground of plaintiff’s default under the contract.

There is no dispute (1) that the plaintiff had breached the contract when it was canceled; (2) that the contract contained a clear provision for cancellation for default; (3) that the Act under which the suit is brought by section 3(d) excepts [217]*217from the provisions of the Act contracts terminated for default of the contractor; and (4) that plaintiff’s contract was on October 8, 1943 terminated by the defendant upon the claim of plaintiff’s default.

The gravamen of this suit depends upon the interpretation of the word “default”. The plaintiff insists that the word as used in the Act was intended to, and should be interpreted as “gross or wilful default”. Such default, plaintiff says is not shown in this case and in the absence of gross or wilful default, the plaintiff claims he is entitled to a “fair settlement” for his terminated contract, under the provisions of the Act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glade Mountain Corp. v. Reconstruction Finance Corp.
104 F. Supp. 695 (D. New Jersey, 1952)
Haberle v. Reconstruction Finance Corp.
104 F. Supp. 636 (District of Columbia, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
94 F. Supp. 214, 1950 U.S. Dist. LEXIS 2095, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-reconstruction-finance-corp-tned-1950.