Johnson v. Norcross Bros.
This text of 95 N.E. 833 (Johnson v. Norcross Bros.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
This was an action upon a written contract by which the plaintiff, the party of the second part, agreed with [446]*446the defendant, the party of the first part, to provide all the-materials and do all the work of “ plumbing, gas-piping, and ice water plant piping ” in a certain building, then being erected by the defendant for the owner, as set forth and explained in certain drawings and specifications prepared by the architects. The case was sent to an auditor
Among the provisions of the contract were the following: “ In case any particular shall be deficient, or not clearly expressed in said specifications and drawings, the said party of the second part will apply to the said first party for additional drawings and explanations, and will carry out the general design, as directed by' the said first party, in a thorough manner as part of the contract. ... It shall be lawful for said party of the first part at all times to direct, in writing, any additions to or deviations from the drawings and specifications aforesaid, without in any other respect or particular varying this agreement or impairing the force thereof; and in case of any such addition or deviation so directed in writing, such further time shall be allowed for the completion of said work as the architect shall decide to be reasonable, and such sums of money shall be added to or subtracted from the amount of the consideration hereinafter agreed to be paid, as the increase or diminution in the amount of work and materials thereby occasioned shall be fairly worth. And it is expressly agreed that no alterations or additions are to be paid for unless so directed in writing.” And near the end of the contract is the general provision that “ the general contractor [the Nor cross Brothers Company] will pay for no extra work or material unless ordered in writing.”
The purpose of the provision that the defendant shall not be held to pay anything either for changes, additions or other extra [447]*447work unless ordered in writing is plain. The provision manifestly was intended to prevent any future controversy likely to arise as to the liability of the general contractor for work so done, and it is a useful and reasonable provision.
[447]*447The evidence offered
The plaintiff made twenty-eight requests for findings of fact. As to these the trial judge says in his memorandum that “ so far as the plaintiff’s requests for findings of fact are consistent with the findings of the auditor in his report I give them. So far as they are inconsistent therewith I deny them.” In other words the judge, giving due weight to the report of the auditor and to the other evidence, came to the conclusion that the auditor was right in his findings and adopted them. It cannot be said that in this there was any error in law. The evidence being conflicting, his decision could not be said to be wrong in law. Nor do we understand that the plaintiff has taken any exceptions to this action of the judge.
The plaintiff submitted seventeen rulings, some of which were given and some refused, the latter being those numbered one, five, eight, ten, and twelve to seventeen, both inclusive.
Hardy, J.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
95 N.E. 833, 209 Mass. 445, 1911 Mass. LEXIS 968, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-norcross-bros-mass-1911.