Johnson v. Minneapolis, St. Paul & Sault Ste. Marie Railway Co.

103 N.W. 594, 140 Mich. 292, 1905 Mich. LEXIS 562
CourtMichigan Supreme Court
DecidedMay 22, 1905
DocketDocket No. 54
StatusPublished
Cited by2 cases

This text of 103 N.W. 594 (Johnson v. Minneapolis, St. Paul & Sault Ste. Marie Railway Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. Minneapolis, St. Paul & Sault Ste. Marie Railway Co., 103 N.W. 594, 140 Mich. 292, 1905 Mich. LEXIS 562 (Mich. 1905).

Opinion

Ostrander, J.

Plaintiff was an employe of the White Marble Lime Company at Manistique, and had been for a period of six weeks. The sawmill of the White Marble Lime Company is situated north of the main line of defendant, and to the north of the mill; and parallel with its ,northern side, upon the land of the mill company, are two Spur tracks, to secure which this1 company had, by agreement with defendant, graded the land and furnished ties, the railroad company furnishing the steel. No one could [293]*293use the tracks without permission of the White Marble Lime Company, but the defendant had permission to store cars there when the mill was not in operation. The White Marble Lime Company also had property south of the main line of defendant, and the arrangement between the two companies included the switching of cars from the site north of the main line to the yard on the south side of the main line, as well as to the main line of defendant’s road. Directly to the west of the sawmill is a river, and the two spur tracks mentioned run to the bank of the river, upon which, at the end of the tracks, bumpers or stopping posts are built. These spur tracks are about 500 feet long, and run nearly in straight lines from the switch to the river. To summon the switch engine and its crew, the engineer or foreman of the mill blew the mill whistle, giving one hour’s notice; and it was the rule and custom for switching to be done on these spur tracks twice a day, in the forenoon and in the afternoon. Upon the appearance of the switch engine and its crew in the yard, the foreman of the mill directed what cars were to be taken out, and the disposition to be made of empty cars or others ■coming in. In pushing in cars, it frequently occurred that the locomotive would bring them to the switch, or a little beyond it, and, giving them sufficient momentum, uncouple them and let them run in. It was understood by the men employed there, including plaintiff, that when switching began in the yard the work of those employed in loading and unloading cars was to cease until the work of moving the cars had been completed. It was the rule of the place that the men should stop work when switching began. This rule and this custom were known to the (defendant and its employés. Upon such occasions notice was given to the men at work in and about the cars, ■sometimes by the mill foreman, sometimes by the train ■crew, and when the work of switching was completed the men were told to go to work again. Plaintiff was asked this question:

[294]*294“ Q. You did that every day, while you were working outside during those six weeks ? Isn’t that the way ?
“A. Yes. * * * After the foreman told us that the switch was coming we were in the habit of looking out for ourselves hntil the engine had taken out the loads and put back the empties. We did that every day while I was working outside during the six weeks I worked there.”

Plaintiff was injured on April 80, 1903. At the time of the accident there were cars on both the north and south spurs. A flat car loaded with shingle bolts, with posts on top of them, had been placed on the south spur track, its west end being almost directly against the bumper, or stopping post. Next to it to the east was a flat car, on which also were shingle bolts and posts; the shingle bolts being piled two or three feet high on each car. These posts had been unloaded, taken to the mill, trimmed, and reloaded into a box car. East of this second loaded flat car were other cars — one of them a box car. From four to six feet of the shingle bolts had been removed from the car next to the river by throwing them over the bumper and into the river. The little space between the end of the car and the bumper, interfering with this work, in which plaintiff and others or another had been engaged, the men concluded to place a skid from the end of the car over the bumper, so that the bolts could be more easily put into the river. A skid had been found and put in. position, to be nailed to the car. Plaintiff went to the mill to get nails, brought them back, walking down between the two spur tracks, handed one or more of them to' the man on the car, and, in passing him one of them, stepped around to the end of the car, between it and the bumper, or the timber nailed across the bumper, passed the nail to the man on the car, put his hands on the car, and was about to mount it, when some cars pushed in upon the spur by the switch engine struck the cars east of the one on which plaintiff had been at work with sufficient force to pinch him between the end of the car and the bumping post, causing the inj ury complained of.

[295]*295The contention of counsel rests upon very few facts— indeed, may be said to turn upon a single undisputed fact, and the value of that fact in the case. It is undisputed that the only business to be done by the switch engine and its crew in this yard was to move out cars already there, and to move in other cars. It had no other business in the yard. It is undisputed that within a period of time not longer than 10 minutes prior to the accident the switch engine was in the yard at work, and that it pulled out cars which were upon the south track. It is undisputed that plaintiff knew that the afternoon switching had begun. He says:

‘ ‘ I was just handing him the second spike, and I stepped one foot on the rail to get on the flat car when I was caught. I didn’t see the engine. I did not know it was. coming. * * * I knew the engine had been there ten or fifteen minutes before I got hurt. I saw the cars move. I was standing beside the car when the engine first came in. I was looking for a skid at that time. It was snowing, and the smoke from the smokestack came down to the ground between the car, and it was pretty hard to see ahead.”

It was agreed by counsel that the record of the United States weather bureau kept at Manistique on that day showed the prevailing wind was from the north, and that there was a slight fall of snow, not sufficient to be measured. Plaintiff further testified:

“When I knew there was switching, I stopped work. The engine came in every day. We were loading cars every day, and the loaded cars were taken out, and empties put in. When the engine came in after loads, I knew it would afterwards put in the empties. I knew that if it took out loads it would have to put empties back. All the loading would have to stop until the switching was done. I knew the engine came in ten or fifteen minutes before I was hurt. The smoke was coming down from the smokestack, and it was snowing so I couldn’t see up the track when I was hurt. I didn’t know the engine was coming back when I got hurt. I knew when the engine came in ten minutes before I was hurt.
[296]*296“The engine generally came in once in the morning and once in the afternoon. I was in the postmill when it came in the forenoon. I knew it was there ten minutes before I was hurt. I did not know it had not been there before that time. The first I knew of its being there that afternoon was ten minutes before I got hurt. ”

No notice had been given to the mentó resume work. Counsel for plaintiff say that the evidence shows that no whistle was blown by the switch engine on the afternoon in question, that there is a conflict of testimony concerning the fact of ringing the locomotive bell, and that there is a dispute as to whether the foreman gave the men warning of the presence of the switch engine in the yard.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Township of Pinconning v. Detroit & MacKinac Railway Co.
213 N.W. 156 (Michigan Supreme Court, 1927)
Fitzpatrick v. Michigan Central Railroad
112 N.W. 915 (Michigan Supreme Court, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
103 N.W. 594, 140 Mich. 292, 1905 Mich. LEXIS 562, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-minneapolis-st-paul-sault-ste-marie-railway-co-mich-1905.