Johnson v. Mercer

128 F.2d 357, 1942 U.S. App. LEXIS 4733
CourtCourt of Appeals for the Fifth Circuit
DecidedMay 29, 1942
DocketNo. 9678
StatusPublished

This text of 128 F.2d 357 (Johnson v. Mercer) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. Mercer, 128 F.2d 357, 1942 U.S. App. LEXIS 4733 (5th Cir. 1942).

Opinion

McCORD; Circuit Judge.

W. G. Gray, acting for himself and W. M. Redditt, secured an oil and gas lease from the Trustees of Pickering Lumber Company. The lease covered several tracts of land located in Texas, .and was for a primary term of three years with provision for continuance. It was provided that the lease was to terminate if drilling operations were not begun within sixty days, and that until such time as oil, gas, or other minerals were discovered in paying quantities drilling operations were to be conducted continuously, with not more than sixty days elapsing between the abandonment or cessation of drilling of one well and the commencement of another.

Gray and Redditt drilled a well which failed to produce, and then commenced the drilling of a second well. When drilling of the second well had progressed to the depth of 4,100 feet, Gray ordered the drilling contractors to cease drilling and plug the well back to 2,945 feet for the purpose of testing the sands. The well failed to produce at this depth.

Gray and Redditt entered into contract for the sale of their lease to John G. Pundt. Pundt agreed to pay $2,500 in cash as a down payment, $5,000 ten days later, and $57,500 upon delivery of proper assignments when and if title to the property was approved by his attorney. A second contract entered into by the -parties contemporaneously with the lease sale contract provided that at his own expense Pundt was to complete Gray’s and Redditt’s second well which had been plugged back. The contracts provided that if the attorney failed to approve the titles, Pundt was to recover his cash advances and drilling and development costs out of one-half of the oil, gas, distillate, and other minerals which might be produced from the property.

Mercer and Johnson, the drilling contractors who had been drilling the second well for .Gray and Redditt, had not received pay for their work, and they refused to remove their rig from the hole and allow Pundt to complete the well. Drilling operations on the lease were at a standstill, and the sixty day limit allowed by the Pickering lease was running out. Time was of the essence, and by agreement of the parties Pundt began the drilling of a new well instead of deepening the uncompleted well which was under the domination of the original drilling contractors. In drilling the new well and developing the lease Pundt expended large sums of money, and various contracts were entered into for work which gave rise to additional obligations.

Mercer and Johnson had not been paid for their drilling work on the second well, so they filed a lien claim and filed, suit against Gray and Redditt in the Texas State Court. The suit was removed to the Federal Court and a receiver was appointed to take charge of the properties. Gray filed his petition reciting the fact that ma-ny claims and obligations .had arisen out of transactions involving the Pickering lease and its development. He prayed that all interested persons be made parties to the suit so that their respective rights and priorities might be established in one pro-, ceeding. Thereafter, by interventions and cross-actions, other parties, including the appellants John G. Pundt and Victor S. Johnson, were brought into the proceedings. Twenty-six distinct claims were thus brought before the court for adjudication.

The court appointed a master who, after conducting hearings for fourteen days, made findings of fact and conclusions of law and made his report to the court. Objections and exceptions to the report were filed. The court considered the objections and exceptions, filed an opinion, and approved all findings and conclusions of the master, except the one denying lien rights to Mid-Continent Supply Company and other creditors similarly situated. Judgment settling all claims was then entered, and of the many parties involved only Victor S. Johnson and John G. Pundt appealed. Claims were allowed against Pundt and Johnson, jointly and severally, as follows: Cameron Iron Works, $2,395.-58Halliburton Oil Well Cementing Company, $1,884.60; M. M. Kinley, $1,000; National Tank Company, $1,819.14; The Pace Corporation, $835.85; V. B. Stone, $1,500; Mid-Continent Supply Company, $31,196.51; and C. M. Cope Drilling Co., $11,384.60.

[359]*359Both Pundt and Johnson attack several of the awards as being not supported by the pleadings of the parties. Rules of pleading obtaining in the State Courts are not controlling, and we hold that under the liberal rules of procedure applicable to all actions in Federal Courts, the complaints, cross-complaints, answers, admissions, and the evidence in the case sufficiently raised and brought to issue all matters which were finally adjudicated by the trial court.

The record is voluminous, containing more than 1800 printed pages, much of it dealing with matters no longer in controversy. The evidence is in sharp disagreement on many issues and we shall not attempt to review it in detail. Assignments of error not discussed herein are held to be without merit.

The appellant Victor S. Johnson complains of the finding of the master that he and Pundt were partners in the lease development project, and that he “became liable therewith to the same extent as Pundt.” It is contended that Johnson was merely lending money to Pundt for use in connection with developing the project, and that he was nothing more than an unsecured creditor of Pundt. Both Pundt and Johnson vigorously deny that a partnership ever existed between them. Although the evidence is probably not sufficient to clearly establish a partnership relationship between Pundt and Johnson, we think it was sufficient to establish Johnson’s liability on the claims entered fn judgment against him. There is evidence that Pundt represented that Johnson was his associate in the undertaking and was financing the operations; that Johnson participated in conferences relating to the development of the lease; and that he was vitally interested in the development, and was allowing himself to be held out as the moving financial spirit of the enterprise. The evidence was sufficient to show an association and relationship in the project sufficient to support the judgment entered against Johnson on the above named claims.

As to the $31,196.51 supply account claim of Mid-Continent Supply Company, Victor S. Johnson filed a cross-complaint against Pundt alleging that he had guaranteed the account at Pundt’s request and upon the distinct understanding that Pundt would personally pay the full amount due Mid-Continent, but that Pundt had failed to livr. up to this agreement. Johnson prayed that if Mid-Continent secured judgment against him, that he be given a judgment over against Pundt and subrogation to Mid-Continent’s lien. Johnson thereafter admitted liability to Mid-Continent on its claim, a severance was had, and summary judgment for the full amount of the claim plus interest was entered against him. Pundt made no contest of Johnson’s cross-claim against him on the Mid-Continent transaction, and on the trial he testified that Johnson had guaranteed the account at his request and that he expected this amount to be charged back to him. Certainly, as between the parties Johnson and Pundt, the agreement as to the Mid-Continent account was valid. The claim being admitted, judgment should have been allowed to Johnson over against Pundt with subrogation as prayed in the cross-complaint. The court erred in denying this claim.

Pundt paid Gray and Redditt in excess of nine thousand dollars on the contract purchase price of the oil and gas lease, and actually expended approximately twenty thousand dollars more in developing and protecting the lease.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
128 F.2d 357, 1942 U.S. App. LEXIS 4733, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-mercer-ca5-1942.