Johnson v. Maryland Casualty Co.

280 S.W.2d 398, 225 Ark. 224, 1955 Ark. LEXIS 571
CourtSupreme Court of Arkansas
DecidedJune 20, 1955
Docket5-714
StatusPublished
Cited by1 cases

This text of 280 S.W.2d 398 (Johnson v. Maryland Casualty Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. Maryland Casualty Co., 280 S.W.2d 398, 225 Ark. 224, 1955 Ark. LEXIS 571 (Ark. 1955).

Opinion

Minor W. Millwee, Justice.

In 1951 the E. V. Bird Construction Company, hereinafter called “Bird,” entered into a contract with the University of Arkansas for the construction of the Arkansas Law School Building at the university. On October 4, 1951, Bird as principal and Maryland Casualty Company, hereinafter called “Maryland,” as surety executed the standard “Statutory Performance Bond” whereby they became obligated to pay all indebtedness for labor and materials furnished in the construction or repair of said building.

Shortly after execution of the bond, Maryland ascertained that Bird’s financial condition was such that Maryland would be unable to reinsure part of its obligation under the bond as it desired to do. The manager of Maryland’s Arkansas office in Little Rock directed W. R. McNair, President of Cravens and Company, the local agent of Maryland at Fayetteville, Arkansas, to endeavor to have Bird increase its capital structure in the approximate sum of $20,000. McNair communicated the request to Floid Bird, son of Mrs. E. Y. Bird, and one of Bird’s managers at the time. There were some negotiations with Mrs. Bird relative to procurement of additional capital by the assignment of certain life insurance annuities by her, but this was not done. After an unsuccessful attempt to secure additional capital from another uncle, Floid Bird sought the assistance of the appellant, L. E. Johnson. Appellant was shown some of the letters from Maryland’s Little Rock manager to McNair which the latter had furnished to Floid Bird. These letters emphasized the necessity of Bird securing additional operating capital and suggested that the furnishers of same execute a “Subordinate Loan Contract” in which Maryland’s priority over all other claimants in the event of a default under the construction contract would be recognized.

On November 6, 1951, appellant advanced $5,000 to Bird and the latter executed its demand note to appellant for the advancement. The next day, November 7, 1951, appellant wrote Maryland at Little Rock as follows:

“About twenty-five years ago E. Y. Bird let me have money to get my start. Of course this was repaid years ago, but I will always feel grateful for his help, therefore, I loaned his two sons, Floyd and Larry, $5,000.00 on their note and stand ready to back them to a limit of $20,000.00.”

Sometime later appellant had a telephone conversation with the manager of Maryland’s Little Rock office in which the latter suggested the execution of some kind of agreement by appellant that he would furnish the balance of the money to Bird and also a financial statement.

On November 28, 1951, appellant entered into a written “Investment Agreement” with Bird in which he agreed to advance a total of $20,000 from time to time, including the $5,000 already advanced, to be used by Bird for payment of labor or materials used in the construction project and for which Bird should execute promissory notes payable to appellant upon completion of the construction contract. Appellant advanced to Bird the further sums of $10,000 on August 15, 1952 and $5,000 on November 3, 1952, pursuant to this agreement. Proper notes were executed by Bird to appellant and the monies so advanced were used by Bird in the payment of labor and material accounts. On August 18,1952, Bird advised the University of Arkansas by letter that it desired that any money held by the university as retainage upon completion of the building be paid jointly to Bird and appellant. This letter was duly approved by the university on August 19, 1952, without the knowledge or approval of Maryland.

Bird defaulted in the performance of its contract which was taken over by Maryland. On July 12, 1953, the University of Arkansas paid retainage to Maryland in the sum of $34,073.32 which was used in payment of labor and material bills incurred in construction of the building. Maryland also paid additional sums in excess of $20,000 to complete the construction according to contract. In making the three loans to Bird the appellant did not execute the “Subordinate Loan Contract” suggested by Maryland’s agent. The laborers and material-men made no assignment of their respective liens. There was no express agreement between Maryland and appellant relative to such liens nor was there any agreement between them that appellant would be protected under the surety bond or have a superior lien on the retainage.

Appellant brought this action against Bird and Maryland to recover the $20,000 advanced to Bird under the investment agreement. In the complaint it was alleged that appellant and Maryland made an agreement to the effect that if appellant would make the $20,000 available to Bird then Maryland would include within the provisions of the surety bond any loss that appellant might incur; that Maryland consented to and ratified Bird’s assignment of the retainage under the construction contract to appellant and agreed that he would have a lien on same for the payment of his advances to Bird; and that Maryland had been unjustly enriched and should be estopped to deny that appellant’s claim was within the provisions of the surety bond. In an amendment to the complaint appellant asserted that by reason of his advancement of the $20,000 with Maryland’s knowledge that it was to be used to pay labor and material bills, appellant was thereby .subrogated to the rights of the laborers and materialmen to the retainage held by the university and paid over to Maryland. Maryland answered with a general denial and affirmatively pleaded that the agreement between appellant and Bird was not binding on Maryland, and that any agreement between appellant and Maryland was without consideration and barred by the Statute of Frauds.

There was a jury trial of the cause as between appellant and Maryland. At the conclusion of the testimony offered by appellant as outlined above, the trial court sustained Maryland’s motion for a directed verdict in its favor. This appeal is from the judgment rendered upon said directed verdict. Thus the question is whether the evidence, when given its strongest probative force in favor of appellant, is legally sufficient to support a jury finding of Maryland’s liability to appellant for the $20,000 advanced to Bird.

The performance bond involved in the instant case is the ordinary statutory bond which obligates the surety only to pay all indebtedness for labor and materials furnished in the construction or repair of the building. In 9 Am. Jur., Building and Construction Contracts, 1954 Pocket Supplement, § 92.1, the author states:

“The well established general rule is that a claim for money loaned or advanced to a building or construction contractor is not within the coverage of the ordinary form of contractor’s bond conditioned for the performance of the contract and the payment of all claims for labor and material, even though the borrowed money has been wholly applied to the payment of the cost of labor and material actually going into the construction project. Generally, the recovery of such money loaned or advanced is sought on the theory that inasmuch as the money loaned to the contractor had been used to pay for labor or material going into the project, the lender of the money was entitled to be considered as a furnisher of labor and material, and therefore protected by the bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
280 S.W.2d 398, 225 Ark. 224, 1955 Ark. LEXIS 571, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-maryland-casualty-co-ark-1955.