Johnson v. Hughes

232 P.2d 362, 120 Utah 50, 1951 Utah LEXIS 186
CourtUtah Supreme Court
DecidedJune 6, 1951
DocketNos. 7544, 7545
StatusPublished
Cited by1 cases

This text of 232 P.2d 362 (Johnson v. Hughes) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. Hughes, 232 P.2d 362, 120 Utah 50, 1951 Utah LEXIS 186 (Utah 1951).

Opinion

LATIMER, Justice.

These are two separate cases, commenced in the lower court to recover damages caused by appellants’ failure to properly construct a house for each of the respondents. The cases were heard together in the court below and, by stipulation, were consolidated in the briefs and arguments before this court. The appeals present substantially the same claimed errors, and therefore, the two cases will be disposed of in this one opinion.

On or about March 20, 1947, respondents Lloyd I. Burn-ingham and his wife entered into a written agreement with appellants, under the terms of which appellants agreed to construct a home for the Burninghams. In preparing the specifications for the home, appellants used a standard “Description of Materials” form supplied by the Federal Housing Administration, although the construction was not financed with funds from that agency and no examination or approval of the construction was made by government representatives. The form was prepared and signed by appellant C. H. Hughes. Subsequently, the contract was modified to include the erection of a retaining wall, garage, [53]*53patio, driveway and other incidental extras. On August 16, 1947, the building was completed and Burninghams paid the full amount due and entered into possession of the premises.

Shortly after they took possession, ceiling and wall cracks began developing in the plaster and portions of the cement retaining wall began to disintegrate. Complaints were made to appellants about the defects in the construction, and, upon failing to receive a satisfactory adjustment, suit (No. 7545) was commenced. In their complaint, Burninghams alleged that the crumbling which had developed in the retaining wall was caused by improperly mixed concrete, in that sufficient cement was not used; and that the cracks in the walls and ceilings of the house had developed because appellants had used an inferior and improper plaster mixture and had not properly staggered the lath. After the pre-trial hearing, the trial judge ordered that respondent Clarence E. Peck, who was the subcontractor for plastering the house, be included as a party defendant. Accordingly, the Burninghams amended their complaint to include Peck as a defendant and appellants filed a cross-complaint against him. Prior to resting their case, the Burninghams again amended their complaint to include an allegation that an additional cause for the cracking was that the rafters supporting the roof of the building had not been adequately braced, and that they were not of sufficient size to hold the roof firm and rigid.

The respondents, Vern F. Johnson and his wife, entered into their oral agreement with appellants on April 16, 1947. By this contract, appellants agreed to construct a home for the Johnsons for the cost of materials and labor plus ten per cent. No written specifications were prepared, but there was an understanding that a good and properly constructed house would be erected. On November 16, 1947, the Johnsons took possession of the premises and paid the remaining amount due on the contract. Sometime there[54]*54after, the Johnsons entered into another agreement with appellants to construct a concrete driveway and walks on the premises. The amount due on both contracts was paid in full.

Shortly after Johnsons took possession, the plaster on the walls and ceilings of the house began to crack, the number of cracks increasing and the size enlarging. After completion of the walks and driveways, the concrete mixture began to crumble. The Johnsons informed appellants of the defects in the construction and though C. H. Hughes, one of the appellants, indicated that a plasterer would be sent to repair the defects, nothing was done. In their complaint (action No. 7544) Johnsons alleged that defective plaster had been used in the various rooms; that the plaster and lath had been improperly applied; and that the mixture of concrete used in the driveway had not contained a sufficient amount of cement. As in the Burningham case, the complaint was later amended to include an allegation that the rafters in the roof of the house had been improperly braced and were too small to keep the roof firm and rigid. The pre-trial order did not require the inclusion of Peck as a defendant, and he is not a party in the Johnson case.

The trial judge found that in constructing the retaining wall for the Burninghams and the driveways and walks for the Johnsons, the appellants had used too small an amount of cement in the concrete mixture. He further found that the roofs of both houses had been improperly constructed in that the rafters were spaced too far apart and improperly braced; that the rock lath was not staggered and the seams not covered with metal lath as required by proper construction; and that the failure to meet the ordinary standards of good construction as set forth above caused the retaining wall to disintegrate and the plaster to crack. The trial court awarded judgment in favor of the Burninghams in the total amount of $2,350.00, arrived at in the following way: $100.00 to repair the retaining wall; $250.00 to properly brace the roof; and $2,000.00 to [55]*55replaster the walls and ceilings. In the Johnson case, judgment was awarded against appellants in the amount of $1,850.00, being totalled as follows: $100.00 to repair the driveway; $250.00 to strengthen the roof; and $1,500.00 to replaster the walls and ceilings.

We are met at the threshold of this cause with respondents’ contention that the controversy between appellants and Peck is not properly before this court. We overrule this assertion for the reason that while there are some procedural irregularities, they are not jurisdictional. Peck was joined as a party defendant in the suit below and a judgment was rendered in his favor. He was named as a party in the notice of appeal and we assume, as there is no evidence to the contrary, that the clerk of the district court properly mailed to him or his counsel a notice of the appeal. While he did not file a brief nor participate in the oral arguments, it does not affirmatively appear that appellants stipulated to dismissing him as a party or waived their rights to proceed as against him. They appealed from the final judgment that denied them any relief as against him which we believe to have been the proper procedure to vest this court with jurisdiction. Contrary to respondents’ argument, a cross appeal is not involved.

Appellants raise the same points on appeal in both cases with two variations. In the Burningham case (No. 7545) they assert two additional points, i. e., that the judgment in favor of Peck should be reversed, and that the award of $100.00 for the repair of the wall and patio was erroneous. Stated generally, the points common to both cases can be consolidated into one contention; that is, the evidence does not sustain the findings made by the trial judge.

The evidence in the record requires us to overrule this contention with the exception of the award of $250.00 for strengthening the roof. Appellants do not dispute the fact that the plaster on the walls and ceilings of the two houses was badly cracked. They, however, seek to cast the re[56]*56sponsibility on Peck, the plasterer, claiming- that the court should have found that he used an improper and deficient mix. Even if such were the case insofar as respondents are concerned, they would be entitled to recover as it was appellants’ responsibility to furnish a reasonably well constructed home.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Casados v. Covrig
596 P.2d 640 (Utah Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
232 P.2d 362, 120 Utah 50, 1951 Utah LEXIS 186, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-hughes-utah-1951.