Johnson v. County of Steele

60 N.W.2d 32, 240 Minn. 154
CourtSupreme Court of Minnesota
DecidedAugust 7, 1953
Docket35,944
StatusPublished
Cited by11 cases

This text of 60 N.W.2d 32 (Johnson v. County of Steele) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. County of Steele, 60 N.W.2d 32, 240 Minn. 154 (Mich. 1953).

Opinion

240 Minn. 154 (1953)

HAROLD C. JOHNSON
v.
COUNTY OF STEELE AND ANOTHER.[1]

No. 35,944.

Supreme Court of Minnesota.

August 7, 1953.

*156 Leach & Leach, for appellant.

Byron J. Casey, for respondent county of Steele.

Lord & Walbran, for respondent P.C. Hosfield.

PER CURIAM.

This is an action in nuisance and trespass brought by a landowner for alleged invasions and appropriations of his property during certain ditch construction work. Plaintiff appeals from the orders sustaining the separate demurrers of the two defendants.

The complaint alleges that the county board of defendant county, pursuant to a petition asking for a "repair" of a certain ditch running through plaintiff's land, appointed defendant P.C. Hosfield to prepare the necessary plans and specifications to make this ditch "function efficiently." The county accepted the plans and specifications prepared by Hosfield and let a contract for such work. Hosfield supervised the actual construction work. The complaint alleges that such purported "repairs" were in fact "improvements" and that the ditch was "widened, deepened, changed and altered," thereby appropriating and damaging plaintiff's land and washing out a bridge owned by plaintiff. Plaintiff asked for treble damages under authority of M.S.A. 548.05.

Defendants each demurred on the grounds that the facts stated did not constitute a cause of action. No explanation or argument was offered in the motion, and the record does not contain a transcript of any oral argument. The order is also silent regarding the reason that the complaint fails to state a cause of action, and no memorandum accompanies the order.

1. In support of the demurrer, respondent county first contends that the complaint does not state a cause of action because the allegation that the purported "repairs" were in fact "improvements" is a mere conclusion of law and unsupported by factual allegations. The allegation that defendants "widened, deepened, changed and altered" the channel and extended the waste banks is a sufficient *157 factual allegation to support the legal conclusion that the alterations constituted an "improvement" of a ditch. See, Opinions Attorney General, File 602-J.

2. The county also contends that it is uncertain whether it is plaintiff's claim that the plans and specifications were erroneous and the contract and actual construction followed them, or whether he claims that the plans and contract were within the authorized limits but the actual construction work exceeded these limits. The complaint alleges the acceptance of the plans and specifications, the letting of "a contract therefor," and the eventual construction of the "purported repairs," which were in fact "improvements." Although possibly subject to a motion to make more definite and certain, a comprehensive reading of the complaint compels the conclusion that it is plaintiff's contention that the plans and specifications, and the contract let pursuant thereto, called for construction work amounting to "improvements."

The complaint does not allege that proper notice and hearing, as required by the "repair" provision of the statutes,[2] were not given, and thus we must presume that all required procedural steps were taken. 7 Dunnell, Dig. (3 ed.) § 3435.

Assuming that all the well-pleaded factual allegations are true as we must in testing a complaint, the situation presented is one in which a county board received a petition asking for a "repair" of a certain ditch. Such petition could only qualify as a "repair" petition and not as an "improvement" petition because of the limited number of signers. Pursuant to this petition, the board appointed defendant Hosfield as engineer to prepare the necessary plans and specifications "to make said ditch function efficiently." The engineer prepared plans and specifications which called for widening, deepening, altering, and changing the existing channel. Plaintiff was notified of a hearing, at which time he would have been entitled to such information as could have been given by the engineer.[3]*158 After such hearing, the county board accepted the plans and specifications and ordered the letting of a contract for the construction work proposed; the same engineer supervised such work. The work amounted to a widening, deepening, and altering of the original channel, thereby appropriating and damaging plaintiff's land and washing out the bridge owned by plaintiff. Plaintiff at no time appealed from the order of the county board, as provided by statute,[4] but brings a common-law action in nuisance and trespass to recover for such damages.

3. There is a fundamental difference between a "repair" proceeding and an "improvement" proceeding both substantively and procedurally. Substantively, a "repair" proceeding contemplates only the restoration of the ditch to its original condition without in any manner changing or altering its channel. See, County of Brown v. Martinsen, 153 Minn. 268, 190 N.W. 255; Opinions Attorney General, File 602-J. Thus, the "repair" statute makes no provision for an award of damages since, under proper procedure, a "repair" will not affect the land through which the ditch flows other than the damage occasioned by the original establishment of the ditch for which the landowners presumably were fully compensated at that time.[5] The "improvement" proceeding, on the other hand, contemplates extension and alteration of the original ditch with resulting damages to private property. Thus, the "improvement" statute, § 106.501, provides for awarding damages to owners of land damaged by such work.

Procedurally, a "repair" proceeding requires only the filing of a petition by any party interested in or affected by the drainage system in order for the board to order a hearing and eventually *159 authorize the repairs.[6] However, the "improvement" statute is quite specific in providing that, before any drainage system shall be "improved," a petition signed by not less than 26 percent of the owners or property affected must be filed. The complaint in the case at bar specifically alleges that the petition could not qualify as an "improvement" petition in that, among other things, such petition was not signed by such proper number of petitioners.

4. Provisions in statutes regulating the construction of public drains and designed for the protection of landowners must be strictly followed. 6 Dunnell, Dig. (3 ed.) § 2821. Thus, it has been held that a petition signed as required by statute is a jurisdictional prerequisite to the establishment of a ditch system. State ex rel. Utick v. Board of Co. Commrs. 87 Minn. 325, 92 N.W. 216, 60 L.R.A. 161; County of Martin v. Kampert, 129 Minn. 151, 151 N.W. 897; In re Judicial Ditch No. 9, 167 Minn. 10, 208 N.W. 417; In re Judicial Ditch No. 12, 227 Minn. 482, 36 N.W. (2d) 336, certiorari denied, 337 U.S. 938, 69 S. Ct. 1514, 93 L. ed. 1743; In re Judicial Ditch No. 10, 171 Minn. 478, 214 N.W. 285. Since an "improvement" proceeding equally contemplates the taking and injury of land not otherwise damaged and appropriated by the original ditch establishment, it follows that the proper petition is also a jurisdictional prerequisite to an "improvement" proceeding. Since the complaint alleges that there was no proper petition for an "improvement" here, it would appear that the county was without jurisdiction to order any construction other than "repairs."

5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nusbaum v. County of Blue Earth
422 N.W.2d 713 (Supreme Court of Minnesota, 1988)
Wilson v. Ramacher
352 N.W.2d 389 (Supreme Court of Minnesota, 1984)
Williamson v. Cain
245 N.W.2d 242 (Supreme Court of Minnesota, 1976)
DePalma v. Rosen
199 N.W.2d 517 (Supreme Court of Minnesota, 1972)
Larson v. Freeborn County
126 N.W.2d 771 (Supreme Court of Minnesota, 1964)
Janssen v. County of Chippewa
98 N.W.2d 239 (Supreme Court of Minnesota, 1959)
Wolfram v. State Ex Rel. Burnquist
74 N.W.2d 510 (Supreme Court of Minnesota, 1956)
Oelke v. County of Faribault
70 N.W.2d 853 (Supreme Court of Minnesota, 1955)
Taylor v. County of Sherburne
67 N.W.2d 827 (Supreme Court of Minnesota, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
60 N.W.2d 32, 240 Minn. 154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-county-of-steele-minn-1953.