Johnson v. Columbia Properties

CourtCourt of Appeals for the Ninth Circuit
DecidedFebruary 10, 2006
Docket04-35592
StatusPublished

This text of Johnson v. Columbia Properties (Johnson v. Columbia Properties) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. Columbia Properties, (9th Cir. 2006).

Opinion

FOR PUBLICATION UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT

MORRIS JOHNSON, JR.,  Plaintiff-Appellant, No. 04-35592 v.  D.C. No. CV-03-00054-A- COLUMBIA PROPERTIES ANCHORAGE, LP, RRB Defendant-Appellee. 

MORRIS JOHNSON, JR.,  Plaintiff-Appellee, No. 04-35671 v.  D.C. No. CV-03-00054-RRB COLUMBIA PROPERTIES ANCHORAGE, LP, OPINION Defendant-Appellant.  Appeal from the United States District Court for the District of Alaska Ralph R. Beistline, District Judge, Presiding

Argued and Submitted July 14, 2005—Anchorage, Alaska

Filed February 10, 2006

Before: Alfred T. Goodwin, Melvin Brunetti, and William A. Fletcher, Circuit Judges.

Opinion by Judge William A. Fletcher

1615 1618 JOHNSON v. COLUMBIA PROPERTIES ANCHORAGE

COUNSEL

Hugh G. Wade, Wade, Kelly & Sullivan, Anchorage, Alaska, for the plaintiff-appellant/appellee.

Douglas J. Serdahely and Michael A. Grisham, Patton Boggs, Anchorage, Alaska, for the defendant-appellee/appellant. JOHNSON v. COLUMBIA PROPERTIES ANCHORAGE 1619 OPINION

W. FLETCHER, Circuit Judge:

Morris Johnson sued Columbia Properties Anchorage LP (“Columbia”) for breach of contract in an Alaska state court, alleging, inter alia, that Columbia failed to pay for crane ser- vices he provided in connection with the construction of the Marriott Hotel in Anchorage. After Columbia removed the case, the federal district court denied Johnson’s motion to remand and granted Columbia’s motion for partial summary judgment. We hold that the district court properly exercised jurisdiction over this case, and that it correctly held that John- son’s claim for payment for the crane services is time-barred. Finally, we hold that the district court did not abuse its discre- tion in denying attorneys’ fees to Columbia.

I. Background

Johnson is a citizen of Alaska. Columbia is a limited part- nership organized in Ohio. Its two partners, CP Anchorage, GP, LLC, and CSC Holdings, LLC, are limited liability com- panies (LLCs), also organized in Ohio. The two LLCs are owned by a Kentucky corporation; by an Ohio corporation; and by a trust whose sole trustee is a bank incorporated in Delaware with its principal place of business in Minnesota.

Columbia managed the construction of the Marriott Hotel in Anchorage between 1998 and 2000. In August 1998, Dave Mueller, Columbia’s project manager, entered into a contract with Johnson, an independent contractor, under which John- son agreed to provide crane services. On August 17, 1998, Johnson sent a proposal to Mueller for rental of a 125-ton crane, as well as for wages for a crane operator and an oiler. Brian Prince, a project engineer for Columbia, replied on August 25th, accepting the proposal and summarizing the agreement between Johnson and Columbia. Prince’s one- paragraph letter stated that Johnson would provide the “125 1620 JOHNSON v. COLUMBIA PROPERTIES ANCHORAGE ton truck crane” to Columbia “per your proposal of 8/17/98 to Dave Mueller.” Also, “[t]he crane will be required proba- bly sometime in mid-September and be required probably through the end of the year, and periodically after that.” The letter further noted that “no other agreements (such as Pur- chase Orders, Contracts, etc.) will be sent unless you specifi- cally request one.” The letter concluded that, unless Prince heard back from Johnson to the contrary, “I will assume that we have reached an agreement for your services to be pro- vided as we need them.” The letter did not mention any bill- ing arrangements or any other equipment or services.

Johnson states in his affidavit that in August and September of 1998 he and Mueller discussed other lifting and hoisting services Johnson could contribute to the Marriott Hotel proj- ect, and that he sent Mueller his rates for the rental and opera- tion of 50- and 25-ton cranes and a forklift. Johnson states that, based on these discussions, the parties made oral modifi- cations to the agreement summarized in Prince’s August 25th letter, expanding the range of services that Johnson would provide to Columbia. Johnson’s affidavit summarizes what he contends were the final terms of the agreement, concluded in late September 1998:

1) When requested, Johnson would provide the appropriate crane or hoist to satisfy Columbia’s requirements; 2) both parties would maintain ordi- nary job records, time cards and daily logs, but there was to be no contemporaneous exchange of such records, nor any requirement for signatures or writ- ten acknowledgment of receipt of services; 3) at the conclusion of the project [Johnson] would invoice Columbia for [his] services; 4) Columbia would review [his] notice and [the parties] would attempt to resolve any question or discrepancy if there was a conflict between [his] invoice and Columbia’s job records . . . [and] 5) the invoice or invoices would be JOHNSON v. COLUMBIA PROPERTIES ANCHORAGE 1621 due and payable promptly after submittal, and if unpaid, would draw interest from the invoice date.

Johnson stated in his affidavit that he provided crane ser- vices during four periods beginning in late September 1998: (1) he provided a 50-ton crane on four different occasions from September 28, 1998, through December 5, 1998; (2) he provided the 125-ton crane described in the August 28 letter for one month beginning on December 4, 1998; (3) he pro- vided a 20-ton crane from January 15, 1999, through August 8, 1999; and (4) he provided the 50-ton crane from July 29, 1999, to August 3, 1999.

According to Johnson’s affidavit, he submitted a handwrit- ten summary of his work logs to Mueller shortly after he fin- ished providing the crane services on August 8, 1999. Johnson states that he provided the summary “so that I could prepare an invoice” once Columbia looked over the logs for “any problems or questions with my summary.” Johnson stated that Mueller never got back to him about the summary. As described below, Johnson did not send an invoice to Columbia until sometime in January 2002.

According to Johnson’s affidavit, Mueller was replaced by Andy King as project manager sometime in mid to late 1999. In February 2000, King contacted Johnson and asked him to perform cleanup work in a storage yard at Ship Creek, a loca- tion near the Port of Anchorage and some distance from the Marriott Hotel. Johnson states in his affidavit that King “un- derstood” his earlier agreement with Columbia, and he implies that King intended the Marriott crane services con- tract to cover the Ship Creek cleanup work as well. King remembers the transaction differently. He states in his affida- vit that the cleanup project was covered by a “stand-alone contract,” and that he and Johnson “did not discuss any terms of any sort from any preexisting or ongoing agreement.” Johnson used a forklift and a crew of manual laborers to per- 1622 JOHNSON v. COLUMBIA PROPERTIES ANCHORAGE form the cleanup work at Ship Creek. He used no cranes. Johnson completed this work on February 24, 2000.

Johnson sent Columbia an invoice totaling $105,328 in Jan- uary 2002. This invoice covered all the services he had pro- vided to Columbia, including the crane services at the Marriott Hotel and the cleanup at Ship Creek. On February 14, King responded by expressing surprise at the size and the lateness of the bill. He asked for back-up documentation for the Ship Creek job. There is no indication in the record whether Johnson responded to the request for documentation. On February 13, 2003, over a year after submitting the invoice, Johnson filed this suit for breach of contract in Alaska state court.

Columbia removed the suit to federal court based on diver- sity of citizenship.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rolling Greens MHP, L.P. v. Comcast SCH Holdings L.L.C.
374 F.3d 1020 (Eleventh Circuit, 2004)
Great Southern Fire Proof Hotel Company v. Jones
177 U.S. 449 (Supreme Court, 1899)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Navarro Savings Assn. v. Lee
446 U.S. 458 (Supreme Court, 1980)
Sun Oil Co. v. Wortman
486 U.S. 717 (Supreme Court, 1988)
Carden v. Arkoma Associates
494 U.S. 185 (Supreme Court, 1990)
Howarth v. First National Bank of Anchorage
540 P.2d 486 (Alaska Supreme Court, 1975)
Byrne v. Ogle
488 P.2d 716 (Alaska Supreme Court, 1971)
Strotek Corp. v. Air Transport Ass'n of America
300 F.3d 1129 (Ninth Circuit, 2002)
Vess v. Ciba-Geigy Corp. USA
317 F.3d 1097 (Ninth Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Johnson v. Columbia Properties, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-columbia-properties-ca9-2006.