Johnson Service Co. v. Fayette Title & Trust Building

96 Pa. Super. 535, 1929 Pa. Super. LEXIS 199
Superior Court of Pennsylvania·Decided April 16, 1929·No. Appeal 145·Published·Cited by 4 cases

Opinion

Opinion by

Babdrige, J.,

This appeal is from a decree of the lower court striking off a mechanic’s lien filed by a sub-contractor. In support of the motion; it was contended (a) that the lien does not sufficiently set forth definite dates of furnishing materials and performing labor; (b) that the claimant does not specify the kind or nature of the labor; (c) that the lien is defective in form.

Seventeen hundred and ninety-five ($1,795) dollars was alleged to be due under a verbal contract for the installation of a temperature control apparatus. The work was done and materials were furnished between October 8, 1924, and May 20, 1925, as set forth in the •bill of particulars, which is as follows:

“2 — Slate switch boards each mounted with 4 lever handle switches and 1 graduated switch. Each board contained in iron box with cover.
1— Plush switch in iron box.
6 — Metal diaphragm coil valves.
2— By-pass dampers.
2 — Presh air dampers.
1 — Yent damper.
5 — Metal diaphragm draft regulators to operate the above dampers.
1— 3x3 double cylinder electric air compressor complete with automatic governor switch to control to 15 pound air pressure.
2— 30 gallon air storage tanks and pressure gage.
2700' — Galvanized pipe with all fittings necessary to make a complete system of air piping as required.
Labor—
11/20 — 26/24 ...................... 44 hrs.
*538 12/1/24 ..... 8 hrs,
12/23 — 24/24 12 “
1/5/25 ...... 5 “
3/4/25 ....... 3 “
3/26/25 .... 4 “
5/6/25 ...... 4 “
5/15 — 20/25 . 40 “
Contract completed 5/20/25.

It will be noted that the material is stated in detail but no dates are given when it was furnished or the prices charged for the different materials, and this is also true, in part, for the labor performed; for instance, the first item is for labor between November 20th and 26th — 44 hours.

The Act of April 17, 1905, P. L. Í72, provides that the lien shall set forth “the amount or sum claimed to be due and the nature or hind of the work done, or the kind and amount of material furnished, or both; and the time when the materials were furnished, or the work done, or both, as the case may be.”

One of the objects of this legislation was to give the owner of a building, who was not a privy to the contract. between a contractor and a sub-contractor, but who eventually pays the bill, sufficient data so that he could properly inform himself whether the contract was fulfilled. There have been many suits growing out of the correct interpretation and application of this provision, and some difficulty has arisen to reconcile the decisions thereunder.

For our present purposes we will briefly consider two classes of cases; (1) those where labor was done or materials were furnished, or both, under a contract, and (b) where there was no contract.

In the first class is Willson v. Canevin, 226 Pa. 362. There a sub-contractor filed a lien for a lump sum under a written contract, as follows: “Contract price, $3,400; extras ordered and furnished, $145.50, total *539 $3,545.50.” Attached to the claim was an itemized statement giving the items of materials furnished, with the year, month, and day they were furnished, but did not give an itemized price of each item. The court, in holding it to be a valid lien, said, “The statement gives the owners a detailed account of the various items of materials furnished, the total of the price to be paid and the kind of materials furnished. This is all the information he needs to enable him to deal intelligently with the contractor and protect himself.”

In Bennett Lumber Co. v. Hartrick, 61 Pa. Superior Ct. 456, a lien was filed under a contract for certain lumber furnished and mill work done between the dates of December 19, 1911, and April 23, 1912. The plaintiff’s claim was for ten items consisting of window and door frames and a. specified quantity of cornice. The court held that the materials were placed in the building and the owners had an opportunity to inspect them and that the fairness of the price charged could easily be ascertained, and as there was no statutory obligation resting on the plaintiff to specify the price of each article where the whole was furnished under a lump contract, the claim was not objectionable on that ground.

In Curti v. Hartrick, 61 Pa. Superior Ct. 447, the claim was for materials furnished and labor done between November 10, 1911, and May 4, 1912, under a written bid. The claim set forth the number of perch of stone furnished and price per perch, the number of window sills and chimney caps, with itemized prices thereof, and contained an item of $50 for “material and labor building concrete footing course” and four hours extra labor at 25 cents per hour — $1. Exception was taken to the bill of particulars attached to the lien on the ground that the prices were not itemized and that it contained a lumping charge. The court held that for all the items, except for the labor, the *540 specifications were sufficient as the work was done under a contract. The items for labor and material in building the concrete footing course were not included in the contract and no information was 'given as to the material used or the labor involved, or the extent of the construction; and the one dollar item gave no information as to the character of the labor or upon what it was applied; and therefore that part of the. claim was held to be deficient.

In the following cases, materials were furnished and work done without contract:

In Barker Paint Co. v. General Carbonic Co., 78 Pa. Superior Ct. 493, the lien filed was stricken off by the court as no dates were given showing when the various materials were furnished, except the time of the beginning and completing of the work. The court said: “A careful reading of the lien gives the impression that the claimant -intended to aver that he made an estimate of what the work would- cost, that the contractor authorized him to proceed with the undertaking and that the claimant charged, not a lump sum on a contract, but what the labor and material were worth. If this is the correct view of the claim, the appellant’s account is for the actual value of the labor and material, in which case, as a sub-contractor, it was his duty to set forth the dates and amounts of the materials furnished and the labor performed in the execution of the work.” The judgment of the lower court striking off the lien was affirmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Johnson Service Co. v. Fayette Title & Trust Building, 96 Pa. Super. 535, 1929 Pa. Super. LEXIS 199 (Pa. Ct. App. 1929).

96 Pa. Super. 535 (Johnson Service Co. v. Fayette Title & Trust Building) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Fried v. Fried
501 A.2d 211 (Supreme Court of Pennsylvania, 1985)
Fitzpatrick v. Howes
76 Pa. D. & C. 543 (Bucks County Court of Common Pleas, 1951)
Harvard v. McMullen
74 Pa. D. & C. 222 (Beaver County Court of Common Pleas, 1950)
Duplex Elec. Co. v. Simons, Brittain & English, Inc.
156 A. 617 (Superior Court of Pennsylvania, 1931)