Johnson, Drake & Piper, Inc. v. New York State Thruway Authority

30 Misc. 2d 995, 221 N.Y.S.2d 648, 1961 N.Y. Misc. LEXIS 2253
CourtNew York Court of Claims
DecidedOctober 12, 1961
DocketClaim No. 33264
StatusPublished

This text of 30 Misc. 2d 995 (Johnson, Drake & Piper, Inc. v. New York State Thruway Authority) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson, Drake & Piper, Inc. v. New York State Thruway Authority, 30 Misc. 2d 995, 221 N.Y.S.2d 648, 1961 N.Y. Misc. LEXIS 2253 (N.Y. Super. Ct. 1961).

Opinion

Bernard Ryan, P. J.

On or about February 9,1953 claimant corporation entered into a contract with the New York State Thruway Authority for the construction of a portion of the-Thruway, being Ontario Section, District 5, Subdivision 15, Ransom Road to Genesee County line in the County of Erie. The contract was designated by numbers ST 53-02, OT 53-1. One A. L. Dougherty, doing business as A. L. Dougherty Company, subcontracted the performance of certain items of the work and this suit arises from developments encountered in his operation.

[996]*996Claimant’s contract provided as follows:

5. SUB-SURFACE EXPLORATION
Sub-surface explorations have been made within the limits of the proposed work. Interested parties may review the records of these explorations at the office of the District Engineer in Buffalo, New York.
The information contained in the foregoing paragraph is offered in good faith by the Department and reflects the opinions of the Department engineers relative to the sub-surface conditions. The Contractor’s attention, however, is called to the fact that the information obtained therefrom is not to be substituted for personal investigation and research by the Contractor as required by Article three of the Contract Agreement.
6. EXCAVATION
Overhaul will not be paid for under this contract. The cost of overhaul as such shall be included in the price bid for the various excavation items. All suitable material removed from the road excavation and drainage ditches shall be used in the roadway embankments or otherwise, as directed by the Engineer.
The quantity of excavation is sufficient to include those quantities required for embankment, foundation course, shoulders and trench backfill. All material for embankment, foundation, shoulders and trench will be paid for under Item 2B. No payment will be made under Items 39ÍBYS, 2590'S, 259LS or 119S for acceptable material which is taken from the excavation thru the gravel deposit between Sta. 972+00 and 1010+00.
Materials excavated and found by the Engineer to be unsuitable for use in the roadway embankments shall be wasted along toe of fills or otherwise, as directed by the Engineer.
7. FOUNDATION COURSE, SHOULDERS, TRENCH BACKFILL
The Contractor’s attention is called to Items 39ERYS, 259GS, 259LS and 119S under which no payment is made for material (gravel). It is the intent that the material found between Sta. 972+00 and 1010+00 be used in these items and paid for under Item 2B (Unclassified Excavation). Payment under these items is for placing the material only, the cost of haul on these items would be included under 2B. The remaining surplus of excavated material of 41,022 C. Y. is felt to be ample to balance the quantity which was removed from this area after the cross sections were taken. However, should the quantity of acceptable material required exceed that which is available, necessitating using an off the job source, the Contractor would be paid for any additional foundation course material under Item 39BY.
Further attention is called to the typical section between Sta. 972+00 and 1010+00 which requires a 6" minimum foundation course in place of the 12" minimum foundation course which is used throughout the remainder of the project.

Representatives of the subcontractor visited the site of the project prior to bidding. Claimant has not satisfied us that their investigation thereof was conducted with reasonable care. Had it been they would, we believe, have observed certain conditions which, according to witnesses whose testimony preponderates, disclosed that the job site between Stations 972 and 1002, colloquially known as the “ big cut”, were readily to be seen. [997]*997There was sand on the bottom of the face, gravel and sand mixture in the middle of the face and gravel on top of the open face. These conditions were observed by others; not only by the engineer in charge for the State Thruway Authority, but by some of claimant’s own employees and by an entirely disinterested witness, an employee of the Clarence Sand and Gravel Company, who had, prior to Thruway construction, operated machinery in the gravel pit.

The contract called for the excavation of estimated quantities of earth from certain areas on the project site and the placing of earth in fill areas thereon. Details were set forth in earthwork sheets depicted on Sheet 8 of the contract plans. There a table of balances recited the quantities estimated to be excavated from certain locations which were designated by contract station numbers. The table gave the yardage which, it was estimated, would be obtained between Station 972 and Station 1010 as 393,628 cubic yards. This was denominated Balance 7. Combining all the cut and fill estimates, an estimated surplus of 220,672 cubic yards of material was indicated. The estimated yardage of select material available from Balance 7 was 179,650 cubic yards. Deducting that figure from the estimated surplus reduced that estimate to 41,022 cubic yards.

The “ big cut ” was in the path of the Thruway. Altogether claimant took from it 410,624 cubic yards of material. This figure included 25,000 cubic yards which was not moved until after April 15, 1954. In 1953 claimant set aside from the material so excavated and stockpiled 19,246 cubic yards. This yardage was later used to meet gravel requirements for foundation course specified in the contract and designated as Item 39BYS.

Claimant contends that in the Spring of 1953 it discovered a vein of sand underlying the area upon which both lanes of the Thruway would be built between the stations comprising Balance 7. The vein varied in depth, but at spots measured 12 feet. This underlying sand met the contract specifications for embankment, Item 2B, but was unsuitable for the several gravel items. (See quotations from contract hereinabove.) Claimant then proposed to excavate the face of the cut which sloped upwards for 20 feet on a 45-degree angle and further proposed to use both sand and gravel for Item 2B and the gravel items indiscriminately as it came from the cut. Permission was refused by the defendant’s engineer and claimant was directed to procure gravel from the cut which would meet the contract specifications. To do this claimant was obliged to operate its equipment in a manner which increased its cost.

[998]*998It is claimant’s contention that when its representatives inspected the site the sand vein was not visible and thus its presence was unknown to claimant. However, as we have already stated, we find the preponderance of the evidence to be that the sand stratum was exposed to view. Therefore the claimant should have been aware of the situation.

Claimant further contends that it was misled by the earthwork sheets, in particular that the entire 393,628 cubic yards of material estimated to be available in Balance 7 met the contract specifications for the gravel items. However, reading the earthwork sheets together with the special notes in the proposal hereinabove quoted, particularly the last sentence of paragraph 7 which read should the quantity of acceptable material required

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
30 Misc. 2d 995, 221 N.Y.S.2d 648, 1961 N.Y. Misc. LEXIS 2253, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-drake-piper-inc-v-new-york-state-thruway-authority-nyclaimsct-1961.