Johnson Brothers Contracting, Inc. v. Simpson Tacoma Kraft Company, Llc.

CourtCourt of Appeals of Washington
DecidedAugust 4, 2014
Docket71735-9
StatusUnpublished

This text of Johnson Brothers Contracting, Inc. v. Simpson Tacoma Kraft Company, Llc. (Johnson Brothers Contracting, Inc. v. Simpson Tacoma Kraft Company, Llc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson Brothers Contracting, Inc. v. Simpson Tacoma Kraft Company, Llc., (Wash. Ct. App. 2014).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

JOHNSON BROTHERS CONTRACTING, INC., No. 71735-9-1 ro ° Appellant, DIVISION ONE S 3° f- 3* UNPUBLISHED OPINION ?> o- i XT :-. n

SIMPSON TACOMA KRAFT COMPANY, K •-- LLC, FILED: August 4, 2014 5 ^ Respondent. o

Appelwick, J. — Johnson Brothers Contracting, Inc. appeals the summary

judgment order dismissing its breach of contract, promissory estoppel, and negligent

misrepresentation claims against Simpson Tacoma Kraft Company, LLC. JBC sued after

Simpson declined to follow through with an oral eighteen month contract for the sale of

hog fuel. Simpson argues that JBC's claims are barred by the statute of frauds and the

independent duty doctrine. We affirm.

FACTS

In early 2009, Simpson Tacoma Kraft Company LLC was building a power plant

that would require large quantities of "hog fuel" to operate. "Hog fuel" is ground forest

slash that is used to fuel generators. Johnson Brothers Contracting Inc. (JBC), a Montana

company, produces hog fuel. Simpson approached JBC to supply hog fuel for its plant.

The parties met on March 3, 2009 at a Chehalis restaurant owned by Brent Deroo.

Deroo acted as JBC's hog fuel sales broker in the negotiations. Simpson was

represented by Steve Regelin, its fuel procurement manager at that time. Regelin

indicated that Simpson was a few months away from completing its plant and would soon

need about 100 truckloads of hog fuel per day to run the plant's generators. No. 71735-9-1/2

During their discussion, the parties agreed on JBC supplying 90 truckloads a week

for 12 months, after which either party could give written notice to terminate the

agreement six months from that date. Each truckload held about 33 tons. The parties

discussed an initial price of $53 per ton. The going rate for hog fuel at that time was $63

per ton, so this was a good deal for Simpson. Simpson also proposed that JBC set up a

processing site in Olympia, nearby Simpson's plant, to reduce trucking and transport

costs. No written contract was produced.

A few days later, Regelin sent an e-mail to JBC acknowledging the meeting and

their discussions. Johnson requested that Regelin send a more detailed letter of intent

so Johnson could present it to a lender if he needed to obtain funding. Regelin did so,

writing, "This letter is to confirm Simpson Tacoma Kraft Company's desire to enter into

an agreement with Johnson Brothers Contracting, Inc. to purchase hog fuel produced in

your facilities." It then detailed the terms set forth by the parties. The letter concluded, "I

believe this captures the items we discussed and I'm looking forward to developing this

important source of hog fuel using forest slash material."

Though the letter was sufficient to obtain funding, it was more "wishy-washy" than

Johnson would have liked. But, Johnson thought the parties made a deal at the March 3

meeting. Johnson also thought that Regelin and Deroo were proceeding as if the deal

was done. Deroo treated the March 3 meeting as a commitment, one that obligated JBC

to move forward on the project.

According to Johnson and Deroo, Regelin called at the end of March and

confirmed that JBC should proceed with the Olympia site per the terms of the March 23

letter. JBC obtained a site lease from Welco LLC, and developed the Olympia location No. 71735-9-1/3

for the purpose of providing hog fuel to Simpson. JBC expended about $200,000 setting

up the processing site. Simpson's representatives visited the processing site regularly as

it progressed. One Simpson representative, Blayde Fry, visited several times that spring.

In late spring, Regelin retired and a new fuel buyer, Bill Disbrow, took over. At this

point, Disbrow indicated that Simpson would not be purchasing hog fuel from JBC's

Olympia site as discussed. Fry had expressed concern about the quality of JBC's

Olympia hog fuel, which he said led to Simpson's ultimate decision not to enter into a

contract with JBC. According to Regelin, neither the March 3 meeting nor the March 23

letter constituted a binding contract. Instead, they were demonstrations of interest in

entering into an agreement in the future. Johnson maintained, however, that the parties

had formed a contract that Disbrow broke because he overcommitted to other suppliers

that offered better deals.

Disbrow instructed JBC to shut down the site to "stop the bleeding." JBC resold

its hog fuel to another company, but at a loss.

On March 12, 2012, JBC sued Simpson for breach of contract, promissory

estoppel, and negligent misrepresentation. Simpson moved for summary judgment

seeking to dismiss all of JBC's claims. Simpson argued that the statute of frauds barred

JBC's breach of contract and promissory estoppel claims; that JBC failed to present a

valid negligent misrepresentation claim; and that the statute of limitations precluded JBC's

suit.

The court granted Simpson's motion in its entirety. JBC appeals. No. 71735-9-1/4

DISCUSSION

This court reviews summary judgment orders de novo. Hadlev v. Maxwell, 144

Wn.2d 306, 310-11, 27 P.3d 600 (2001). Summary judgment is appropriate only where

there are no genuine issues of material fact and the moving party is entitled to judgment

as a matter of law. CR 56(c); Peterson v. Groves, 111 Wn. App. 306, 310, 44 P.3d 894

(2002). When considering the evidence, we draw reasonable inferences in the light most

favorable to the nonmoving party. Schaaf v. Hiqhfield, 127 Wn.2d 17, 21, 896 P.2d 665

(1995). We may affirm the trial court's ruling on any grounds adequately supported by

the record. State v. Costich, 152 Wn.2d 463, 477, 98 P.3d 795 (2004).

I. Breach of Contract

JBC asserts that the trial court improperly concluded that the statute of frauds

barred its breach of contract claim. Under the statute of frauds, certain contracts must be

in writing to be valid. See RCW 19.36.010. This includes contracts that will not be

performed in one year. RCW 19.36.010(1). Where a contract is for the sale of goods,

the Uniform Commercial Code (UCC) applies. RCW 62A.2-101, .2-102. The UCC has

its own statute of frauds provision, which states that a contract for the sale of goods for

$500 or more is not enforceable unless it is in writing. RCW 62A.2-201(1). JBC does not

assert that it had a written contract for this transaction, nor that it had an oral agreement

for a year or less.

A. Contract for Services or Goods

Johnson contends that its agreement with Simpson was not for the sale of goods,

but for a service—namely, the processing and transport of hog fuel. Where a contract

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ford v. Logan
483 P.2d 1247 (Washington Supreme Court, 1971)
Lige Dickson Co. v. Union Oil Co. of California
635 P.2d 103 (Washington Supreme Court, 1981)
Schaaf v. Highfield
896 P.2d 665 (Washington Supreme Court, 1995)
Hines v. Data Line Systems, Inc.
787 P.2d 8 (Washington Supreme Court, 1990)
Eastwood v. Horse Harbor Foundation, Inc.
241 P.3d 1256 (Washington Supreme Court, 2010)
Peterson v. Groves
44 P.3d 894 (Court of Appeals of Washington, 2002)
State v. Costich
98 P.3d 795 (Washington Supreme Court, 2004)
Hadley v. Maxwell
27 P.3d 600 (Washington Supreme Court, 2001)
Lawyers Title Ins. Corp. v. Baik
55 P.3d 619 (Washington Supreme Court, 2002)
Tacoma Athletic Club, Inc. v. Indoor Comfort Systems, Inc.
902 P.2d 175 (Court of Appeals of Washington, 1995)
Hadley v. Maxwell
144 Wash. 2d 306 (Washington Supreme Court, 2001)
Lawyers Title Insurance v. Baik
147 Wash. 2d 536 (Washington Supreme Court, 2002)
State v. Costich
152 Wash. 2d 463 (Washington Supreme Court, 2004)
Eastwood v. Horse Harbor Foundation, Inc.
170 Wash. 2d 380 (Washington Supreme Court, 2010)
Peterson v. Groves
111 Wash. App. 306 (Court of Appeals of Washington, 2002)
Portland Ass'n of Credit Men, Inc. v. Earley
254 P.2d 758 (Washington Supreme Court, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
Johnson Brothers Contracting, Inc. v. Simpson Tacoma Kraft Company, Llc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-brothers-contracting-inc-v-simpson-tacoma--washctapp-2014.