Johnson Bros. Corp. v. Rapidan Redevelopment Ltd. Partnership

423 N.W.2d 725, 1988 Minn. App. LEXIS 488, 1988 WL 50210
CourtCourt of Appeals of Minnesota
DecidedMay 24, 1988
DocketC7-87-2254
StatusPublished
Cited by1 cases

This text of 423 N.W.2d 725 (Johnson Bros. Corp. v. Rapidan Redevelopment Ltd. Partnership) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson Bros. Corp. v. Rapidan Redevelopment Ltd. Partnership, 423 N.W.2d 725, 1988 Minn. App. LEXIS 488, 1988 WL 50210 (Mich. Ct. App. 1988).

Opinion

OPINION

FORSBERG, Judge.

This appeal is from a grant of partial summary judgment to respondents Rapi-dan Redevelopment Limited Partnership and Actaeon Corporation (“Rapidan/Ac-taeon”) against appellants Northbrook Excess and Surplus Insurance Company and Transport Indemnity Company (“NES-CO/Transport”). Rapidan/Actaeon, the owners of a hydroelectric generating station, purchased force majeure insurance policies from NESCO/Transport after entering into construction contracts for the refurbishment of the station. The only other parties involved in this appeal are respondent Johnson Brothers Corporation (“JBC”), the general contractor on the *727 project, and respondent Allis-Chalmers Corporation (“Allis-Chalmers”), 1 a subcontractor responsible for providing turbines for the project. We affirm the trial court’s grant of partial summary judgment to Ra-pidan/Actaeon.

PACTS

In March 1983, Rapidan/Actaeon and JBC entered into a construction agreement for the refurbishment of the generating station. That contract required substantial completion on or before May 20,1984. For each day that substantial completion was delayed, JBC was to pay Rapidan/Actaeon liquidated damages in the amount of $2,000 per day. JBC was not liable for delay caused by force majeure, which was defined by the agreement as any condition or occurrence “not within the reasonable control” of the party claiming its existence, including but not limited to “floods, storms, strikes, * * * acts of God, unavailability of materials, delays of common carriers, * * * failure of equipment, explosions, failure in obtaining permits, [and] delays by the Owner.”

To cover these exceptions, Rapidan/Ac-taeon purchased force majeure insurance policies from NESCO/Transport, with each insurer providing 50 percent of the total coverage. The policies require NES-CO/Transport to indemnify Rapidan/Ac-taeon in the amount of $2,000 per day for force majeure delays, which are defined in the same manner as in the agreement with JBC. The policies provide for different deductibles: if no party is at fault, the deductible is $100,000; if the contractor (JBC) or the turbine manufacturer (Allis-Chalmers) is liable for a delay, the deductible equals the amount of that party’s respective liability.

In July 1985, JBC sued a number of parties, including Rapidan/Actaeon (to recover certain progress payments allegedly due under the agreement) and Allis-Chal-mers (for breach of the subcontract). Rapi-dan/Actaeon thereafter sued JBC for breach of the agreement, NESCO/Trans-port for payment under the force majeure policies, and Allis-Chalmers for damages as a result of alleged delays in delivery of equipment.

Rapidan/Actaeon filed proofs of loss with NESCO/Transport for 187 days of force majeure delays. At some point, NES-CO/Transport paid Rapidan/Actaeon $124,-000, calculated as follows: $374,000 (187 days of delay at $2,000 per day) minus a $250,000 deductible (representing the assumed liability of Allis-Chalmers).

In April 1987, Rapidan/Actaeon moved for partial summary judgment against NESCO/Transport, asserting that a $100,-000 deductible should have been applied to this payment instead of $250,000. The trial court found that there was no just reason for delay, and judgment was entered against NESCO/Transport in the amount of $150,000. The trial court subsequently dismissed a motion by NESCO/Transport for rehearing. This appeal followed.

ISSUE

Did the trial court err in granting summary judgment?

ANALYSIS

1. The first issue in this case involves the cause of a portion of the 187-day delay. In the memorandum attached to its order dismissing NESCO/Transport’s motion for rehearing, the trial court stated:

[Deposition evidence shows that a total of 187 days of force majeure delay was incurred of which 127 days was by reason of the labor strike and the balance of delay was for other reasons.

On appeal, NESCO/Transport contend that in this statement the trial court acknowledges that the cause of the remaining 60-day delay has not been determined. NES-CO/Transport therefore argue that an issue of fact exists as to the nature of the delays incurred during this 60-day period *728 and that the court erred in granting partial summary judgment.

NESCO/Transport claim that the additional 60 days of delay were caused by failure of the seals in the Allis-Chalmers turbine generators. 2 If Allis-Chalmers was at fault for such a delay, NESCO/Trans-port might be entitled to a higher deductible represented by Allis-Chalmers’ liability. However, NESCO/Transport submitted no evidence in support of their claim.

More importantly, NESCO/Transport failed to challenge the evidence submitted by Rapidan/Actaeon in support of its motion for partial summary judgment. That evidence included a letter dated September 13, 1984 from JBC to Rapidan/Actaeon in which JBC outlined the specific reasons they were requesting a 187-day force maj-eure extension of the project’s substantial completion date. This letter 3 indicates that the entire 187-day delay was caused by strikes, high water problems, and severe weather conditions; there is no suggestion that any portion of the delay was caused by failure of the Allis-Chalmers seals.

Minn. R.Civ.P. 56.05 provides in part: When a motion for summary judgment is made and supported as provided by Rule 56, an adverse party may not rest upon the mere averments or denials of his pleading but must present specific facts showing that there is a genuine issue for trial. If he does not so respond, summary judgment, if appropriate, shall be entered against him.

Given NESCO/Transport’s failure to properly challenge the letter explaining the causes of the 187-day delay, we conclude that there is no genuine issue of fact on this issue. 4 NESCO/Transport cannot rely upon mere allegations that the 60-day delay is due to a defect in Allis-Chalmers’ equipment.

2. The second issue in this case involves the amount of the deductible to be applied to Rapidan/Actaeon’s claim under the force majeure policies. The construction and interpretation of contracts and insurance policies are questions of law for the court to decide. Hunt v. IBM Mid America Employees Federal Credit Union, 384 N.W.2d 853, 856 (Minn.1986); Iowa Kemper Insurance Co. v. Stone, 269 N.W.2d 885, 886-87 (Minn.1978).

Both policies provide for the following deductibles: if no party is at fault, the deductible is $100,000; if JBC or Allis-Chal-mers is liable for a delay, the deductible equals the amount of that party’s respective liability. Under the terms of the construction agreement between Rapidan/Ac-taeon and JBC, it is undisputed that JBC is not liable for force majeure delays.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Bank of St. Paul v. Coating Specialties, Inc.