Johnson Aircrafts, Inc. v. Wilborn

190 S.W.2d 426, 1945 Tex. App. LEXIS 573
CourtCourt of Appeals of Texas
DecidedOctober 5, 1945
DocketNo. 14710.
StatusPublished
Cited by23 cases

This text of 190 S.W.2d 426 (Johnson Aircrafts, Inc. v. Wilborn) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson Aircrafts, Inc. v. Wilborn, 190 S.W.2d 426, 1945 Tex. App. LEXIS 573 (Tex. Ct. App. 1945).

Opinion

SPEER, Justice.

F. E. Wilborn, John C. Sanders, W. O. Wilborn, and W. R. Cox sued Johnson Air-crafts, Inc., a corporation, for expenses paid for labor growing out of a written contract made between the named corporation and F. E. Wilborn, W. F. Oliver, and John C. Sanders under which contract the corporation employed the last three named parties to build and construct parts of a plane the corporation had designed; allegations are made that those instituting the suit were the owners of the account.

Johnson Aircrafts, Inc., has appealed from an adverse judgment entered on a jury verdict rendered on three special issues submitted. The corporation will be referred to as appellant and plaintiffs who instituted the suit will be called appellees.

The written contract out of which this controversy arose is rather lengthy and bore date of March 18, 1943. Obviously it was designed to cover many contingencies. We shall refer to pertinent parts of it without setting it out in full. Among other things it provided for the manufacture by appellees of certain parts of the “control surface” of an aeroplane appellant had designed; appellant agreed to furnish space in its plant for appellees to perform the contract; appellees agreed to furnish all “equipment,” “jigs,” and “fixtures” necessary to manufacture the parts contemplated; appellees were to be compensated for the manufacture of said parts either (1) at a cost plus plan, (2) upon a fixed price per unit, or (3) per ship, as may be determined by the mutual consent of both parties (appellant and appellees), after appellees shall have manufactured for appellant and it had received ten ships; settlement for work and said manufacturing to he made according to schedule of Government contracts. [Emphasis ours.) Appellees were to furnish all payroll money used by them prior to the time actual production shall have begun on said ships; but that when production had begun, appellant would furnish funds for payrolls. There is a condition in the contract that appellees will “pay” (loan) to appellant $5000 to be repaid by appellant on or before six months with interest at six per cent per annum. The contract was to last for the duration of the present war, and if appellant began a program of building commercial planes, the parties would negotiate with each other for a continuation of the contract. That the “jigs” and “machines” (made by appellees) shall be the property of appellant and appellees may not remove them from appellant’s plant, and further: “However, the party of the second part *428 (appellees) shall have the right of reimbursement for any amount of money expended by him (them) in labor in building, erecting and manufacturing said jigs and machines.” There is a further provision in the contract to the effect that such work, manufacture and production of parts by ap-pellees, should be under the supervision of appellant and in harmony with its engineering standards.

The record discloses that appellees did loan appellant the $5000 provided for in the contract, and perhaps as much as $8000 more subsequent to the execution of the contract. On August 28, 1944, appellees sued appellant for amounts alleged to be owing for borrowed money and for $4187.52 for labor expended in the manufacture of certain jigs, machines and fixtures which they asserted they had obligated themselves to make and manufacture, under the contract; they attempted to show the necessity for and asked that a receiver be appointed to wind up appellant’s business. Apparently appellant paid to appellees the borrowed •money with interest after suit was filed, and on September 8, 1944, appellees filed their first amended petition omitting the borrowed money items and prayer for receivership, and sought only a recovery of the $4187.52 item for labor in the manufacture of the parts.

Appellant, as defendant below, answered with general denial, special pleas in defense and a cross action for damages for alleged libelous statements made by appellees claimed to be injurious to appellant’s good name and credit. For lack of evidence the court found against appellant on its cross action and no complaint is made thereof on this appeal, and we need not give it further attention. We have mentioned this phase of the case only because of a paragraph ia appellant’s answer, to which we shall later refer.

Appellant answered by admitting the execution of the contract of March 18, 1943; that there was a controversy between it and appellees on and prior to August 28, 1942 (obviously an erroneous date) ; that appellant claimed it did not owe appellees any sum whatever and that appellees claimed it owed $4187.52. We think it necessary to copy paragraph 6 of the answer because of contentions raised on appeal. That paragraph reads:

“Defendant denies each and every allegation in said petition contained, and here now alleges that the work alleged to have been performed, and service alleged to have been rendered by the plaintiffs herein under the terms of said contract and agreement were not according to specifications which had been theretofore laid down by the defendant in accordance with said contract, and that the completed product and services rendered was of no value to the defendant herein; that under the terms of said contract the plaintiffs herein were to furnish all labor, material and equipment for the erection of certain jigs and forms, which said jigs and forms were to be delivered to the defendant herein and all costs for the preparation thereof were to be paid for by the plaintiffs, and when said jigs and other equipment and fixtures and manufactured products were accepted by the defendant then the defendant was to pay for the same, and the defendant alleges that such manufactured products, jigs and fixtures, when so delivered if the same were delivered, were not according to the specifications and plans outlined by the defendant to the plaintiffs and were by the defendant rejected, and therefore the defendant alleges that it is not indebted to the plaintiffs in any sum of money whatsoever.”

Points one and two relied upon by appellant for reversal are said by it to be “under assignment of error Ño. one.” That assignment asserted error of the trial court in overruling its motion .for an instructed verdict because “under the terms of the contract between the parties no amount of money ever became due.” The reconstructed assignment of eri'or was taken from the first paragraph of appellant’s amended motion for new trial. The motion for new trial constitutes the assignments of error to be reviewed by the appellate court. Rule 374, Texas Rules Civil Procedure. A “point” relied upon must be germane to one or more assignments of error. Rule 418, T.R.C.P. It must follow that to entitle a point to consideration there must be an assignment of error. We then look to the alleged assignment of error to ascertain if the court erred in the matters complained of in the assignment. Did the court err in overruling appellant’s motion for an instructed verdict ? At the close of appellees’ testimony and also at the close of all evidence, appellant filed a motion requesting the court to instruct a verdict in its favor. No grounds for the request were included in the motions. The court entered no order thereon but marked them “Refused” dating and signing same. Rule 268, T.R.C.P. pro *429

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Emery Waterhouse Co. v. Lea
467 A.2d 986 (Supreme Judicial Court of Maine, 1983)
Crozier v. Horne Children Maintenance and Educational Trust
597 S.W.2d 418 (Court of Appeals of Texas, 1980)
Texas Bank & Trust Co. of Dallas v. Custom Leasing, Inc.
498 S.W.2d 243 (Court of Appeals of Texas, 1973)
Granato v. Bravo
498 S.W.2d 499 (Court of Appeals of Texas, 1973)
Seamless Floors by Ford, Inc. v. Value Line Homes, Inc.
438 S.W.2d 598 (Court of Appeals of Texas, 1969)
Schad v. Williams
398 S.W.2d 603 (Court of Appeals of Texas, 1965)
Copeland v. Ogle
372 S.W.2d 731 (Court of Appeals of Texas, 1963)
Bell v. Spraggins
372 S.W.2d 740 (Court of Appeals of Texas, 1963)
Reid v. Nortex Construction Company
366 S.W.2d 870 (Court of Appeals of Texas, 1963)
Jones v. Hortenstine
291 S.W.2d 761 (Court of Appeals of Texas, 1956)
De Busk v. Quest
290 S.W.2d 569 (Court of Appeals of Texas, 1956)
Carmichael v. Williams
286 S.W.2d 456 (Court of Appeals of Texas, 1956)
Dollie Adams Oil Corp. v. Cree
279 S.W.2d 619 (Court of Appeals of Texas, 1955)
Southwestern Bell Tel. Co. v. Shell
266 S.W.2d 476 (Court of Appeals of Texas, 1954)
State v. Camper
261 S.W.2d 465 (Court of Appeals of Texas, 1953)
Goldman v. Campbell
249 S.W.2d 633 (Court of Appeals of Texas, 1952)
Craft v. Hahn
246 S.W.2d 897 (Court of Appeals of Texas, 1952)
Carter v. Old Faithful County Mut. Fire Ins. Co.
243 S.W.2d 215 (Court of Appeals of Texas, 1951)
Miller v. Long-Bell Lumber Co.
217 S.W.2d 867 (Court of Appeals of Texas, 1949)
Ligon v. Green
206 S.W.2d 629 (Court of Appeals of Texas, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
190 S.W.2d 426, 1945 Tex. App. LEXIS 573, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-aircrafts-inc-v-wilborn-texapp-1945.