John W. Mecom, Cross-Appellant v. Levingston Shipbuilding Company, Cross-Appellee

622 F.2d 1209, 1980 U.S. App. LEXIS 15164
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 4, 1980
Docket78-3154
StatusPublished
Cited by45 cases

This text of 622 F.2d 1209 (John W. Mecom, Cross-Appellant v. Levingston Shipbuilding Company, Cross-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John W. Mecom, Cross-Appellant v. Levingston Shipbuilding Company, Cross-Appellee, 622 F.2d 1209, 1980 U.S. App. LEXIS 15164 (5th Cir. 1980).

Opinion

JOHN W. PECK, Circuit Judge.

This is an appeal from a judgment entered by a district court sitting in admiralty for damages arising out of the sinking of a barge in the Sabine River in Orange, Texas. The defendant contends that damages should be limited to the reasonable cost of removing the vessel from the river in the most efficient manner at the time the incident occurred. It further asserts that this action is barred by laches. Plaintiff cross-appeals, arguing that he is entitled to recover all expenses associated with his three unsuccessful attempts to remove the vessel from a navigable channel. Plaintiff also cross-appeals from the denial of prejudgment interest and the allowance of a set-off against his damage award for repairs to the barge that were performed by defendant prior to its sinking. We affirm in part and reverse in part.

In January, 1973, the plaintiff, John W. Mecom, raised his submersible drilling barge, Rig 25, after a long period of nonuse, and towed it to defendant’s shipyard. Once *1211 there, it was placed in drydock and surveyed for damage to its hull and bottom. Upon learning that the state of deterioration made the prospect of repairing the barge uneconomical, Mecom instructed defendant, Levingston Shipbuilding Company (Levingston), to repair all holes found or cut in the hull. His intent was to tow the rig to another location for use as a dock barge or jetty.

Levingston made repairs to the hull, and, on February 15, 1973, removed the barge from drydock, located at the northern end of Orange Harbor Island, at Orange, Texas, and towed it to the southern end of the island. Levingston’s dockmaster and his crew moored the barge to the bank of the island with manila ropes, intending to return with anchors and steel cables to further secure the vessel. Before they returned, however, the rig slipped off the mudflat where it had been placed and into a side branch of the Sabine River channel, a navigable waterway, where it sank with only a portion of the superstructure remaining above water.

Levingston was immediately notified of the sinking and thereafter conducted a thorough investigation into its cause. Me-com informed Levingston that he intended to hold it liable for the sinking. He also demanded that the defendant take such remedial measures as the law required, including the removal of the barge from the channel. Levingston responded, denying liability, but offering to raise the barge at Mecom’s expense. Plaintiff refused this offer.

On June 23, 1973, the United States Army Corps of Engineers sent Mecom a notice that Rig 25 was obstructing navigation. The letter demanded that plaintiff remove or salvage the barge as required by the Rivers and Harbors Appropriation Act of 1899, 33 U.S.C. § 409, 1 and advised that the government would take action to remove it in the event Mecom failed to act. Shortly thereafter, Mecom contracted to remove the barge with a marine salvor, Ben Wyly, who had worked for plaintiff at various times over a several year period.

Wyly and his crew began operations to drag Rig 25 out of the navigable portion of the river in September or October of 1973. This effort continued through March of 1974, when, after dragging the rig 40 feet, the pulling tackle broke. Mr. Wyly testified that it was impossible to pull the barge any farther because of the steep slope of the river bottom. Wyly had requested a crane mounted on a barge to dig a 120 foot slip into which Rig 25 could be dragged. He testified that the only such crane in the area belonged to Mecom, but that it was temporarily unavailable because it was being used on another job at a distant location. Consequently, from March through the end of 1974, Wyly’s efforts were confined to maintaining and rerigging the vessel, using a skeleton crew, while awaiting the arrival of the needed piece of equipment.

While waiting for the crane, Mecom heard of a polyurethane foam injection process, successfully used by the military to refloat sunken ships. After consulting with a manufacturer of the product, preparing *1212 the vessel, obtaining the proper equipment, and testing the foam at the site, Wyly attempted to refloat Rig 25 by injecting the foam into its hull. This effort lasted throughout 1975 and it too ended unsuccessfully. When this attempt failed, Wyly returned to the original dragging operation. He eventually obtained the crane needed to dig the slip, but his dragging activity was halted by the Coast Guard sometime in 1976 because of the pollution it was creating.

Mecom filed suit in October 1975, two years and eight months after the barge sank. In his final amended complaint, he demanded reimbursement for all of his removal expenses, amounting to $345,439 through 1976. Levingston denied liability in its answer and counterclaimed in the amount of $18,844 for the repairs made to plaintiff’s rig prior to its sinking. The case was tried to the district court upon the issue of liability. Damages and laches were issues upon which a special master took evidence. The court concluded that Levingston was negligent in failing to adequately secure the rig. It adopted the special master’s report in full, concluding that plaintiff should recover fully the $97,552 spent on the first ill-fated recovery attempt, up to the point at which the pulling tackle broke in March of 1974. Plaintiff’s further expenses were denied as imprudent. In addition, the court granted Mecom $110,000, representing the present cost of removing the barge from the river. The laches issue was decided adversely to the defendant, the court finding that Levingston suffered no prejudice as a result of plaintiff’s delay in filing his complaint. Levingston did prevail on its counterclaim for repairs, and Mecom was denied prejudgment interest on his damage award. Prom that judgment, both parties have perfected this appeal. Only the court’s finding on the issue of liability is unchallenged here.

The Present Cost of Removal

The district court awarded Mecom $110,000 as the present cost of removing Rig 25 from the Sabine River channel. The award was premised upon Mecom’s continuing duty to raise the vessel under § 15 of the Rivers and Harbors Appropriation Act of 1899, 33 U.S.C. § 409. At the time of hearing on damages before the special master, plaintiff had entered into a $110,000 contract for the removal of the barge, which the court found to be conclusive evidence on the cost of removal. Subsequent to the issuance of the master’s report, but prior to the entry of judgment by the district court, however, Mecom abandoned Rig 25 to the government as permitted by § 15 of the Act. This circumstance, which was brought to the attention of the district court by the plaintiff, should have resulted in the court’s deletion of this item of damages from the award.

In the recent case of Tennessee Valley Sand & Gravel Co. v. M/V Delta, 5 Cir. 1979, 598 F.2d 930, 934, this Court reviewed the principles governing the obligations and liability of a non-negligent owner of a sunken vessel. There, we said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sunglory Maritime, Ltd. v. PHI, Inc.
212 F. Supp. 3d 618 (E.D. Louisiana, 2016)
Olivette Coffey, Jr. v. Dwight Braddy
834 F.3d 1184 (Eleventh Circuit, 2016)
Rondeno v. Law Office of William S. Vincent
111 So. 3d 515 (Louisiana Court of Appeal, 2013)
Great Lakes Business Trust v. M/T Orange Sun
855 F. Supp. 2d 131 (S.D. New York, 2012)
Louisiana v. Rowan Companies, Inc.
728 F. Supp. 2d 896 (S.D. Texas, 2010)
Transmontaigne Product Services, Inc. v. M/V Wilbur R. Clark
679 F. Supp. 2d 1308 (S.D. Alabama, 2009)
Powell v. Global Marine, LLC
671 F. Supp. 2d 830 (E.D. Louisiana, 2009)
Sweet Pea Marine, Ltd. v. APJ Marine, Inc.
411 F.3d 1242 (Eleventh Circuit, 2005)
SL Service, Inc. v. International Food Packers, Inc.
217 F. Supp. 2d 180 (D. Puerto Rico, 2002)
Settoon Marine, Inc. v. Great Lakes Dredge & Dock Co.
657 So. 2d 537 (Louisiana Court of Appeal, 1995)
General Electric Co. v. Inter-Ocean Shipping
862 F. Supp. 166 (S.D. Texas, 1994)
Interocean Ships, Inc. v. Samoa Gases
26 Am. Samoa 2d 28 (High Court of American Samoa, 1994)
Musumeci v. Penn's Landing Corp.
640 A.2d 416 (Superior Court of Pennsylvania, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
622 F.2d 1209, 1980 U.S. App. LEXIS 15164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-w-mecom-cross-appellant-v-levingston-shipbuilding-company-ca5-1980.