John Snow, Inc. v. United States

78 Fed. Cl. 763, 2007 U.S. Claims LEXIS 329, 2007 WL 3033638
CourtUnited States Court of Federal Claims
DecidedOctober 12, 2007
DocketNo. 06-97C
StatusPublished

This text of 78 Fed. Cl. 763 (John Snow, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Snow, Inc. v. United States, 78 Fed. Cl. 763, 2007 U.S. Claims LEXIS 329, 2007 WL 3033638 (uscfc 2007).

Opinion

OPINION AND ORDER

WHEELER, Judge.

This case arises from a 1998 cost-plus-fixed-fee contract between Plaintiff John Snow, Inc. (“JSI”) and the United States Agency for International Development (“USAID”) to implement a program aimed at reducing neonatal and maternal mortality in Egypt. The contract contained a list of tasks that JSI would perform, and milestone completion dates for each task. In performing one of the tasks, JSI shipped 119 Preemicare incubators to Egypt during January through April 2002, and installed the incubators in various Egyptian healthcare facilities during May through July 2002. Shortly after installation, healthcare facilities staff reported that some of the incubators were experiencing problems such as overheating, erratic data display boards, and malfunctioning alarms. JSI thereupon attempted to repair the incubators, and later removed them from service. During the next 2-1/2 years, JSI together with its subcontractor and manufacturer, attempted to determine the extent and causes of the malfunctions and to repair and test the incubators.

After first paying JSI for the costs of the incubators in 2002, USAID’s Contracting Officer issued a final decision on March 9, 2005 disallowing these costs, and USAID then recouped $872,327.18 from JSI through administrative offsets. JSI has moved for partial summary judgment on its breach of contract claim, arguing that even if the incubators were defective, USAID failed to act in a timely manner to disallow the costs. Although acknowledging that genuine fact issues exist on whether the incubators performed properly, JSI contends that applicable Federal Acquisition Regulation (“FAR”) contract clauses prohibit USAID from disallowing costs nearly three years after accepting the incubators. In response, Defendant asserts that JSI breached the contract by delivering nonconforming incubators. Defendant denies that USAID ever accepted the incubators, and argues that disallowing the costs was a reasonable and lawful response to JSI’s breach.

JSI brought suit in this Court on February 6, 2006, and filed its Motion for Partial Sum[764]*764mary Judgment on October 26, 2006. After conducting limited discovery pursuant to Rule 56(f), Defendant filed its Response to JSI’s motion on June 29, 2007, and JSI filed its Reply on August 31, 2007. At the September 19, 2007 oral argument, the Court denied from the bench JSI’s motion for partial summary judgment, and advised the parties that this opinion would follow. For the reasons explained below, the Court concludes that genuine issues of material fact exist, and that resolution of this matter by summary judgment is precluded. Accordingly, JSI’s Motion For Partial Summary Judgment is DENIED.

Factual Background1

JSI is an experienced government contractor based in Boston, Massachusetts, providing assistance to public health programs worldwide. In 1998, JSI entered into Contract No. 263-C-0098-00041-00 with USAID, a cost-plus-fixed fee completion form of contract to provide equipment and services to the Egyptian Ministry of Health Programs (“MOHP”). See FAR ¶ 16.306(d). The contract incorporated by reference many standard FAR clauses, including FAR ¶ 52.212-4, “Contract Terms and Conditions — Commercial Items (May 1997)” (“Commercial Items” clause), and FAR ¶ 52.246-3, “Inspection of Supplies — Cost Reimbursement (April 1984)” (“Inspection” clause). Under the contract, JSI procured 119 Preemicare neonatal incubators from a subcontractor, ICS Technologies, Inc. (“ICS”), in 2001 for $785,880.35. USAID approved the ICS subcontract, but the parties disagree on whether the subcontract approval also constituted approval of the incubators.

ICS delivered the incubators to Egypt in three shipments, and they cleared Egyptian customs on January 26, 2002, February 12, 2002, and April 29, 2002 respectively. Thereafter, JSI stored the incubators in its own building until installing them in healthcare facilities throughout Egypt during May through July 2002. Shortly after installation, MOHP’s staff began experiencing problems with the incubators, such as overheating, erratic data display boards, and malfunctioning alarms. On September 24, 2002, JSI met with ICS and Preemieare’s local representative, Hi-Med, to attempt to resolve these problems.

In December 2002, Preemicare sent an engineer to Egypt to investigate and remedy the problems reported by MOHP. The engineer issued a report on January 7, 2003 recommending that retrofits be done at Preemicare’s cost. On January 13, 2003, Hi-Med sent a letter to JSI expressing concern for the safety of the incubators and recommending that all incubators be removed from service until modifications could be made. JSI shared this information with MOHP and USAID, and the following day, January 14, 2003, MOHP ordered all facilities to remove the incubators from service to allow JSI to examine and retrofit them. JSI removed all the incubators from Egyptian facilities and stored them during the retrofitting process. Preemicare’s engineer completed the retrofit and issued certifications for 112 incubators by August 2003.

Before returning the certified incubators to Egyptian healthcare facilities, JSI retained ECRI, a U.S. non-profit health services research agency based in Plymouth Meeting, Pennsylvania, to conduct an independent study of the incubators. ECRI found an overall failure rate of 90 percent among the 44 incubators tested, and recommended to JSI on May 25, 2004 that the incubators not be used in patient care. The ECRI report concluded in part that “[hjealthcare organizations in the United States would not accept these incubators for clinical care----” Def.’s June 29, 2007 Response, App. at 231.

On September 29, 2004, representatives of MOHP, USAID, and JSI met and agreed upon a plan to return the incubators to service. Beginning in October 2004, JSI undertook additional efforts to repair and modify the incubators to comply with the ECRI test protocols. In spite of these efforts, USAID issued JSI a notice of intent to disallow the cost of the incubators on November 1, 2004. Four months later, on March 9, 2005, after [765]*765failing to reach a negotiated agreement with JSI, USAID’s Contracting Officer issued a final decision disallowing the cost of the incubators and stating that JSI was indebted to the U.S. Government in the amount of $872,327.18 ($785,880.35 for the incubators + $23,576.41 fee + $62,870.43 procurement services charge). USAID collected the amount due plus interest from JSI through administrative offsets in 2005.

In its February 6, 2006 two-count Complaint, JSI alleged breach of contract and breach of the implied covenant of good faith and fair dealing. JSI contends in its Motion for Partial Summary Judgment that the applicable FAR contract clauses require the Court to find that USAID breached the contract when the Contracting Officer issued the final decision to disallow the cost of the incubators, and collected the debt of $872,327.18 through administrative offsets.

Discussion

A. Standard for Decision

Summary judgment is appropriate only when (1) no genuine issue of material fact exists, and (2) the moving party is entitled to judgment as a matter of law. See RCFC 56(c); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986); Telemac Cellular Corp. v. Topp Telecom, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Telemac Cellular Corporation v. Topp Telecom, Inc.
247 F.3d 1316 (Federal Circuit, 2001)
Eli Lilly And Company v. Barr Laboratories, Inc.
251 F.3d 955 (Federal Circuit, 2001)
Lathan Co. v. United States
36 Cont. Cas. Fed. 75,842 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
78 Fed. Cl. 763, 2007 U.S. Claims LEXIS 329, 2007 WL 3033638, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-snow-inc-v-united-states-uscfc-2007.