John R. Sand & Gravel Co. v. United States

60 Fed. Cl. 347, 2004 U.S. Claims LEXIS 78, 2004 WL 785047
United States Court of Federal Claims·Decided April 13, 2004·No. No. 02-509 L·Published·Cited by 1 cases

Opinion

ORDER

HEWITT, Judge.

The court has before it Motion of the Members of the Metamora Group for Stay Pending Appeal (stay motion or Stay Mot.), plaintiffs and defendant’s responses thereto (plaintiffs response or PL’s Resp. and defendant’s response or Def.’s Resp., respectively), and Reply of the Members of the Metamora Group in Support of Them Motion for Stay Pending Appeal (reply or Reply). For the following reasons, the stay motion is DENIED.

The court has now had two full opportunities to consider whether or not the Metamora Group should be joined as a party in this case and has twice decided that the Metamora Group should not be joined; first, because the Metamora Group itself sought intervention untimely under Rule 24 of the Rules of the United States Court of Federal Claims (RCFC), John R. Sand & Gravel Co. v. United States, 59 Fed.Cl. 645, 652 (2004), and, second, because the United States untimely requested the court to provide the Metamora Group notice and an opportunity to intervene under RCFC 14(b)(1), John R. Sand & Gravel Co. v. United States, 60 Fed. CL 272, 272-73, 2004 WL 785051, at *1-2 (2004).1 The pretrial conference in this matter is four weeks away and trial is scheduled to begin on May 18, 2004 in Detroit.

[349]*349The parties generally agree, Stay Mot. at 2, PL’s Resp. at 3-4, Def.’s Resp. at 3, that a four-factor test applies to this court’s decision to grant a stay pending appeal of this court’s denial of a motion to intervene:

“(1) whether the stay applicant has made a strong showing that he is likely to succeed on the merits; (2) whether the applicant will be irreparably injured absent a stay; (3) whether issuance of the stay will substantially injure the other parties interested in the proceeding; and (4) where the public interest lies.”

Standard Havens Prods., Inc. v. Gencor Indus., Inc., 897 F.2d 511, 512 (Fed.Cir.1990) (quoting Hilton v. Braunskill, 481 U.S. 770, 776, 107 S.Ct. 2113, 95 L.Ed.2d 724 (1987)).2 The court addresses the four factors in turn.

For the reasons stated in its prior opinions, the court does not believe that the Metamora Group is likely to succeed on the merits. This litigation has moved and continues to move steadily toward trial. The delay of the Metamora group in seeking to join the case must be considered in the context of the actual litigation schedule. The Metamora Group knew of the litigation and apparently decided to take a chance that a non-judicial resolution or summary judicial resolution would occur. In the circumstances of this case, the court has found the Metamora Group’s motion to intervene, whether as of right or permissively, untimely.3 The court has also concluded that the Metamora Group, which must have acted on behalf of the United States in respect to plaintiffs takings claim, is not entitled to appear separately from the United States.

It is difficult to see how the Metamora Group would be irreparably injured absent a stay. The court recently entered a revised protective order (styled a “Confidentiality Agreement”) to permit defendant to provide copies of confidential information of plaintiff to the Metamora Group. Order of April 9, 2004, Exhibit A. The court has also stated:

Of course there is no reason why the United States should not call on the members of the Metamora Group or others engaged in the remediation, and the agents (including counsel) of any of them, for assistance in the defense of the suit, whether as witnesses, experts, or otherwise. The court merely holds that such persons and entities, in the circumstances of this case, are not appropriately joined with the United States as parties defendant.

John R. Sand & Gravel Co. v. United States, 60 Fed.Cl. 272, 275, 2004 WL 785051, at *2-3 (2004). It is clear that the United States and the Metamora Group are cooperating in the defense of the suit.

The Metamora Group argues that plaintiff would not be disadvantaged by a stay because pre-judgment interest is available in a takings claim, Reply at 9, and suggests that delay would only be harmful where “the directly interested parties ‘are otherwise ready to move forward,”’ id. (emphasis supplied) (quoting Am. Mar. Transp., Inc. v. United States, 15 Cl.Ct. 360, 361 (1988)). The plain[350]*350tiff in this ease is ready to move forward and, except in the context of the motion practice with respect to the proposed intervention of the Metamora Group, the United States has not sought a stay or a delay of the trial schedule. The court does not regard the availability of pre-judgment interest as a significant factor to support a stay not otherwise supported.

The court believes that the public interest favors the denial of the motion to stay. The court believes it is a subject of concern that a party whose property may have been taken by the United States for a public purpose could, in connection with its prosecution of its Constitutional claim, be required to prevail not only against the United States, but against a large array of entities who served, in effect, as the agents of the United States in the actions that form the basis for the takings claim. The United States may wish to “privatize” the defense of a takings claims. John R. Sand & Gravel Co. v. United States, 60 Fed.Cl. 272, 274-75, 2004 WL 785051, at *2 (2004). The court has been provided, however, with no reason why the public interest is served thereby.

IT IS SO ORDERED.

Free access — add to your briefcase to read the full text and ask questions with AI

John R. Sand & Gravel Co. v. United States, 60 Fed. Cl. 347, 2004 U.S. Claims LEXIS 78, 2004 WL 785047 (uscfc 2004).