John Morgan Construction Co. v. McDowell

813 P.2d 138, 62 Wash. App. 79, 1991 Wash. App. LEXIS 272
CourtCourt of Appeals of Washington
DecidedJuly 29, 1991
DocketNo. 25494-4-I
StatusPublished
Cited by1 cases

This text of 813 P.2d 138 (John Morgan Construction Co. v. McDowell) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Morgan Construction Co. v. McDowell, 813 P.2d 138, 62 Wash. App. 79, 1991 Wash. App. LEXIS 272 (Wash. Ct. App. 1991).

Opinion

Grosse, C.J.

John Morgan Construction Co., Inc., and Helen E. Plastino (hereinafter referred to collectively as Morgan Construction) appeal from a summary judgment denying their motion to permanently enjoin respondent Brock A. McDowell, d/b/a Brock A. McDowell Co. (McDowell), from enforcing a judgment foreclosing a mechanics' lien. Morgan Construction contends that the trial court erred in concluding that McDowell did not have to file a lis pendens to enforce a mechanics' lien as against parties who purchase the affected property more than 8 months after the filing of a notice of claim of lien but prior to foreclosure of the lien. We affirm.

The relevant facts are undisputed. In 1986 McDowell, an excavation contractor, contracted with Windsor Development, Inc., to install sewers and storm drains on a 4-lot short plat owned by Windsor. Shaffer Crane, Inc., another contractor on the project, filed a claim of lien against lot 2 of the development on March 9, 1987. On April 28, 1987, McDowell filed an amended claim of lien for labor and materials against the entire short plat.

On September 21, 1987, Shaffer Crane commenced an action to foreclose its lien against lot 2. Shaffer Crane [81]*81also filed a lis pendens. In October of 1987, McDowell filed a complaint in intervention in the lawsuit commenced by Shaffer Crane, seeking to foreclose its lien against the entire short plat. McDowell did not file a lis pendens. In January 1988, Windsor sold lot 3 of the short plat. McDowell agreed to release its lien on lot 3 in exchange for partial payment of the amount alleged to be unpaid.

In April 1989, appellant John Morgan Construction purchased lot 4B1 of the short plat from Windsor. In May 1989, appellant Helen Plastino purchased lot 1. Both appellants maintain that they did not have actual knowledge of McDowell's claim of lien or of the pending foreclosure action at the time they purchased the lots from Windsor.

The foreclosure action was tried on September 7, 1989, at which time McDowell apparently learned of the sale of lots 1 and 4B. The trial court entered a judgment in McDowell's favor totaling $6,693.57, plus attorney fees, and upholding the validity of McDowell's lien. A judgment on priority and a decree of foreclosure were entered on October 11, 1989.

On October 24, 1989, Morgan Construction filed a motion for order to show cause seeking to restrain McDowell from executing on the judgment against its lots. An order granting the requested restraint, pendente lite, was entered on November 15, 1989. Morgan Construction then moved for summary judgment seeking to enjoin McDowell permanently from enforcing its judgment against lots 1 and 4B "because the plaintiffs [Morgan Construction] were innocent purchasers of the subject property, in good faith and for value, and as such are protected by the lis pendens statute." Cross motions for summary judgment were heard on December 8, 1989. The trial court denied Morgan Construction's motion and [82]*82granted McDowell's motion, striking the temporary restraining order and dismissing Morgan Construction's action.

On appeal, Morgan Construction maintains that it was a bona fide purchaser of the property who took free of McDowell's lien foreclosure judgment. In essence, Morgan Construction invites this court to engraft an additional condition on RCW 60.04, the mechanics' liens statute, requiring lien claimants to file a lis pendens upon commencing a foreclosure action in order to enforce the lien against those who purchase the property during a pending foreclosure action with constructive knowledge of the claim of lien, but without actual knowledge of the foreclosure action. We decline the invitation.

A bona fide purchaser for value is "one who without notice of another's claim of right to, or equity in, the property prior to his acquisition of title, has paid the vendor a valuable consideration.'" Miebach v. Colasurdo, 102 Wn.2d 170, 175, 685 P.2d 1074 (1984) (quoting Glaser v. Holdorf, 56 Wn.2d 204, 209, 352 P.2d 212 (1960)). Notice in this sense, however, is not actual notice:

"It is a well-settled rule that where a purchaser has knowledge or information of facts which are sufficient to put an ordinarily prudent man upon inquiry, and the inquiry, if followed with reasonable diligence, would lead to the discovery of defects in the title or of equitable rights of others affecting the property in question, the purchaser will be held chargeable with knowledge thereof and will not be heard to say that he did not actually know of them. In other words, knowledge of facts sufficient to excite inquiry is constructive notice of all that the inquiry would have disclosed."

(Italics ours.) Miebach v. Colasurdo, 102 Wn.2d at 175-76 (quoting Peterson v. Weist, 48 Wash. 339, 341, 93 P. 519 (1908)).

Here, Morgan Construction does not dispute that it had constructive notice of McDowell's claim of lien. As [83]*83this court has observed in a similar context, constructive notice of a recorded claim of hen is sufficient to put a party on inquiry notice

to investigate the status of . . . recorded liens. It did not do so. Had it done so it would have discovered those hens had priority over its more recent judgment lien and that a foreclosure action was pending with respect to those liens.

R.O.I., Inc. v. Anderson, 50 Wn. App. 459, 463, 748 P.2d 1136 (1988). Because it had constructive notice of McDowell's claim of lien, Morgan Construction's assertion that it is a bona fide purchaser fails.

A mechanics' lien arises and attaches upon the performing of labor or furnishing of materials. RCW 60.04-.010. In order to perfect and eventually enforce such a lien, a claimant must follow a series of detailed statutory requirements, including the recording of a claim of lien with the auditor of the county in which the property is located within 90 days of the cessation of labor. RCW 60.04.060. In addition,

[n]o lien created by [RCW 60.04] binds the property subject to the lien for a longer period than eight calendar months after the claim has been filed unless an action be commenced in the proper court within that time to enforce such lien ....

RCW 60.04.100.

When a claimant follows the requirements of RCW 60.04, including the timely recording of a claim of lien, and then commences an enforcement action within 8 months of the claim of lien, the lien binds the property from the time labor was first performed and has priority over "any lien, mortgage or other incumbrance which may attach subsequently to the time of the commencement of the performance of the labor . . .".

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Park South LLC v. Denali Construction LLC
Court of Appeals of Washington, 2024

Cite This Page — Counsel Stack

Bluebook (online)
813 P.2d 138, 62 Wash. App. 79, 1991 Wash. App. LEXIS 272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-morgan-construction-co-v-mcdowell-washctapp-1991.