John McShain, Inc. v. L'Enfant Plaza Properties, Inc.

402 A.2d 1222, 1979 D.C. App. LEXIS 380
CourtDistrict of Columbia Court of Appeals
DecidedJune 5, 1979
Docket12462, 12642
StatusPublished
Cited by20 cases

This text of 402 A.2d 1222 (John McShain, Inc. v. L'Enfant Plaza Properties, Inc.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John McShain, Inc. v. L'Enfant Plaza Properties, Inc., 402 A.2d 1222, 1979 D.C. App. LEXIS 380 (D.C. 1979).

Opinion

GALLAGHER, Associate Judge:

L’Enfant Plaza Properties, Inc. (L’En-fant) sued John McShain, Inc. (McShain) for damages due to the delay in a construction project occasioned by the defendant’s trespass. The trial court entered judgment for L’Enfant in the amount of $291,276.31, plus costs. McShain appeals and L’Enfant cross-appeals.

L’Enfant is a real estate developing company responsible for the construction of the East building of L’Enfant Plaza. The East building was part of Stage II of the construction process for the entire L’Enfant Plaza hotel and office complex. 1 On May 11, 1971, construction began on Stage II. 2 The construction contract for Stage II called for the building to be completed within twenty months of commencement of work; thus, the building was required to be finished by January 11, 1973.

*1224 On June 11, 1971, L’Enfant’s contractor, the George Hyman Construction Company (Hyman), discovered an encroachment upon L’Enfant’s land. This encroachment was made of concrete reinforced with steel bars and extended from the footings of the building on the adjacent property — owned by the Department of Housing and Urban Development (HUD) constructed by McShain. It varied in thickness from eighteen to forty-two inches, was located about twenty-three feet below grade, and ran along the common boundary for approximately 240 feet.

On June 23, McShain, having agreed to assume responsibility for the removal of the encroachment, hired a subcontractor to do the work. This work lasted from June 28 until July 16 — including removal of the debris.

The building was finally completed on June 25,. 1973. L’Enfant filed this complaint almost a year later, on June 21, 1974. The trial court granted McShain’s motion for summary judgment on the ground that suit was barred by the applicable statute of limitations — which provides a three-year limit. 3 On appeal, we reversed, holding that the encroachment constituted a continuing trespass, which accordingly gave rise to successive causes of action until its removal. L’Enfant Plaza East, Inc. v. John McShain, Inc., D.C.App., 359 A.2d 5, 7 (1976). We remanded for trial to determine the amount of damages incurred on or after June 21, 1971. Id.

After remand, the trial court granted L’Enfant’s motion for partial summary judgment on the issue of liability. The parties then proceeded to trial on the proper measure of damages. The trial court, sitting without a jury, entered judgment for L’Enfant — concluding that McShain had been responsible for a thirty-one day delay, but that recovery for six of those days was barred by the statute of limitations. Its calculations of damages included: the added field supervision, overhead and equipment; the escalation of labor and material costs; the extra cost of concrete; and lost profits.

On appeal, McShain concedes that the evidence supports a finding of a net delay of fourteen days and that the appropriate measure of damages is $2,839.84 per day. 4 McShain attacks eighteen separate findings of fact, however, as clearly erroneous. It also attacks, as unsupported, the trial court’s conclusion that the delay caused by defendant carried over — undiminished—to the time of the building’s completion.

On cross-appeal, L’Enfant argues that the statute of limitations does not bar its claim for “lost profits which were partially attributable to pre-June 21,1971 delay since those damages were not ascertainable with reasonable certainty until after June 21, 1971.”

The specific findings attacked by McShain all relate to either one or the other of its essential arguments: (1) that the evidence does not support the court’s conclusion that defendant was responsible for a net delay of thirty-one days; and (2) that there is no evidence to show that the encroachment-caused delay, however long it was, was carried over undiminished for about two years to delay the final completion date by the same number of days.

When reviewing the decision of a trial court, which has sat without a jury, we may not set aside its judgment “except for errors of law unless it appears that the judgment is plainly wrong or without evidence to support it.” D.C.Code 1973, § 17-305(a); Max Holtzman, Inc. v. K&T Co., D.C.App., 375 A.2d 510, 512 (1977); Parking Management, Inc. v. Gilder, D.C.App., 343 A.2d 51, 54 (1975). Consequently, we must determine whether the findings challenged by McShain have support in the record.

Finding Number 14:

During removal of the encroachment, Hyman’s intended north-to-south progress along the east side was effec *1225 tively foreclosed. . . . Although Hyman was able to continue pouring concrete on the west side and on the east side north of Column Line 11, it was unable to pour any concrete on the east side south of Column Line 11 (except underpinning work, discussed below) until July 14.

McShain asserts that certain evidence is contrary to this finding. First, it points to testimony indicating that the construction and pouring of footings was proceeding north to south from column sixteen through twelve on June 18. This evidence does not, however, negate the finding, but in fact supports it, because the court specifically noted that Hyman was able to continue pouring concrete “on the east side north of Column Line 11.” Second, McShain refers to testimony that on July 6 Hyman poured concrete for underpinning pits numbers six and nine on the east wall. Again, this evidence is not inconsistent with the court’s finding but supports it. The court’s finding specifically excepts underpinning work. Third, McShain refers to testimony purportedly showing that concrete was poured on July 10 for a service slab at columns ten and eleven — in the encroachment area. McShain, however, mistakenly views the evidence; its reference to the testimony indicates that on July 12, only the placement of reinforcing bars occurred at the “strap beam and footings at Lines 10 and 11,” whereas concrete for the service slab was poured north of the main encroachment area at lines fifteen and sixteen. The court expressly noted that “some preliminary form construction and rebar placement took place in the encroachment area during the two or three work days prior to July 14, [and] had there been no encroachment this work would have been done during the period June 11 through 14 . . ..” Fourth, McShain contends that a photograph shows five footings were constructed between June 2 and July 6 on the east side of the encroachment to support five concrete columns. Examining this photograph in light of the testimony explaining the position of those footings and columns, we observe that McShain is inaccurate. The footings and columns in the photograph are north of the principal encroachment area.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matiella v. Murdock Street LLC
District of Columbia, 2024
Zand v. Islamic Republic of Iran
District of Columbia, 2022
Krukas v. Aarp
District of Columbia, 2019
Krukas v. AARP, Inc.
376 F. Supp. 3d 1 (D.C. Circuit, 2019)
Jane Doe v. Kipp DC Supporting Corp.
373 F. Supp. 3d 1 (D.C. Circuit, 2019)
Pleznac v. Equity Residential Mgmt., L.L.C.
320 F. Supp. 3d 99 (D.C. Circuit, 2018)
Morton v. DISTRICT OF COLUMBIA HOUSING AUTHORITY
720 F. Supp. 2d 1 (District of Columbia, 2010)
Jung, Bow G. v. Mundy Holt Mance PC
372 F.3d 429 (D.C. Circuit, 2004)
Beard v. Edmondson and Gallagher
790 A.2d 541 (District of Columbia Court of Appeals, 2002)
Gaetan v. Weber
729 A.2d 895 (District of Columbia Court of Appeals, 1999)
District of Columbia v. Anderson
597 A.2d 1295 (District of Columbia Court of Appeals, 1991)
Shives v. Furst
521 A.2d 332 (Court of Special Appeals of Maryland, 1987)
Kaushiva v. Hutter
454 A.2d 1373 (District of Columbia Court of Appeals, 1983)
L'Enfant Plaza Properties, Inc. v. United States
645 F.2d 886 (Court of Claims, 1981)
Flack v. Laster
417 A.2d 393 (District of Columbia Court of Appeals, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
402 A.2d 1222, 1979 D.C. App. LEXIS 380, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-mcshain-inc-v-lenfant-plaza-properties-inc-dc-1979.