John M. Peduto and El-Ro, Inc. v. City of North Wildwood

878 F.2d 725, 1989 U.S. App. LEXIS 9186, 1989 WL 70021
CourtCourt of Appeals for the Third Circuit
DecidedJune 29, 1989
Docket88-5809
StatusPublished
Cited by49 cases

This text of 878 F.2d 725 (John M. Peduto and El-Ro, Inc. v. City of North Wildwood) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John M. Peduto and El-Ro, Inc. v. City of North Wildwood, 878 F.2d 725, 1989 U.S. App. LEXIS 9186, 1989 WL 70021 (3d Cir. 1989).

Opinion

OPINION OF THE COURT

NYGAARD, Circuit Judge.

This case arises from a claim by appellants John M. Peduto and El-Ro, Inc. that a temporary sewer moratorium and construction ban imposed by the City of North Wildwood, New Jersey constituted a com-pensable taking of their property. The district court dismissed appellants’ complaint on res judicata grounds, holding that the New Jersey state court had already adjudicated appellants’ federal claims. The primary issue in this appeal is whether applying New Jersey claim preclusion rules violates appellants’ due process rights. Since New Jersey’s inverse condemnation procedure afforded appellants a full and fair opportunity to litigate their federal claims in state court, we hold that appellants were not denied due process of law. Accordingly, we will affirm the order of the district court.

I.

Appellants owned and developed three condominium projects in the City of North Wildwood, New Jersey (“the City”). Construction on the individual projects commenced in August, 1984, October, 1984 and March, 1985 respectively. In August, 1985, the City imposed a sewer moratorium and construction ban pursuant to a directive from the New Jersey Department of Environmental Protection (NJDEP). The sewer moratorium temporarily prevented any further sewer connections or extensions. This ban allegedly delayed appellants’ construction projects by an estimated eight months. Appellants assert that the City led them to believe sewer service would be available for their proposed projects. Appellants claim that the eight-month delay deprived them of the use of their property resulting in a temporary taking without compensation.

On July 10, 1986, appellants filed an action in the Superior Court of New Jersey, Cape May County, against the City, NJDEP, the Cape May County Municipal Utilities Authority and Van Note Harvey Associates. The Cape May action raised claims under state common law, 42 U.S.C. *727 § 1983 and the federal and state constitutions. Count one alleged a compensable taking of property via inverse condemnation. Count two alleged a denial of procedural due process. Count three alleged a denial of substantive due process. Counts four and five alleged state and common law negligence. On May 11, 1987, the Cape May County Court dismissed appellants’ complaint with prejudice. The court’s opinion addressed appellants’ federal claims at length. App. at 75-83. This decision was not appealed.

On July 23, 1987, appellants filed this action in federal district court, once again naming the City as a defendant. The complaint states claims virtually identical to counts one, two and three of the Cape May County action. On October 7, 1988, the district court granted the City’s motion to dismiss appellants’ complaint on res judica-ta grounds. Pursuant to the full faith and credit statute, 28 U.S.C. § 1738, the court applied New Jersey claim preclusion rules and determined that direct estoppel barred “relitigation of the federal questions actually litigated and determined in the Cape May County action.” Peduto v. City of North Wildwood, 696 F.Supp. 1004, 1007 (D.N.J.1988). This timely appeal followed. We have jurisdiction pursuant to 28 U.S.C. § 1291. Since we are concerned with the interpretation and application of legal precepts, our standard of review is plenary. United States v. Adams, 759 F.2d 1099, 1106 (3d Cir.), cert. denied, 474 U.S. 906, 971, 106 S.Ct. 336, 88 L.Ed.2d 321 (1985).

II.

Appellants do not seriously contest that the district court erred in its application of New Jersey issue preclusion principles; 1 instead they claim that the interplay between federal takings jurisprudence and New Jersey’s Entire Controversy Doctrine denied them an opportunity to litigate their federal claims in federal court, thereby denying them due process. First, appellants assert that under the procedure set forth in Williamson County Regional Planning Comm’n v. Hamilton Bank, 473 U.S. 172, 194-196, 105 S.Ct. 3108, 3120-22, 87 L.Ed.2d 126 (1985), which held that a landowner must follow state procedures for seeking just compensation before bringing a Section 1983 action in federal court, they were required to bring an inverse condemnation action in New Jersey state court. Next, appellants argue that under New Jersey’s “entire controversy doctrine”, which requires that “a party who has elected to hold back from the first proceeding a related component of the controversy be barred from thereafter raising it in a subsequent proceeding”, Woodward-Clyde Consultants v. Chemical and Pollution Sciences, Inc., 105 N.J. 464, 523 A.2d 131, 135 (1987) (citations omitted), 2 they were compelled to *728 litigate all of their claims, including their federal constitutional claims, in state court when they filed their inverse condemnation action. Thus, they argue that the New Jersey issue preclusion doctrine denied them a federal forum to present their federal claims, and that such a denial violates their due process rights.

Our analysis begins with the Full Faith and Credit Act, 28 U.S.C. § 1738. Under the Act, “a federal court must give the same preclusive effect to a state-court judgment as another court of that State would give.” Parsons Steel, Inc. v. First Alabama Bank, 474 U.S. 518, 523, 106 S.Ct. 768, 771, 88 L.Ed.2d 877 (1986); Na-navati v. Burdette Tomlin Memorial Hospital, 857 F.2d 96, 111 (3d Cir.1988), cert. denied, — U.S.-, 109 S.Ct. 1528, 103 L.Ed.2d 834 (1989). This rule has been applied to civil rights actions brought pursuant to 42 U.S.C. § 1983. Migra v. Warren City School Dist. Bd. of Education, 465 U.S. 75, 104 S.Ct. 892, 79 L.Ed.2d 56 (1984); Allen v. McCurry, 449 U.S. 90, 101 S.Ct. 411, 66 L.Ed.2d 308 (1980). A federal court can refuse to accord preclusive effect to a state court judgment if application of the state preclusion law would violate due process. Kremer v. Chemical Construction Corp., 456 U.S. 461, 482, 102 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
D. New Jersey, 2026
SINGH v. DROPPA
D. New Jersey, 2022
FISHER v. PRATT
D. New Jersey, 2020
Davis v. State (In re Venoco, LLC)
596 B.R. 480 (D. Delaware, 2019)
106 North Walnut, LLC v. 106 North Walnut, LLC
447 F. App'x 305 (Third Circuit, 2011)
William Morgan v. Covington Twp
648 F.3d 172 (Third Circuit, 2011)
June Wisniewski v. Travelers Casualty and Surety
390 F. App'x 153 (Third Circuit, 2010)
Di Loreto v. Costigan
351 F. App'x 747 (Third Circuit, 2009)
Miles v. Township of Barnegat
343 F. App'x 841 (Third Circuit, 2009)
Di Loreto v. Costigan
600 F. Supp. 2d 671 (E.D. Pennsylvania, 2009)
Torromeo v. Town of Fremont
438 F.3d 113 (First Circuit, 2006)
Center for Professional Advancement v. Mazzie
347 F. Supp. 2d 150 (D. New Jersey, 2004)
Dlx, Inc. v. Commonwealth of Kentucky
381 F.3d 511 (Sixth Circuit, 2004)
DLX Inc v. Comwlth KY
Sixth Circuit, 2004
W.J.F. Realty Corp. v. Town of Southampton
220 F. Supp. 2d 140 (E.D. New York, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
878 F.2d 725, 1989 U.S. App. LEXIS 9186, 1989 WL 70021, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-m-peduto-and-el-ro-inc-v-city-of-north-wildwood-ca3-1989.