John Kurt Sensabaugh v. Commonwealth of Virginia

Court of Appeals of Virginia·Decided February 9, 1999·No. 2811973·Unpublished

Opinion

COURT OF APPEALS OF VIRGINIA

Present: Chief Judge Fitzpatrick, Judges Willis and Bumgardner Argued at Salem, Virginia

JOHN KURT SENSABAUGH MEMORANDUM OPINION * BY

v. Record No. 2811-97-3 CHIEF JUDGE JOHANNA L. FITZPATRICK FEBRUARY 9, 1999

COMMONWEALTH OF VIRGINIA

FROM THE CIRCUIT COURT OF NELSON COUNTY J. Michael Gamble, Judge

Bruce K. Tyler for appellant.

Richard B. Campbell, Assistant Attorney General (Mark L. Earley, Attorney General, on brief), for appellee.

John Kurt Sensabaugh (appellant) was convicted in a bench trial of failing to carry out a promise to perform construction in return for an advance of money in violation of Code § 18.2-200.1. Appellant contends the language used in the notice did not comply with the statute and, therefore, the Commonwealth failed to prove an essential element of the crime. Additionally, he argues that the evidence was insufficient to support the conviction. Finding no error, we affirm.

I.

Under familiar principles of appellate review, we examine the evidence in the light most favorable to the Commonwealth, granting to it all reasonable inferences fairly deducible

therefrom. See Juares v. Commonwealth, 26 Va. App. 154, 156, 493

*

Pursuant to Code § 17.1-413, recodifying Code § 17-116.010, this opinion is not designated for publication.

S.E.2d 677, 678 (1997). So viewed, the evidence established that appellant entered into a written contract with David Copson (Copson) to construct a building. The contract estimated a starting date of January 16, 1995, and a completion date of February 28, 1995, and required Copson to make four payments as

follows:

Upon signing contract, a deposit of $4,800.00 is to be made. The deposit covers rough-in plumbing, stone, concrete, and excavating. A second draw of $9,930.00 is to be made for all rough framing, roofing, windows, shingles, interior rough-in plumbing and electrical (Material to be delivered within 48 hours of second draw). A third draw of $7,900 is to be made for all finish work.

The balance upon completion and payable upon completion is $5,332.00.

When the contract was first negotiated, appellant "told"

Copson to get the building permit. Copson filed for a permit on January 9, 1995, and paid appellant the first advance on January 16, 1995, when the contract was signed. The building permit could not be issued until appellant provided proof of a properly secured contractor's license, which did not occur until April 25, 1995, almost two months after the building was supposed to be completed.

On April 6, 1995, Copson paid the second draw of $9,930. In late May of 1995, even though the work required under the second draw/advance was incomplete, appellant requested payment of the

third draw. Copson testified as follows:

Mr. Sensabaugh told me it was time for the third draw. I was unwilling to make the payment all at once because the work had gone

so slowly, so I wanted to stretch it out a little bit, so I gave him partial payment.

As a result, Copson wrote three checks to appellant: one for $3,500 on May 22, 1995; one for $2,600 on May 30, 1995; and one for $1,800 on June 2, 1995. 1 "[W]ithin a week or so" of Copson paying the balance of the third draw, appellant's workers "packed up all . . . their tools and left the job." At that point, "there was still some electrical work to be done, there was the sewer connections to be made," as well as insulation, sheetrock, and finished plumbing. Moreover, "the framings weren't even done for" the skylights that were supposed to be installed in the roof. Although the toilet bowl had been delivered, the sinks and heat pump had not. Appellant also failed to deliver the skylights, electrical lighting, sheetrock, gutters, linoleum flooring, interior window

frames, and insulation.

Copson attempted to contact appellant to determine when

appellant and his workers were going to return to the job site to

1 On May 25, 1995, three days after Copson paid appellant the first installment on the third draw, the parties prepared and executed a document entitled, "Extras." In it, the parties agreed upon a price for additional work, including a second floor loft, an extra window, and a counter with a double sink. The total amount for the "extras" was $1,514.55. Copson wrote appellant a check for $1,000 and agreed to pay the balance with the fourth draw upon completion of the building. Copson testified that he wanted to make sure of any additional expenses, so he asked appellant about "any other extras" or charges. Appellant "told [him] that there was a few things that he had done that normally he would bill for, but he wasn't going to bill [Copson] for them because he was so far behind schedule . . . ."

finish the building. Copson telephoned "several times a week, sometimes every day, ten, twenty times probably." On June 26, 1995, Copson received a letter from appellant demanding that Copson pay the fourth draw and additional money for seventeen listed "extras" before any work could be completed.

On July 1, 1995, Copson responded in writing to appellant's letter. Although he refused to pay the final draw, Copson indicated that he would pay appellant for various "extra" items, as they had previously discussed. Over the next month, the parties "negotiated back and forth," and they eventually reached an agreement. On August 14, 1995, Copson's attorney sent appellant a copy of a proposed agreement to sign and return. Copson never received a response from appellant, and his "phone calls weren't returned." Appellant failed to do any further work

or have any of the finishing material delivered.

On October 17, 1996, Copson mailed a certified letter to

appellant, return receipt requested. The letter was addressed to East Coast Property & Development, 321 Isle Avenue, Waynesboro, Virginia, 22980, the same name and address printed on the letterhead of the contract signed by the parties. In the first paragraph, Copson gave "notice that [their] contract . . . is canceled." The second and third paragraphs demanded repayment of portions of the first two draws due to incomplete and/or unsatisfactory work. The fourth paragraph addressed the performance of "extra" work. In the fifth paragraph of the

letter, Copson wrote:

The third draw of $7900 "for all finish work"

was advanced to you on May 22 - $3500, May 30 - $2600 and June 2 - $1800. None of the finishing materials including, but not limited to, insulation, sheetrock, skylights, interior doors, bathroom sink and fixtures, heat pump, flooring, lights and gutters were ever even delivered. You owe me all this money - $7900.

Four paragraphs later, Copson concluded, "I demand that you pay me the $25,000 you owe me immediately." The letter was returned to Copson undelivered and unopened. 2 The evidence also established that approximately two months after appellant "left the job," David Thompson, an Assistant Building Code Official for Nelson County, inspected the uncompleted building. Thompson indicated in his report that seven items "were incomplete or deficient"; that the building was "still at the rough-in stage"; and that it could not be used or occupied until the wiring and plumbing had been completed and inspected. As of the September 1997 trial, no additional work had been performed. James Pace, a contractor, estimated that the cost of completion of the building would be $22,270, not including the cost of a heat pump and plumbing work.

At the conclusion of the presentation of evidence, the trial court took the issue of appellant's guilt under advisement to "look over" the exhibits and "look at the cases." In his letter

2 We do not address the issue of whether actual receipt of the notice was required as it is not presented in this appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

John Kurt Sensabaugh v. Commonwealth of Virginia, (Va. Ct. App. 1999).

John Kurt Sensabaugh v. Commonwealth of Virginia (John Kurt Sensabaugh v. Commonwealth of Virginia) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Moore v. Commonwealth
491 S.E.2d 739 (Supreme Court of Virginia, 1997)
Marable v. Commonwealth
500 S.E.2d 233 (Court of Appeals of Virginia, 1998)
Watkins v. Commonwealth
494 S.E.2d 859 (Court of Appeals of Virginia, 1998)
Juares v. Commonwealth
493 S.E.2d 677 (Court of Appeals of Virginia, 1997)
Martin v. Commonwealth
358 S.E.2d 415 (Court of Appeals of Virginia, 1987)
Boothe v. Commonwealth
358 S.E.2d 740 (Court of Appeals of Virginia, 1987)
Jimenez v. Commonwealth
402 S.E.2d 678 (Supreme Court of Virginia, 1991)
Board of Supervisors v. King Land Corp.
380 S.E.2d 895 (Supreme Court of Virginia, 1989)
Brooks v. Commonwealth
258 S.E.2d 504 (Supreme Court of Virginia, 1979)
Last v. Virginia State Board of Medicine
421 S.E.2d 201 (Court of Appeals of Virginia, 1992)
Barr v. Town & Country Properties, Inc.
396 S.E.2d 672 (Supreme Court of Virginia, 1990)
Norman v. Commonwealth
346 S.E.2d 44 (Court of Appeals of Virginia, 1986)
Klink v. Commonwealth
407 S.E.2d 5 (Court of Appeals of Virginia, 1991)
Derr v. Commonwealth
410 S.E.2d 662 (Supreme Court of Virginia, 1991)
Rader v. Commonwealth
423 S.E.2d 207 (Court of Appeals of Virginia, 1992)
Anderson v. Commonwealth
29 S.E.2d 838 (Supreme Court of Virginia, 1944)