John E. And Ellen Petersen, V Baseline Engineering Inc

CourtCourt of Appeals of Washington
DecidedSeptember 4, 2013
Docket43001-1
StatusUnpublished

This text of John E. And Ellen Petersen, V Baseline Engineering Inc (John E. And Ellen Petersen, V Baseline Engineering Inc) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John E. And Ellen Petersen, V Baseline Engineering Inc, (Wash. Ct. App. 2013).

Opinion

D COURT QP APPEALS 20 13 SEP -4 AM 10=21

STAFF OF WASHING TOl 1 Y4OUTY - — -

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II

JOHN PETERSEN, JR. and E. ELLEN No. 43001 1 II - -

PETERSEN, husband and wife,

Appellants,

V.

BASELINE ENGINEERING, INC., a UNPUBLISHED OPINION Washington corporation,

Respondent.

HUNT, P. . — E.Petersen, Jr., Ellen Petersen appeal the superior court's grant of J John and

summary judgment to Baseline Engineering, Inc. and dismissal of the Petersens' breach of

contract claim. The Petersens argue that there are issues of fact about whether Baseline breached

its contract to assist the Petersens in a short plat application process. We affirm. We also grant

attorney fees and costs on appeal to Baseline.

FACTS

I. BACKGROUND

John E. Petersen, Jr. and his wife, Ellen Petersen, acquired an option to purchase a .91

acre Brown's Point property, which they intended to subdivide and to sell to another party. The

option to purchase allowed the Petersens time to " heck for environmental constraints or critical c

areas located on or adjacent to the property prior to purchase." Clerk's Papers (CP)at 95. The No. 43001 1 II - -

Petersens contacted Baseline Engineering, Inc., surveying, engineering, and land development a

services firm.

A. Baseline Short Plat Application Contract

On October 18, 2006, Baseline sent John Petersen a letter stating its interest in " ssist[ ng a i

the Petersens] in short platting [the] property in Brown's Point."CP at 41. Baseline advised

Petersen that it had discussed the project with Pierce County staff "for the purpose of

determining whether additional lots could be obtained" and had concluded a two lot short plat - would be "the most feasible and economical" approach. CP at 41. Baseline offered the

following services: ( a "boundary 1) and topographic survey "; (2)preparation of a "short plat

drawing and other standard application materials for submittal to Pierce County "; and (3)

with consult[ ng]" i Petersen " and or / representative, [ or] other subconsultants ( such as

geotechnical engineer, traffic engineer, wetland biologist, etc.), local agency staff (City, and

County, Washington State Department of Transportation],Fire Marshal, etc.)." at 41, 42 [ CP

capitalization omitted).

The section of the letter addressing preparation of the short plat application stated:

SHORT PLAT APPLICATION

Prepare short plat drawing and other standard application materials for submittal to Pierce County. This task does not include Sensitive Areas Analysis, Traffic Impact Analysis, Geotechnical Reports, or other specialized technical studies as may be required by Pierce County during review ofthe application.

CP at 42 (emphasis added).The letter further explained:

The above described scope to make application to Pierce County for a short plat is generally predictable and can be defined. However, until Pierce County reviews and comments on the application, it is not possible to determine with any degree of certainty actions which will be required to obtain complete short plat approval

2 No. 43001 1 II - -

from the County. After Pierce County review comments are received, we will be able to more precisely determine "additional scope and fees" i.. engineering e design and final plat documents.

CP at 42 (emphasis added). The letter also advised that Petersen would be "responsible for all

City, State, County or Local fees and taxes."CP at 42. Petersen signed the letter and accepted

Baseline's proposal on November 20.

B. Sewall Wetland and Stream Analysis

Meanwhile, Petersen hired Sewall Wetland Consulting, Inc. to conduct a "[ w] etland and

s] [ tream analysis" of the property; Petersen separately hired an engineering geologist to

provide a soils report. CP at 96. In a November 2, 2006 letter, wetlands ecologist Ed Sewall advised Petersen that (1)there were conditions suggesting a wetland area, likely caused by fill

having been placed on the property; and (2) was his " rofessional opinion that the site['] soil it p s

and vegetation conditions are a result of past disturbance and appear to not be a result of wetland conditions." CP at 48. Sewall also cautioned Petersen that "only early growing season

monitoring would confirm if the area is wet or not." at 48. CP

C. Two Lot Short Plat Application and County Response; PSA To Sell Property to Buchanan - Baseline completed the boundary and topographic survey in December, but it could not

proceed further with the short plat application until Petersen provided Baseline with a landscape

plan and title report. Petersen provided Baseline with the landscape plan and title report in July 2007, after exercising the option to purchase the Brown's Point property on June 25,2007

1 Purchase and Sale Agreement.

3 No. 43001- 11- 1

Nevertheless, Baseline planner Kevin Foley declined to perform the civil engineering site

development work at this stage because the county had not yet reviewed the initial short plat

application. Consistent with the contract, Foley told Petersen that the engineering site

development work should wait until they received the county's initial review of the short plat

application because the county's final decision on certain issues, such as lot density and location

of any sensitive areas, would affect that engineering site work and could require major design

changes. Foley also told Petersen that he did not think Sewall's wetland and stream analysis

would meet county requirements.

Despite Foley's advice, Petersen hired engineer Brant Schweikl to do the site

development permit work in mid July. On August 28, the Petersens entered into a PSA to sell -

the property to Herman Buchanan for $ 85, 00, with a September 29 closing date. According to 4 0 Petersen, although the PSA did not specifically state any conditions or contingencies other than a

financing contingency, preliminary plat approval"was a requirement for the sale. CP at 108. "

Also in August, Baseline submitted to the county a two lot short plat application, which -

included, at Petersen's request, the Sewall wetland and stream analysis about which Foley had

expressed doubts to Petersen. Petersen justified inclusion of Sewall's analysis, stating:

I wanted my expert['] s sensitive area analysis" i] the hands of the county " [n environmental biologist. My feeling was; ifthe county wants something else they would tell us. If they felt we had a potential environmental issue they would tell us ifwe needed to provide any additional information.

2 The contract provided that Baseline would provide Petersen information about "` dditional a scope and fees, "' including engineering design, only after the county reviewed the initial short plat application. CP at 42.

0 No. 43001 1 II - -

CP at 98 99 ( mphasis added). - e

On August 28, county senior planner Dierdre Wilson sent Baseline a letter stating that (1)

the two lot short plat did not meet the county's density requirements unless there were -

environmentally constrained lands"on the parcel reducing the area subject to development; and

2) "[ esearch in our GIS system does not result in any environmentally constrained lands on r]

this parcel that may reduce the developable area for net developable acreage calculations."CP at

50.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Estate of Richardson
525 P.2d 816 (Court of Appeals of Washington, 1974)
Hansen v. Transworld Wireless TV-Spokane, Inc.
111 Wash. App. 361 (Court of Appeals of Washington, 2002)
Owens v. Harrison
120 Wash. App. 909 (Court of Appeals of Washington, 2004)
Dice v. City of Montesano
131 Wash. App. 675 (Court of Appeals of Washington, 2006)
Spradlin Rock Products, Inc. v. Public Utility District No. 1
164 Wash. App. 641 (Court of Appeals of Washington, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
John E. And Ellen Petersen, V Baseline Engineering Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-e-and-ellen-petersen-v-baseline-engineering-inc-washctapp-2013.