John Deere Industrial Equipment Co. v. Triple Cities Equipment, Inc.

646 F. Supp. 114, 3 U.C.C. Rep. Serv. 2d (West) 1659, 1986 U.S. Dist. LEXIS 19673
CourtDistrict Court, N.D. New York
DecidedSeptember 30, 1986
Docket84-CV-819
StatusPublished

This text of 646 F. Supp. 114 (John Deere Industrial Equipment Co. v. Triple Cities Equipment, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Deere Industrial Equipment Co. v. Triple Cities Equipment, Inc., 646 F. Supp. 114, 3 U.C.C. Rep. Serv. 2d (West) 1659, 1986 U.S. Dist. LEXIS 19673 (N.D.N.Y. 1986).

Opinion

McAVOY, District Judge.

FINDINGS OF FACT AND CONCLUSIONS OF LAW

On June 17 through 18, 1986, a bench trial was held in the above-captioned matter. On the basis of the evidence adduced at that trial as well as the applicable law, the Court, pursuant to Rule 52(a) of the Federal Rules of Civil Procedure, makes the following findings of fact and conclusions of law: 1

FINDINGS OF FACT

1. Plaintiff, John Deere Industrial Equipment Company (“John Deere”), is a Delaware corporation with its principal place of business in Moline, Illinois.

2. Defendant, Triple Cities Equipment, Inc. (“TCE”), is a New York corporation with its principal place of business in Vestal, New York.

3. Defendant Carl J. Hughes, a resident of the State of New York, was at all times relevant to this action, the President of TCE.

4. Defendant Linda L. Hughes, a resident of the State of New York, was at all times relevant to this action, an officer of TCE.

5. In late 1966 and early 1967, John Deere and TCE entered into a series of agreements whereby TCE became a franchisee of John Deere and agreed to buy from John Deere certain machinery and equipment for resale to retail customers. See Plaintiffs Exhibits 1 through 8.

6. On July 31, 1967, defendants Carl J. Hughes and Linda L. Hughes signed an agreement whereby they personally guaranteed all of the obligations of TCE to John Deere. See Plaintiff’s Exhibit 30.

7. This guarantee and the agreements between TCE and John Deere were in full force and effect at all times relevant to this action.

8. In November and December of 1982, TCE sold several pieces of equipment to retail customers and failed to remit payment for those items to John Deere as required by the parties’ agreement.

9. In April 1983, TCE’s check, submitted as payment of amounts due and owing from TCE to John Deere under their agreement, was dishonored. Soon thereafter, the check was paid.

10. During the second week of May 1983, George DeClue, a John Deere representative, discovered during his monthly inventory check that several pieces of TCE’s equipment were out of inventory. In light of this, DeClue demanded payment from TCE of the amounts due and owing for the equipment.

11. Several days later, on May 16,1983, Declue returned to TCE with Leo Holland, another John Deere representative. On that date, Carl Hughes indicated that additional pieces of TCE’s equipment were out of inventory. On the basis of these further representations, DeClue and Holland demanded payment from TCE of $237,054.19, the amount due and owing for the equipment out of inventory. When TCE failed to remit payment by May 17, 1983, John Deere terminated the dealership contract and demanded payment of the entire balance of TCE’s account. See Plaintiff’s Exhibit 22.

12. In order to insure payment from TCE, John Deere immediately took possession of TCE’s inventory and moved it to another location. Pursuant to the terms of its agreement with TCE, John Deere sold TCE’s complete new machines to other dealers and credited TCE’s account with the amounts derived from these sales. See Plaintiff’s Exhibit 6, ¶ 11. With TCE’s consent, John Deere also repurchased resalable parts from TCE’s inventory and after an inventory of the parts, TCE’s account *116 was credited for the parts. See Plaintiff’s Exhibits 14 and 58.

13. By letter dated June 13, 1983, John Deere informed TCE that a public auction for the sale of TCE’s remaining collateral, which consisted of used goods and attachments and parts that could not be resold at retail, had been scheduled for June 29, 1983. The letter also indicated that TCE had a right to redeem its collateral prior to the auction by tendering payment of all amounts still due and owing to John Deere, the amount of which would be provided to TCE upon request. See Plaintiff’s Exhibit 23.

14. By letter dated June 21,1983, TCE’s counsel requested a specific redemption price from John Deere. See Plaintiff’s Exhibit 24. When TCE was provided only with a redemption price range of between $199,000 and $210,000, see Plaintiff’s Exhibit 25, it requested that the June 29 auction be postponed until such time as John Deere could provide a specific redemption price and an itemized account detailing how the price was determined. See Plaintiff’s Exhibit 26. John Deere was unable to provide a specific redemption price at that time because it had not completed its inventory of the plaintiff’s resalable parts.

15. Eventually, the inventory was completed and TCE’s account was credited for the resalable parts. See Plaintiff’s Exhibit 14. By letter dated October 6, 1983, John Deere’s counsel informed TCE that its total net indebtedness to John Deere was $249,-697.54. See Plaintiff’s Exhibit 39. At no time prior to or after that letter did TCE attempt to redeem its collateral. Instead, it agreed to an auction date of November 18, 1983. See Plaintiff’s Exhibit 38.

16. The auction was conducted by a professional auctioneer at TCE’s place of business. Prior to the auction, John Deere notified heavy equipment dealers across the Eastern United States, including its own dealers, of the pendency of the sale. The sale was well publicized, see Plaintiff’s Exhibits 52 through 54, and well attended. The defendants’ only complaint concerning the sale was that the sale was conducted too late in the construction season because of John Deere’s delay in providing a redemption price.

17. After the sale, TCE’s account was credited with the net proceeds of the sale. See Plaintiff’s Exhibit 55. By letter dated February 28, 1984, John Deere informed TCE that there remained a deficiency of $140,790.63 due and owing from TCE to John Deere. See Plaintiff’s Exhibit 28. In the letter, John Deere also demanded payment of the deficiency.

18. Despite this demand, the defendants refused to pay because they contested the accuracy of John Deere’s figures. See Plaintiff’s Exhibits 34 and 36. As a result, John Deere commenced this action on June 13, 1984. After commencement of this action, John Deere discovered an error in its calculations of interest on the plaintiff’s account and reduced the amount sought in this action to $128,430.68 plus interest from June 12, 1984.

19. After the loss of its inventory, TCE went out of business and the Hughes sustained additional financial losses, including the loss of the buildings which housed the dealership.

CONCLUSIONS OF LAW

1. Jurisdiction herein is predicated upon diversity of citizenship. 28 U.S.C. § 1332(a).

2. TCE’s failure in late 1982 and early 1983 to remit payment to John Deere of funds derived from the sale of equipment constituted a breach of the parties’ dealership agreement.

3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bankers Trust Co. v. J. V. Dowler & Co.
390 N.E.2d 766 (New York Court of Appeals, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
646 F. Supp. 114, 3 U.C.C. Rep. Serv. 2d (West) 1659, 1986 U.S. Dist. LEXIS 19673, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-deere-industrial-equipment-co-v-triple-cities-equipment-inc-nynd-1986.