John Day Co. v. Alvine & Associates, Inc.

510 N.W.2d 462, 1 Neb. Ct. App. 954, 1993 Neb. App. LEXIS 307
CourtNebraska Court of Appeals
DecidedJuly 6, 1993
DocketA-91-1187
StatusPublished
Cited by2 cases

This text of 510 N.W.2d 462 (John Day Co. v. Alvine & Associates, Inc.) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Day Co. v. Alvine & Associates, Inc., 510 N.W.2d 462, 1 Neb. Ct. App. 954, 1993 Neb. App. LEXIS 307 (Neb. Ct. App. 1993).

Opinion

Connolly, Judge.

This appeal arises from the dismissal of the petition of the John Day Company (John Day), the appellant, seeking damages in contract and in tort from Alvine and Associates, Inc. (Alvine), the appellee. John Day had contracted with an architectural firm for the construction of a building, and the architectural firm had subcontracted with Alvine for mechanical engineering design services. John Day sued Alvine for damages resulting from a problem that developed after *956 completion of the building in the heating, ventilating, and air-conditioning system designed by Alvine. John Day sued in contract on the theory that it was a third-party beneficiary of the subcontract between the architectural firm and Alvine, and in tort on the theory that it was a third party to whom Alvine owed, and breached, a duty of care. The trial court sustained Alvine’s demurrer on grounds that John Day had failed to state a cause of action in either contract or tort. We affirm.

I. FACTS

John Day contracted with How-Nelsen Associates (How-Nelsen) to provide architectural services for the design and construction of John Day’s building at 6263 Abbott Drive, Omaha, Douglas County, Nebraska. How-Nelsen subcontracted with Alvine to provide mechanical engineering design services in connection with the construction of the John Day building. Alvine prepared the specifications for the design and construction of the building’s heating, ventilating, and air-conditioning system (HVAC system), a “once through cooling system” in which well water would be pumped from the source, circulated through the system, and then injected into the ground after one pass through the system. Alvine’s design specifications called for the use of carbon steel piping to carry the well water through the system.

Almost 1 year after the completion of the John Day building, it was discovered that the carbon steel pipes used in the HVAC system were corroding. A test of the well water used in the system revealed that the water had an excessively high chloride content. A metallurgical consulting service determined that the high chloride content of the well water was a major factor contributing to the corrosion of the entire carbon steel piping system. On the recommendation of the consulting service, John Day replaced the carbon steel piping with heavy plastic piping at a cost of $22,828.83.

John Day filed a petition claiming relief in both contract and tort. In claiming breach of contract, John Day alleged that it was the third-party beneficiary of the subcontract between How-Nelsen and Alvine and that Alvine’s failure to test the well water for corrosive agents before ordering the use of carbon *957 steel piping constituted a breach of its duty to John Day to provide proper, workmanlike, and professional mechanical engineering design services. In claiming professional negligence, the term used in the petition, John Day alleged that the failure of Alvine, a professional mechanical engineering firm, to conduct chemical tests of the well water in the process of designing the HVAC system constituted a breach of its duty to John Day to use the skill and knowledge ordinarily possessed by other professional mechanical engineers in good standing in Douglas County. John Day sought $22,828.83 in damages, plus “other damages,” interest, attorney fees, and costs.

Alvine filed a demurrer in which it asserted that John Day had failed to state a cause of action because Alvine was not in privity of contract with John Day and did not owe John Day any legal duty.

The order of the trial court stated that

both Counts are based upon negligence: Count I is negligent performance of the contract, and Count II is [a] straight negligence action. Since there is no privity [of] contract, there is no duty on the part of [Alvine] to [John Day]. [John Day’s] petition does not state a cause of action against [Alvine], and therefore [John Day’s] petition should be dismissed.

The trial court sustained Alvine’s demurrer and dismissed John Day’s petition.

II. ASSIGNMENTS OF ERROR

John Day assigns two errors which we summarize as follows: (1) The trial court erred in holding that both of John Day’s claims against Alvine were based on negligence, and (2) the trial court erred in holding that under a theory of professional negligence, a duty of care ran from Alvine to John Day only if there was privity of contract between those two parties.

III. STANDARD OF REVIEW

In ruling on a demurrer, the petition is to be construed liberally; if as so construed the petition states a cause of action, the demurrer is to be overruled. Matheson v. Stork, 239 Neb. 547, 477 N.W.2d 156(1991).

*958 IV. ANALYSIS

“ ‘If from the facts stated in the petition it appears that the plaintiff is entitled to any relief, a general demurrer will not lie.’ ” Central Nebraska Public Power and Irrigation District v. Walston, 140 Neb. 190, 202, 299 N.W. 609, 615 (1941). “[W]hen a petition contains more than one count, and a general demurrer is directed against the entire pleading, and is not limited to a particular count, if any count states a cause of action, such demurrer must be overruled.” Alexander v. Thacker, 30 Neb. 614, 618, 46 N.W. 825, 826 (1890). Thus, if either of John Day’s claims for relief stated a cause of action, then the trial court erred in sustaining Alvine’s demurrer.

1. Third-Party Beneficiary

In finding that both of John Day’s claims for relief sounded in tort, the trial court rejected John Day’s argument that it was a third-party beneficiary to the subcontract between How-Nelsen and Alvine.

In School District v. Thomas, 51 Neb. 740, 71 N.W. 731 (1897), the Nebraska Supreme Court was confronted with the following scenario: The school district of Beatrice hired W.C. Smith to build two schoolhouses. Smith abandoned the contract and absconded. Completion of the project was assumed by his sureties. The project was completed, and Thomas, a subcontractor on the project, asserted that he was a third-party beneficiary of the contract between the school district and the general contractor. Accordingly, he sued the school district for sums due him for his work on the project. The Supreme Court rejected Thomas’ argument:

It is also argued that the rule “Where a party makes a promise to another for the benefit of a third person, such third person may avail himself of the promise and bring an action thereon . . .” is applicable and may be invoked by [Thomas] as against the school district. There were no portions or elements of the contract between Smith, the original contractor, and the district which ... contain any promise by the district, made for the benefit of the subcontractor, on which he would be entitled to institute a suit against the district; hence the doctrine to which *959

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Standing Stone v. Kirkham Michael & Assocs.
Nebraska Court of Appeals, 2014
Hawkins Construction Co. v. Peterson Contractors, Inc.
970 F. Supp. 2d 945 (D. Nebraska, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
510 N.W.2d 462, 1 Neb. Ct. App. 954, 1993 Neb. App. LEXIS 307, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-day-co-v-alvine-associates-inc-nebctapp-1993.