John Call Engineering, Inc. v. Manti City Corp.

795 P.2d 678, 137 Utah Adv. Rep. 30, 1990 Utah App. LEXIS 111, 1990 WL 89018
CourtCourt of Appeals of Utah
DecidedJune 27, 1990
Docket890384-CA
StatusPublished
Cited by11 cases

This text of 795 P.2d 678 (John Call Engineering, Inc. v. Manti City Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Call Engineering, Inc. v. Manti City Corp., 795 P.2d 678, 137 Utah Adv. Rep. 30, 1990 Utah App. LEXIS 111, 1990 WL 89018 (Utah Ct. App. 1990).

Opinion

OPINION

ORME, Judge:

Appellant John Call Engineering, Inc. (“Call”) appeals a judgment in its favor, contending the award of damages was in an amount far below that to which it was entitled. We agree and vacate the judgment, with instructions to enter judgment in the amount minimally shown by the evidence, as requested by appellant.

FACTS

This case concerns Call’s claim that Man-ti breached a contract it had with Call for engineering services for a sewer construction project. The trial court originally concluded that there was no “meeting of the minds” concerning the contract and that it had been entered under a mutual mistake of fact. The Supreme Court disagreed. John Call Eng’g, Inc. v. Manti City Corp., *680 743 P.2d 1205 (Utah 1987). In its opinion, the Supreme Court held the trial court’s conclusion that there had been a mutual mistake of fact to be erroneous and remanded for trial on the issue of damages. Id. at 1211. The Supreme Court concluded that Manti had not been entitled, under the contract as amended, “to proceed with the project, avoid the valid agreement, and hire another engineer.” Id. at 1209. The Supreme Court also held the “plain and unambiguous” language of the contract provided that Call would provide “engineering services for the design and installation of the sewer,” as well as preparation of a preliminary sewer study which was completed pri- or to Manti’s breach. 743 P.2d at 1207. See also id. at 1210 (Orme, J., concurring) (contract to be treated as one “for the installation of, and provision of all engineering services for, the complete sewer project”).

On remand, a two-day jury trial was held to determine Call’s damages. Call offered the testimony of David Thurgood, the engineer whose firm completed the project for Manti; Randall Peterson, a CPA; Mr. Call; and Charles Peterson, an economic consultant. Manti’s case in chief consisted solely of testimony from David Thurgood. The jury awarded Call $13,440 plus prejudgment interest. On appeal, Call makes several arguments. First, it claims that the jury’s award was based on an arbitrary application of the doctrine of mitigation, and that the issue of mitigation should not have been submitted to the jury given the evidence adduced at trial. Second, it claims that the trial court erred in allowing Manti to amend its answer at the outset of trial to include mitigation as an affirmative defense. Third, Call claims that the court erred in instructing the jury on calculating Call’s damages. Finally, Call appeals the award of witness fees as being inadequate. 1

MITIGATION

In an action for damages for breach of contract, the amount of damages otherwise recoverable by plaintiff can be reduced if plaintiff succeeded in mitigating its damages or if it failed to properly mitigate its damages. “The doctrine of avoidable consequences, also referred to as mitigation of damages, generally operates to prevent one against whom a wrong has been committed from recovering any item of damage arising from the wrongful conduct which could have been avoided or minimized by reasonable means.” Angelos v. First Interstate Bank of Utah, 671 P.2d 772, 777 (Utah 1983).

However, the burden of proving plaintiff has not mitigated its damages and that its award should be correspondingly reduced is on defendant. “The plaintiff has the burden of showing the contract breach and his damages, while, as a rule the defendant has the burden of proving that damages shown could have been minimized.” D. Dobbs, Remedies § 12.6, at 830 (1973). See Pratt v. Board of Educ., 564 P.2d 294, 298 (Utah 1977) (“Although plaintiff is obligated to minimize his damages, the burden is upon the party whose wrongful act caused the damages to prove anything in diminution thereof.”). But see Green v. Nelson, 232 P.2d 776 (Utah 1951) (in breach of tuition agreement case, where information regarding amount of money saved by school for student’s non-attendance was uniquely within the exclusive knowledge of the school, burden of proof shifted back to plaintiff school). “It is not a plaintiff’s burden to produce the evidence on which any reduction of damages is to be predicated.” Comfort Homes, Inc. v. Peterson, 37 Colo.App. 516, 549 P.2d 1087, 1090 (1976). See also Barnes v. Lopez, 25 Ariz.App. 477, 544 P.2d 694, 698 (1976).

“In order to submit the issue [of mitigation] to the jury, there must be competent evidence to show that the plaintiff failed to take reasonable efforts to mitigate his damages.” Barnes, 544 P.2d at 698. In this case, Manti did not offer any evidence, through its own witness or on cross-examination, which would have allowed the *681 court to submit the issue to the jury. 2 Cf. Pratt, 564 P.2d at 298 (“Because defendant failed to sustain its burden, by producing competent evidence proving plaintiff had not taken reasonable efforts to mitigate his damages; the court properly determined there was no factual issue concerning damages, to submit to the jury.”).

Some further explanation of mitigation in the context of breach of contract may be helpful. We note initially that in a contract case, the mitigation doctrine would have the most applicability to claims for special or consequential damages rather than to general damages. However, Call did not pursue special or consequential damages at trial but only its general damages.

In the context of general damages for breach of contract, which damages ordinarily will be the amount plaintiff would have received had the contract been completed less the expenses plaintiff saved by not having to perform, 3 the mitigation doctrine rarely applies. In limited circumstances, however, general damages may be reduced by the amount of gains received by performing another contract which could not have been entered into but for defendant’s breach of the prior contract and plaintiffs being thereby left free to perform the second contract. However, the burden of proof is on defendant. See Comfort Homes, 549 P.2d at 1090 (defendant had burden of proof to show that plaintiff could not have made profits on subsequent contract but for defendant’s breach); Sides v. Contemporary Homes, 311 S.W.2d 117, 120 (Mo.Ct.App.1958) (simple fact that plaintiff “kept busy on other jobs” was insufficient to show that plaintiff could not have made those profits but for defendant’s breach of contract).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
N.D. Illinois, 2026
STEVENSEN 3RD EAST, LC v. Watts
2009 UT App 137 (Court of Appeals of Utah, 2009)
Asael Farr & Sons Co. v. Truck Insurance Exchange
2008 UT App 315 (Court of Appeals of Utah, 2008)
Ford v. American Express Financial Advisors, Inc.
2004 UT 70 (Utah Supreme Court, 2004)
Covey v. Covey
2003 UT App 380 (Court of Appeals of Utah, 2003)
Mahmood v. Ross
1999 UT 104 (Utah Supreme Court, 1999)
Brown v. Weis
871 P.2d 552 (Court of Appeals of Utah, 1994)
Anesthesiologists Associates of Ogden v. St. Benedict's Hospital
852 P.2d 1030 (Court of Appeals of Utah, 1993)
Anesthesiologists Assoc. v. ST. BENEDICT'S
852 P.2d 1030 (Court of Appeals of Utah, 1993)
Amax Magnesium Corp. v. Utah State Tax Commission
848 P.2d 715 (Court of Appeals of Utah, 1993)
LeBaron & Associates, Inc. v. Rebel Enterprises, Inc.
823 P.2d 479 (Court of Appeals of Utah, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
795 P.2d 678, 137 Utah Adv. Rep. 30, 1990 Utah App. LEXIS 111, 1990 WL 89018, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-call-engineering-inc-v-manti-city-corp-utahctapp-1990.