STATE OF MAINE SUPERIOR COURT CUMBERLAND, ss. CIVIL ACTION DOCKET NO. CV-19-353

JOHN B. PRIDE, INC.,

Plaintiff

v. ORDER ON MOTION TO DISMISS DEFENDANT'S COUNTERCLAIMS DANIELL. KINCH,

Defendant

The matter before the court is Plaintiff John B. Pride, Inc.'s ("Pride") motion to dismiss

Defendant Daniel Kinch's ("Kinch") counterclaims in this breach of contract action.

Factual Background

The following facts are drawn from Kinch's Counterclaim, which for the purposes of this

motion must be considered true.

Kinch owns a Terex 72-31 b Articulated Wheel Loader ("Loader") equipped with a

Detroit series 4-71 Model 1043-8300 diesel engine ("Engine"). (Def.'s Countercl., 1-2.) When

Kinch suspected that the Engine needed repairs, he contacted Pride seeking diagnostics and

repairs. (Def.'s Countercl., 2.) Pride estimated that he could rebuild the Engine for $14,523,

using what he considered to be "worst case scenario" figures. (Def.'s Countercl., 3.) On April

12, 2019, Kinch delivered the Loader to Pride so he could begin work. (Def.'s Countercl., 4.)

The contract was finalized at Pride's personal home on April 24, 2019. (Def.'s Countercl., 5.)

Under this contract, Pride would diagnose, repair and paint the Engine. (Def.'s Countercl." 3-5,

9 .) Kinch and Pride orally agreed that Kinch would use his own labor to lower the cost of the

repair. Id.

1 Unforseen problems arose during the repair, which lead to unexpected costs. (Def.'s

Countercl. l) 9.) Eventually, however, the Loader was returned to Kinch on May 28, 2019,

though the Engine was unpainted. Id. Pride's agents returned the following day to continue

reinstalling the Engine into the Loader. (Def.'s Countercl. l) 10.) During the course of that day,

Pride's agents damaged an essential "rubber intake boot." Id. Installation was completed and the

engine was tested by the end of the day. Id. Pride's agents stated that the repairs were complete

and normal operation of the Loader could resume. Id.

Pride communicated the final price for the repairs on May 31, 2019. (Def.'s Countercl. l)

11.) This price was $3688.40 greater than the estimate made by Pride before undertaking the

repair. Id. On June 2, 2019, Pride informed Kinch that there was a serious defect with the Engine

that could render the Engine totally unusable if he attempted to use the Loader. (Def.'s

Co.untercl. l) 12.) Pride promised to repair this defect. Id. Kinch ceased all use of the Loader after

receiving this information.

No repairs were conducted. Kinch reached out many times demanding "written

documentation" of the faulty part. (Def.'s Countercl. l)l) 15-27 .) After several

miscommunications, Pride managed to contact Kinch's father on July 19, 2019. (Def.'s

Countercl. lJ 20.) Pride told Kinch' s father that the correct part had been used in the repair and

there was no danger. Id. Kinch refused to accept Pride's assurance without written

documentation and continued to make repeated demands for such. (Def.'s Countercl. l)l) 21-27 .)

Kinch has not paid Pride for the work, nor has he resumed use of the Loader. (Def.' s Countercl. l)

28.)

2 Procedural History

On August 26, 2019, Pride filed a complaint alleging breach of contract, unjust

enrichment and Quantum Meruit against Kinch. After multiple unsuccessful attempts to serve

process on Kinch, this Court granted authorized service by alternate means on November 6,

2019. Kinch replied by filing what he called an "Affidavit of Default Judgement" and an

"Affidavit of Counter Claim" on December 18, 2019. Pride moved for default on December 19,

2019. On March 4, 2020, this Court denied the motion, and ordered that Kinch's "Affidavit of

Counter Claim" be treated as an answer and counterclaim. On March 19, 2020, Pride filed an

answer to Kinch's counterclaim. Pride then filed the present Motion to Dismiss Counterclaims

on June 16, 2020. Kinch is appearing prose.

Standard of Review

When ruling on a motion to dismiss for failure to state a claim pursuant to M.R. Civ. P.

12(b)(6), the court views the "facts alleged in the complaint as if they were admitted." Nadeau v.

Frydrych, 2014 ME 154, l) 5, 108 A.3d 1254 (per curiam) (quotation marks omitted). A complaint

must set forth the "elements of a cause of action or allege[] facts that would entitle the plaintiff to

relief pursuant to some legal theory." Id. Facts are read in the light most favorable to the plaintiff.

Id. "Dismissal is warranted only when it appears beyond a doubt that the plaintiff is not entitled

to relief under any set of facts that might be proved in support of the claim." Ha/co v. Davey, 2007

ME 48, l) 6,919 A.2d 626 (quotation marks omitted).

Rule 8 requires "a short and plain statement of the claim showing that the pleader is

entitled to relief." M.R. Civ. P. 8(a). "Notice pleading requirements are forgiving; the plaintiff

need only give fair notice of the cause of action by providing a short and plain statement of the

claim showing that the pleader is entitled to relief." Desjardins v. Reynolds, 2017 ME 99, ,i 17,

3 162 A.3d 228 (quotation marks omitted). On the other hand, "a party may not proceed[] on a

cause of action if that party's complaint has failed to allege facts that, if proved, would satisfy the

elements of the cause of action." Burns v. Architectural Doors and Windows, 2011 ME 61,, 17,

19 A.3d 823. Allegations of fraud must be plead with particularity. M.R Civ. P. 9(b). "Malice,

intent, knowledge, and other condition of mind ofa person may be averred generally." Id.

"Pro se litigants are held to the same standards are held to the same standards as

represented parties." Dep 't ofEnvtl. Prat. v. Woodman, 1997 ME 164,, 3 n.3, 697 A.2d 1295.

"This is particularly true in areas so fundamental as the service of process and the statement of a

claim." Uotinen v. Hall, 636 A.2d 991,992 (1994).

Discussion

Pride's motion to dismiss argues that Kinch's counterclaim asserts a single cause of

action for breach of contract. Pride argues that Kinch failed to allege a genuine breach and that

he failed to allege legally cognizable damages. (Pl.'s Mot. 4-6.) Kinch replies that he alleged 9

different ways that Pride breached its contractual duties. (Def.'s Reply 1.)

As a threshold matter, what Kinch refers to as "breach of contract" claims are actually a

mix of contract and tort claims. In particular, Kinch argues that Pride's instructions to stop usage

of personal property in issue indicated that they still had "possession and authority" of his

property. (Def.'s Reply 5.)

Breach of Contract

In order to state a claim for breach of contract, a legally binding contract must first exist.

Tobin v. Barter, 2014 ME 51, ! 9, 89 A.3d 1088. A contract exists when the parties "mutually

4 assent to be bound by all its material terms, the assent is either expressly or impliedly manifested

in the contract, and the contract is sufficiently definite to enable the court to ascertain its exact

meaning and fix exactly the legal liabilities of each party." Sullivan v. Porter, 2004 ME 134, 1

13,861 A.2d 625. Contracts may be oral or written.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Caron v. Bangor Publishing Co.
470 A.2d 782 (Supreme Judicial Court of Maine, 1984)
General Motors Acceptance Corporation v. Anacone
197 A.2d 506 (Supreme Judicial Court of Maine, 1964)
Halco v. Davey
2007 ME 48 (Supreme Judicial Court of Maine, 2007)
Uotinen v. Hall
636 A.2d 991 (Supreme Judicial Court of Maine, 1994)
Jones v. Suhre
345 A.2d 515 (Supreme Judicial Court of Maine, 1975)
Department of Environmental Protection v. Woodman
1997 ME 164 (Supreme Judicial Court of Maine, 1997)
Withers v. Hackett
1998 ME 164 (Supreme Judicial Court of Maine, 1998)
Sullivan v. Porter
2004 ME 134 (Supreme Judicial Court of Maine, 2004)
Burns v. Architectural Doors and Windows
2011 ME 61 (Supreme Judicial Court of Maine, 2011)
Philip C. Tobin v. Philip N. Barter
2014 ME 51 (Supreme Judicial Court of Maine, 2014)
Robert M.A. Nadeau v. Lynnann Frydrych
2014 ME 154 (Supreme Judicial Court of Maine, 2014)
Dana Desjardins v. Michael Reynolds
2017 ME 99 (Supreme Judicial Court of Maine, 2017)
Flynn Construction Co. v. Poulin
570 A.2d 1200 (Supreme Judicial Court of Maine, 1990)
Barley Mill, LLC v. Save Our County, Inc.
89 A.3d 51 (Supreme Court of Delaware, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
John B. Pride, Inc. v. Kinch, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-b-pride-inc-v-kinch-mesuperct-2020.