John B. Kelly, Inc. v. Aronimink Village Apartments, Inc.

122 F. Supp. 905, 1954 U.S. Dist. LEXIS 3337
CourtDistrict Court, E.D. Pennsylvania
DecidedJuly 26, 1954
DocketCiv. No. 11392
StatusPublished

This text of 122 F. Supp. 905 (John B. Kelly, Inc. v. Aronimink Village Apartments, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John B. Kelly, Inc. v. Aronimink Village Apartments, Inc., 122 F. Supp. 905, 1954 U.S. Dist. LEXIS 3337 (E.D. Pa. 1954).

Opinion

GRIM, District Judge.

By a contract dated May 12, 1948, plaintiff agreed to furnish the labor and-materials to do the brickwork in a large building development of the defendant for $1,420,000. Plaintiff completed the work, but defendant held back and refused to pay to plaintiff $50,068.74 out of the contract price contending that the work had not been done satisfactorily. In this action plaintiff has sued for this' sum. At the trial the jury awarded plaintiff a verdict in the sum of $56,500. The jury apparently concluded that some pointing in the brickwork had not been done satisfactorily and in its verdict apparently made an allowance to the defendant for the cost of repointing these bricks, plus interest on this sum. Defendant has filed a motion for a new trial.

As part of the contract between the parties and incorporated therein by. reference there were certain “terms and conditions”. Under these terms and conditions plaintiff was entitled to certain payments as the work progressed provided he obtained certain statements certifying that the work in . its various stages had been done satisfactorily.

The terms and conditions provided:

“Applications for payments under this contract shall be made by the Subcontractor [the plaintiff] to the Contractor1 [the defendant], when approved by the Architect, in quadruplicate * * * on or about the twénty-fifth day of each month after the commencement of work hereunder for payment for work .done during the preceding part of that month. The sum to which the Subcontractor shall be entitled upon any such payment shall be the cost of the portions of the work acceptably completed, as approved by the Architect, Contractor and the Commissioner [of the Federal Housing Administration] less ten per, cent (10%) and less prior advances * * The Subcontractor shall only be entitled to payments in the amount approved by the Architect, Contractor and the Commissioner with respect to the work covered by said application * * * Upon completion by the subcontractor of its contract with respect to each one of the four blocks * * * the entire balance due the subcontractor (including the ten per cent retained by the contractor) with respect to said block, shall be payable to the subcontractor upon the expiration of thirty days from the date of final completion of said block and acceptance of work by the Owner, the Contractor and the Architect with the approval of the Federal Housing Commissioner.”

In view of this clause in the contract, in order to recover plaintiff had to prove that his work had been approv[908]*908ed up to the final stage by the owner, the architect and the Federal Housing Administration. To do this plaintiff introduced into evidence certain statements executed from time to time during the progress of the work by the owner, the general contractor, the architect and the F.H.A. inspectors, certifying that as of the time of each statement the work had been done properly and in accordance with the requirements of the contract. Plaintiff also introduced statements of each of these parties after final completion certifying that one hundred per cent of the work had been done satisfactorily and in accordance with the requirements of the contract. Obviously these statements of approval were properly admissible in the trial of the case.

Because these certificates were in the record the trial judge affirmed a point for charge, which had beeen submitted by the plaintiff, which read as follows:

“The owners, the architect and the Federal Housing Administration have, each, certified in writing, that plaintiff has performed its contract.”

This point for charge states precisely what the evidence shows that these parties had done. Defendant does not contend that these certificates were inadmissible, but it contends that the point for charge should not have been affirmed, because in another part of the contract (the general conditions) it is provided that no certificate issued nor payment made to the subcontractor shall be an acceptance of any work or materials not in accordance with the requirements of the contract. This contention must be rejected. A reading of the entire charge will show2 that the issue as to whether or not the work had been done in accordance with the requirements of the contract was clearly left to the jury. The affirmance of the point for charge to which defendant objects in no way confused the jury and in no way took this fundamental issue from the jury. In my opinion it did nothing more than state a fact which was clearly in accord with the evidence in the case, and, therefore, no error was committed in affirming this point for charge.

Defendant filed a Counter-claim in which it averred that the contract price of $1,420,000 was arrived at by including in it the sum of $129,000 as payment for certain overtime wages which it was anticipated that plaintiff would be required to pay. It averred that the parties believed that in order to complete the work within the period desired by the owner and specified in the contract it would be necessary for plaintiff to work six days a week and to pay his employees double time for the Saturday work. It turned out, however, that plaintiff did his work so swiftly that he finished the job before the date specified in the contract and without having worked six days a week during part of the period of the construction. Because plaintiff did not work six days a week all the time it averred that plaintiff paid only $41,455 for Saturday overtime pay thereby saving $87,545 out of the $129,-000 allotted for overtime pay. It was averred that defendant is entitled to recover this $87,545 from plaintiff, both because this would carry out the implied understanding between the parties and because plaintiff will be unjustly enriched by this amount, if plaintiff is permitted to retain it.

At the time of the trial defendant attempted to prove the averments in the Counter-claim. Plaintiff objected to proof of these averments on the ground that proof of them was inadmissible under the parol evidence rule, and the trial judge sustained the objection. This ruling of the trial judge is assigned as error in the motion for a new trial.3

[909]*909Defendant points to a sentence in the contract as the basis for its contention that proof was admissible to show that the contract price was to be reduced by the amount which plaintiff could save by not working on Saturdays. This sentence is: “This contract is based on working six (6) days a week.” Defendant contends that these words are so ambiguous or that they create so obvious an omission in the contract that parol evidence is admissible to explain what they mean. This contention must be rejected. Immediately following these words in the contract is a paragraph headed “Time of Completion”, which states: “ * * * completion to the satisfaction of the Architect and the Contractor shall be had on or before July 1, 1949.” When these two sentences are read together they mean quite clearly and simply that plaintiff was required to complete the work satisfactorily by July 1, 1949, and to do this it had to work six days a week until the job was done unless it could finish the work satisfactorily before July 1, 1949, without working six days a week.4 It is true that the thought expressed in these sentences could have been stated with more precision, but in my opinion it has been expressed clearly enough to make the problem one of construction rather than a problem of parol evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walker v. Saricks
63 A.2d 9 (Supreme Court of Pennsylvania, 1948)
Gianni v. Russell Co., Inc.
126 A. 791 (Supreme Court of Pennsylvania, 1924)
Priestman-Helmetag Co. v. Wolf
177 A. 30 (Supreme Court of Pennsylvania, 1935)
Pennsylvania Co. v. Lebanon Building & Loan Ass'n
10 A.2d 418 (Supreme Court of Pennsylvania, 1939)
First Nat. Bk. of Scranton v. Payne
37 A.2d 568 (Supreme Court of Pennsylvania, 1944)
O'Brien v. O'Brien
66 A.2d 309 (Supreme Court of Pennsylvania, 1949)
Nallin-Jennings Park Co. v. Sterling
73 A.2d 390 (Supreme Court of Pennsylvania, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
122 F. Supp. 905, 1954 U.S. Dist. LEXIS 3337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-b-kelly-inc-v-aronimink-village-apartments-inc-paed-1954.