John Arborio, Inc. v. Cox

59 A.2d 296, 134 Conn. 545, 1948 Conn. LEXIS 150
CourtSupreme Court of Connecticut
DecidedApril 22, 1948
StatusPublished

This text of 59 A.2d 296 (John Arborio, Inc. v. Cox) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Arborio, Inc. v. Cox, 59 A.2d 296, 134 Conn. 545, 1948 Conn. LEXIS 150 (Colo. 1948).

Opinion

Maltbie, C. J.

In this action the plaintiff corporation, which had made a contract with the state highway department to construct a section of the Wilbur Cross Parkway, seeks to recover additional compensation for certain work it did in excavating for a connecting road between the parkway and another highway, on the ground that the work was not within the scope of its contract, and for the making of a ■fill with “selected” rock, on the ground that it was not required by its contract to use that material. Permission to bring the action was granted by the General Assembly. 24 Spec. Laws 16. The trial court rendered judgment for the defendant and the plaintiff has appealed.

The finding contains numerous paragraphs stating conclusions of law as to the obligations of the plaintiff which it claims to be erroneous; these are necessarily involved in the discussion which follows and we shall not refer to them specifically. Assignments of error in the finding of facts and in the failure of the trial court to make other requested findings will, so far as material, be considered in connection with the issues to which they are relevant.

The contract on its title page is designated as “Town No. 185, Project No. 33,” and it states that it is for the grading and drainage of a section of the Wilbur Cross Parkway in the towns of Hamden and North Haven “from Sta. 132 -f- 0 to Sta. 273 + 0,” a length of 12,586.2 feet. The parkway ran generally in an easterly and westerly direction and station 273 was at the easterly end of the portion in question. *547 The excavation which the plaintiff claims was not in the contract was made in the course of the construction of a temporary connection between the parkway and a highway known as the Old Hartford Turnpike. The connecting road started at about station 273 and ran a considerable distance to the east, curving away from the main line of the parkway. The contract provided that payment for work done under it should be made “at the unit prices bid by said Contractor for the respective estimated quantities and such other items as are contained in its original proposal,” and attached to the contract was a “Schedule of Prices as quoted on the ‘Proposal Form.’ ” When the plaintiff was directed to proceed to excavate for the road, it contended that the work was outside its contract, but finally performed it under protest. Its claim is that it was paid upon the basis of the price fixed in the schedule for “unclassified excavation,” but that it was entitled to payment at a higher price because the excavation was almost wholly of rock.

The contract contains a provision that the contractor’s “proposal together with the Standard Specifications, Form 805, are made a part of this Contract and accepted as such and also the plans of the work, prepared or approved by the State Highway Department, which plans as verified by said Department, are also agreed by each party as being a part hereof.” In determining the scope of the work contracted to be done, it is necessary, therefore, to examine not only the contract but the specifications and plans made a part of it. The specifications contained a provision: “Any requirements appearing on either the plans, these specifications or the ‘Special Provisions’ shall be equally binding on the Contractor.” There are a number of special provisions *548 attached to the contract but none are involved in this case.

The plans consisted of a large number of separate sheets. One of them, an “Index” map, and two others, covering a section of the highway beginning at station 265 and extending to station 278, designate station 273 as “End of Project.” The “Index Map” has, however, a label, “Grade Temporary Connection,” with an arrow pointing to a place beyond station 273. On one of the others the connection to the turnpike beginning at about station 273 and continuing to station 278 is plainly outlined, and there is a label, with an arrow pointing to the outline of the connection, stating, “Grade a temporary connection to Old Hartford Turnpike”; below it is the further direction, “Sta. 273 -f- 0 to Old Hartford Turnpike install 12" Subbase as directed under temporary connection.” The third plan, which contains details of the construction of a bridge over the turnpike at a point somewhat easterly of station 273, has a label, with arrows pointing to places beyond that station, which states: “Grade Temporary Connection to Old Hartford Turnpike.” While it is true that the plans do include some work admittedly not within the scope of the plaintiff’s undertaldng, these clear references to and specific directions as to the grading of the connection indicate strongly that the contract was intended to include it.

This is definitely established by other evidence. Another sheet of the plans is headed “Detailed Estimate Sheet for the Construction of Grading and Drainage On A Section Of The Wilbur Cross Parkway . . . from Sta. 132 -f- 0 to Sta. 273 + 00, length 12,836.20 feet”; then below the last portion of this statement is a further entry, “Approaches to the Parkway 4226.39,” and an addition of this figure *549 to the 12,836.20 feet designated above, making a total of 17,062.59 feet. Below this is a table headed “Excavation and Borrow,” which gives the amount required for such work, “Sta. to Sta.,” and beneath are four columns, one giving the station where the work was to begin, another where it was to end; a third is headed “Unclassified Excavation,” and a fourth, “Earth Fill.” In this table one item, entered in the first three columns, was “270 -f- 0 | 275 + 0 | 55777,” and another, entered in all four columns, was “275 + 0 | 276 + 50 | 1509 112.” The total of the column headed “Unclassified Excavation” is given as 429,248, and the total of that headed “Earth Fill” as 572,678; and these totals include the two items quoted above as regards both excavation and fill. The total amount of “unclassified excavation” given in this table exactly corresponds with the amount of “unclassified excavation” stated in the “Schedule of Prices” attached to the “Proposal Form” submitted by the plaintiff in its bid for the work, a copy of which is attached to and incorporated in the contract.

On September 29,1941, the plaintiff wrote the defendant a letter in which it was suggested that the contract be changed so that “borrow,” that is, material from outside the limits of the highway, should be used for the embankment to which we later refer. A sentence in this letter is in part as follows: “We were wondering if it would not be to our material advantage to use this borrow material instead of using the last cut on our contract between Sta. 270 + 00 to Sta. 276 + 50.” Aside from the testimony of the plaintiff’s vice-president, who wrote the letter, that the figures 276 + 50 were taken from the plans, we would assume this to be so. The figures are found on the “Detailed Estimate Sheet,” which *550 includes the two items previously referred to: one, between stations 270 and 275, 55,777 cubic yards of excavation; and the other, between stations 275 and 276 + 50, 1509 cubic yards of excavation and 12 cubic yards of earth fill. It is an inescapable conclusion that the work upon the connecting road was within the contemplation of the plaintiff when it submitted its bid and within the scope of its contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
59 A.2d 296, 134 Conn. 545, 1948 Conn. LEXIS 150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-arborio-inc-v-cox-conn-1948.