John A. Johnson Contracting Corp. v. Maryland Casualty Co.

274 A.D. 798, 80 N.Y.S.2d 112, 1948 N.Y. App. Div. LEXIS 3396

Opinion

In an action by a general contractor against a subcontractor, and the surety on the latter’s performance bond, to recover damages for breach of contract, in that the subcontractor failed to proceed diligently in the performance of its work, the jury found in favor of plaintiff both on its claim and on the subcontractor’s two counterclaims. Judgment, entered on the verdict of a jury in favor of plaintiff, unanimously affirmed, with costs. No opinion. Present — Lewis, P. J., Carswell, Johnston, Adel and Sneed, JJ. [See post, p. 854.]

Free access — add to your briefcase to read the full text and ask questions with AI

John A. Johnson Contracting Corp. v. Maryland Casualty Co., 274 A.D. 798, 80 N.Y.S.2d 112, 1948 N.Y. App. Div. LEXIS 3396 (N.Y. Ct. App. 1948).

274 A.D. 798 (John A. Johnson Contracting Corp. v. Maryland Casualty Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.