John A. Hall Construction Co. v. Boone & Darr, Inc.

302 N.W.2d 850, 102 Mich. App. 786, 1981 Mich. App. LEXIS 2666
CourtMichigan Court of Appeals
DecidedJanuary 21, 1981
DocketDocket 78-3900
StatusPublished
Cited by6 cases

This text of 302 N.W.2d 850 (John A. Hall Construction Co. v. Boone & Darr, Inc.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John A. Hall Construction Co. v. Boone & Darr, Inc., 302 N.W.2d 850, 102 Mich. App. 786, 1981 Mich. App. LEXIS 2666 (Mich. Ct. App. 1981).

Opinion

N. J. Kaufman, J.

Defendants, A. F. Smith & Son, Inc. (Smith) and Boone & Darr, Inc. (B&D), appeal from a decision of the Washtenaw County Circuit Court rendered April 18, 1978, which denied their right to recover on a payment bond furnished by plaintiff, John A. Hall Construction Company (Hall) and secured by United States Fidelity & Guaranty Co. (USF&G).

On March 19, 1971, Hall submitted its successful bid as general contractor for the construction of Ypsilanti Public High School. Pursuant to the terms of the construction contract, Hall provided a labor and material bond, with itself as principal and USF&G as surety. Hall then entered into a subcontract agreement with JS&J Construction Co. (JS&J) to supply the mechanical and electrical labor and materials.

*789 JS&J was a wholly-owned subsidiary of Hall, John A. Hall being president of both corporations. JS&J entered into a contract with A. F. Smith & Son, Inc. (Smith) to supply electrical work for the project and into another contract with Boone & Darr, Inc. (B&D) for the mechanical portion of the contract. Performance was secured with bonds issued by Seaboard Surety Company for Smith and Fidelity & Casualty Company of New York for B& D. During the course of construction, invoices were rendered by Smith and B&D to JS&J and payments were made by JS&J.

In the latter stages of construction, disputes arose among the parties which resulted in the filing of suit by Hall and JS&J against Smith and B&D. Counterclaims were filed by defendants against Hall and JS&J. A third-party complaint was filed against USF&G seeking recovery on the bond secured by them.

On May 22, 1975, motions for summary judgments were filed by Hall and USF&G. Hall’s motion was based upon the absence of any contractual relationship between it and the defendants, founded on the allegation that Hall and JS&J were separate and distinct corporations. Hall also requested voluntary dismissal of its claims against defendants. Both requests were granted and an order dismissing Hall’s action was filed October 2, 1975. USF&G’s motion for summary judgment was denied by the same order. In its opinion, the lower court concluded that since defendants alleged adequate notice under MCL 129.207; MSA 5.2321(7), and USF&G failed to controvert this allegation, a question of fact remained, thus precluding summary judgment.

Trial commenced October 1, 1975, and, after extensive inquiry, the circuit court concluded that *790 Hall directed and controlled the entire construction project and that JS&J was merely a "shell” corporation. Accordingly, on January 23, 1976, Hall Construction was reinstated as a party-plaintiff.

Further proofs were submitted and Hall filed a motion for reconsideration of the court’s order for reinstatement. This motion was granted and, on May 31, 1977, Hall was again dismissed as a party to the action.

On August 22, 1977, USF&G moved for dismissal or judgment in its favor on the ground that defendants had failed to establish compliance with MCL 129.207; MSA 5.2321(7). In an opinion rendered eight months later, the court found JS&J’s claims against defendants to be without merit, except for a $2,614.41 claim against B&D. The court held that defendants were entitled to judgment on their counterclaims against JS&J for $155,573.36 (B&D) and $72,957.32 (Smith). The court found that the absence of a direct contractual relationship between defendants and Hall and the fact that Hall and JS&J were separate and individual corporations precluded defendants’ recovery against Hall. The court further held that defendants’ failure to comply with MCL 129.207; MSA 5.2321(7) foreclosed defendants’ suit against USF&G, and that action was, therefore, dismissed. Defendants appeal from the circuit court’s decision denying their right to recover on the payment bond furnished by Hall and secured by USF&G.

Defendants raise three issues, two of which have been properly preserved for appeal. Defendants first contend that they established a "direct contractual relationship” between themselves and Hall which would allow recovery on the payment bond.

*791 The focus of this controversy is the language of MCL 129.207; MSA 5.2321(7). This section entitles a "claimant” who has furnished labor or material in the performance of the contract to sue "on the payment bond for the amount, or balance thereof, unpaid at the time of the institution of the civil action”. Crucial to the present controversy, however, is that language of the section which reads in pertinent part:

"Sec. 7 * * * A claimant not having a direct contractual relationship with the principal contractor shall not have a right of action upon the payment bond unless (a) he has within 30 days after furnishing the first of such material or performing the first of such labor, served on the principal contractor a written notice, which shall inform the principal of the nature of the materials being furnished or to be furnished, or labor performed or to be performed and identifying the party contracting for such labor or materials and the site for the performance of such labor or the delivery of such materials, and (b) he has given written notice to the principal contractor and the governmental unit involved within 90 days from the date on which the claimant performed the last of the labor or furnished or supplied the last of the material for which the claim is made * * *. Each notice shall be served by mailing the same by certified mail * * *.”

Defendants’ first issue centers on that portion of the statute requiring a "direct contractual relationship with the principal contractor”. The question is whether the defendants established a "direct contractual relationship” with Hall and are thereby entitled to the protection afforded by the statute.

In support of their position, defendants point to the intricate relationship between Hall and JS&J, noting that JS&J is a wholly-owned subsidiary of *792 Hall, John Hall was the sole shareholder of Hall and was the president of both corporations. The corporations had the same vice-president and identical boards of directors.

Additionally, defendants assert that the alleged JS&J representatives who were running the operation of the project were not from JS&J, but were from Hall. There was no performance or payment bond secured from JS&J by Hall.

It is clear to this Court that the proofs reveal two separate corporate entities controlled by one individual who had established adequate safeguards to shield the parent corporation but had secured no protection for parties dealing with the "shell” corporation. Although defendants admit to having only express contractual ties with the "shell” corporation, they claim that the owner and president of the parent corporation functioned in a dual capacity such that the two corporations should be regarded as one.

Guidance in interpreting the phrase, "direct contractual relationship” is provided by judicial interpretation of the Federal counterpart of the Michigan notice statute. The Miller Act, 40 USC 270a

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pi-Con, Inc. v. a J Anderson Construction Co.
458 N.W.2d 639 (Michigan Supreme Court, 1990)
Tempco Heating & Cooling, Inc v. a Rea Construction, Inc
443 N.W.2d 486 (Michigan Court of Appeals, 1989)
Pi-Con, Inc v. A. J. Anderson Construction Co.
425 N.W.2d 563 (Michigan Court of Appeals, 1988)
SQUARE D. ENVIRONMENTAL CORP. v. Aero Mechanical, Inc.
326 N.W.2d 629 (Michigan Court of Appeals, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
302 N.W.2d 850, 102 Mich. App. 786, 1981 Mich. App. LEXIS 2666, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-a-hall-construction-co-v-boone-darr-inc-michctapp-1981.