Jiménez y Salellas, Inc. v. Maryland Casualty Co.

92 P.R. 200
CourtSupreme Court of Puerto Rico
DecidedApril 1, 1965
DocketNo. CE-64-10
StatusPublished

This text of 92 P.R. 200 (Jiménez y Salellas, Inc. v. Maryland Casualty Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jiménez y Salellas, Inc. v. Maryland Casualty Co., 92 P.R. 200 (prsupreme 1965).

Opinion

Mr. Justice Rigau

delivered the opinion of the Court.

The Puerto Rico Industrial Development Company contracted with Brico Construction Co. for the construction of a building. Brico Construction would construct it. Development required Brico to post the bond required by law whenever the Government or one of its agencies contracts for the construction of some work, 22 L.P.R.A. §§47 and 58. On the terms of the bond, the law provides the following:

“The above-mentioned bond shall be posted by the contractor in cash, by certified check, or through the surety of a bonding company authorized to do business in Puerto Rico, and said payment bond shall secure jointly and severally with the contractor, to the extent of liability covered by the bond, (1) the payment, to the workers and employees of the contractor, of the salaries and wages earned by them in their work; and (2) the payment, to the persons selling, supplying, or delivering equipment, tools, and materials for the work, of the price or value of the materials, equipment, and tools supplied, sold or delivered. The amount of this payment bond shall be not less than one-half of the total value of the contract, plus any amplification, enlargement, or addition thereto.” 22 L.P.R.A. § 48 (vol. 5, 1964 ed., p. 15).

Brico posted the corresponding bond, defendant being the bonding company.

Brico subcontracted with plaintiff-appellant for the construction of the roof of the building for the price of $5,298.72. Appellant performed its part of the contract, but Brico still owed $1,000 to plaintiff. Plaintiff filed an action of debt against the bonding company. The District Court dismissed [202]*202the complaint on the ground that plaintiff’s cause- of action had prescribed. The Superior Court affirmed. We issued a writ of certiorari.

Appellant assigns before us the following two errors: (1) that the Superior Court erred in holding that the prescriptive term referred to in the Act is not susceptible ■ of interruption by an extrajudicial claim; and (2) that the court erred in failing to pass on plaintiff’s contention that defendant was barred from raising the defense of prescription to resist the complaint. For the purposes of discussion, we have inverted the order in which appellant assigns them.

Before passing upon the two questions raised, let us examine briefly the course of the legislative and judicial actions which have created the present state of law on this matter. It was not until the enactment of Act No. 388 of May 9, 1951 (Sess. Laws, p. 948), that the subcontractors and materialmen in the public works were protected by a performance bond against the insolvency or refusal of the contractors to pay the debts incurred for services and materials supplied to them. The former Act, No. 31 of April 23, 1931 (Sess. Laws, p. 340), limited its protection to the laborers and employees working on such works. Furthermore, irrespective of the Act of 1931 supra, the state of law prior to Act No. 388 of 1951 practically denied to the materialmen and subcontractors any protection against the insolvency or reluctance of contractors to pay, owing to the former judicial attitude of strictly construing the bond contracts. In Cristy & Sánchez v. Commonwealth, 84 P.R.R. 226 (1961), we reexamined the judicial precedents applicable at that time to bonds in the construction of public works. There we expressly overruled the cases of Municipality of Fajardo v. Axtmayer et al., 31 P.R.R. 780 (1923); Morales v. Chabert, 43 P.R.R. 114 (1932); and Battle v. Pereyó, 67 P.R.R. 621 (1947), and held that, considering jointly the bond instrument, the General Specifications and the public works con[203]*203tract, the materialmen and labor, including the subcontractors, were covered'by the bond contract.1

We also said in Cristy, supra, that the strict construction of bonds gained favor at a time- when the personal bondsmen, by a mere act of liberality, secured the contract, but that times had changed with the advent of surety companies making a business of acting as surety for compensation. We pointed out that the liberal or broad construction in these cases is controlling. Cristy, supra at 234. We have reaffirmed that position in subsequent decisions. See Ulpiano Casal, Inc. v. Totty Manufacturing Corp., 90 P.R.R. 719 (1964); A. L. Arsuaga, Inc. v. La Hood Const., Inc., 90 P.R.R. 101 (1964). Cf. Maryland Casualty Co. v. Quick Construction Corp., 90 P.R.R. 323 (1964).

Let us examine the first error assigned. The legal provision referred to by appellant in its assignment of error is § 9 of Act No. 388 of May 9, 1951, 22 L.P.R.A. § 55, which reads as follows:

“The cause for action authorized under sections 47-58 of this title against the bond and the bondsmen of the contractor shall be understood to have prescribed six months after final acceptance of the work by the Commonwealth of Puerto Rico. After such period has elapsed, the bond may be cancelled, unless some judicial claim under sections 47-58 of this title is found pending. In such case, the bond shall not be cancelled until final judgment has been entered with respect to the pending claim or claims and same have been satisfied to the limit of the liability of the bond and the bondsmen.”

The work in question was accepted by the Industrial Development Company on January 18, 1962. The complaint was filed on February 20, 1963, or 13 months after acceptance of the work. Appellant contends that the six-month period established by the provision copied above was inter[204]*204rupted by the extrajudicial claims which it instituted. It invokes § 1873 of the Civil Code, 31 L.P.R.A. § 5303, which provides:

“Prescription of actions is interrupted by their institution before the courts, by extrajudicial claim of the creditor, and by any act of acknowledgment of the debt by the debtor.”

■ Appellee maintains that plaintiff’s cause of action prescribed upon expiration of the six-month period provided by law without plaintiff having instituted any judicial action. The District Court concluded that plaintiff’s cause of action “prescribed and was extinguished,” pursuant to the provisions of 22 L.P.R.A. § 55 supra. The Superior Court upheld the District Court and stated that “as to the bond and the bondsmen, the six-month term is fatal if there is no judicial claim.”

Appellant is not right because the term in question is one of extinguishment rather than of prescription. The Act itself, by its own terms, decides the contention when it expressly states that “After such period [of six months] has elapsed, the bond may be cancelled, unless some judicial claim under sections 47-48 of this title is found pending.” 22 L.P.R.A. § 55. (Italics ours.) In the absence of that provision, perhaps there would be merit in appellant’s contention, but it is idle to argue against the express letter of the law. As we have seen, the law requires that judicial claim shall have been instituted. This is a case in which, as observed by Pérez González and Alguer, from the literal wording of the provision we must conclude that it is one of extinguishment rather than of prescription.2 Cf. Sec. of Labor v. Superior Court, 91 P.R.R. 831 (1965); Eisele v. Orcasitas, 85 P.R.R. 84 (1962); and Felici v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
92 P.R. 200, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jimenez-y-salellas-inc-v-maryland-casualty-co-prsupreme-1965.