Jimco, Inc. v. Paving Contractors, Inc.

546 So. 2d 881, 1989 La. App. LEXIS 1340, 1989 WL 70430
CourtLouisiana Court of Appeal
DecidedJune 20, 1989
DocketNo. CA 88 0814
StatusPublished
Cited by1 cases

This text of 546 So. 2d 881 (Jimco, Inc. v. Paving Contractors, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jimco, Inc. v. Paving Contractors, Inc., 546 So. 2d 881, 1989 La. App. LEXIS 1340, 1989 WL 70430 (La. Ct. App. 1989).

Opinion

LANIER, Judge.

This action commenced as a suit in contract on an open account and for recognition of a materialman’s privilege on immovable property. The plaintiff is a supplier of concrete, and the defendants are the owners of the immovable property and the building contractor doing work on the immovable property. Judgment was stipulated in favor of the supplier and against the contractor for $15,563.69, with legal interest thereon from date of judicial demand until paid, a reasonable attorney fee and all costs. The claim against the landowners on the privilege was dismissed. The supplier took this suspensive appeal.

FACTS

Prior to July of 1986, Robert C. Lauer and George E. Schamberger were the owners of two contiguous tracts of land located near the City of Mandeville in St. Tammany Parish, Louisiana. Lauer and Schamber-ger commenced developing this property into a subdivision known as Audubon Trace. They contracted with Paving Contractors, Inc. (Paving) to do the necessary work. Lauer was the only officer, director and stockholder of Paving.

During the period of April 4, 1986, to July 3, 1986, Paving purchased $15,563.69 worth of concrete from Jimco, Inc. (Jimco) for the subdivision. Paving subcontracted with James Butler to do the concrete work for the subdivision. Paving never paid Jimco’s bill.

On July 2, 1986, Lauer executed a residential marketing agreement with Merrill Lynch Realty for the sale of Lots 1 [882]*882through 5 of Audubon Trace. This agreement expired on January 2, 1987. Merrill Lynch Realty put signs on the property. No lots were sold because the subdivision was never finally approved by St. Tammany Parish (Parish).

On September 19, 1986, Schamberger and his wife, Faith G. Schamberger, sold their interest in Audubon Trace to Lauer and his wife, Lisa M. Lauer, for $127,-290.42. On that same date, Mr. and Mrs. Lauer executed a collateral mortgage on Audubon Trace subdivision for $500,000, payable at the First Bank in Mandeville, Louisiana.

On December 17, 1986, Jimco filed a statement of its claim and privilege for materials furnished for work done in Audubon Trace subdivision.

On July 1, 1987, the branch manager for Coldwell Banker Residential Real Estate Services (Coldwell Banker) in Mandeville, Louisiana, sent the following letter to Lauer:

As per our discussion yesterday, concerning Audubon Trace Subdivision, it is my recomendation [sic] that in order to liquidate your lot inventory within a 12 month period, the following must be done:
1. All subdivision improvements must be complete.
2. General clean-up of subdivision and surrounding area (trash litter, underbrush, dead and fallen branches).
3. Lot prices must be drastically reduced to the price range of $16,000 to $17,000.
4. Construction must be started on at least 3 homes. These homes must sell in the $80’s to low $90’s and square footage to be 1700-1800.
If you have any questions, please give me a call.

Lauer testified no attempt to complete the construction of the subdivision took place after July of 1986. The latest Butler could have been at the subdivision was August of 1986. Although the subdivision was given preliminary approval by the Parish, it never received final approval because the sewerage treatment plant was not installed and, thus, the project was never completed. Lauer never talked to the Parish about the subdivision after July of 1986. Because the subdivision never received final approval by the Parish, the subdivision lots could not be legally sold. The bank refused to give further financing to Lauer in July of 1986. Because Lauer ran out of money and could get no further financing, no further construction was done after July of 1986. Lauer needed an additional $65,000 to $75,000 to finish the development. Lauer acquired the Scham-berger interest in the subdivision in September of 1986 and consolidated all of his obligations to the bank under one collateral mortgage. No money was advanced to him at this time. The last money Lauer received from the bank was in June or July of 1986. Paving had no recorded contract with Lauer.

Eddie Price, a Jimco sales representative, testified he checked the subdivision every two or three weeks for Jimco. Numerous attempts to contact Paving about payment were made, but none were successful. On October 28, 1986 (Price’s birthday), Price inspected the subdivision and observed that concrete aprons had been poured. Price did not see the actual pouring. Price acknowledged that the aprons could have been poured as early as October 7, 1986.

PRIVILEGE UNDER LOUISIANA PRIVATE WORKS ACT

(Assignments of Error Numbers 1, 2 and 3)

Jimco contends the trial court erred by finding that the Lauers abandoned the work on the subdivision more than 60 days prior to the date it recorded its statement of claim and privilege. Jimco asserts there was no abandonment as contemplated by La.R.S. 9:4822(C)(2) and (I) because work continued on the site as late as October of 1986, the Lauers had a marketing agreement with Merrill Lynch Realty that did not expire until January of 1987, the Lauers bought the Schamberger interest in the subdivision and refinanced with the bank in September of 1986, and, in July of [883]*8831987, Mr. Lauer consulted with Coldwell Banker about marketing the subdivision.

Jimco’s (the subcontractor) contract was with Paving (the general contractor); it was not with the Lauers (the owners). Thus, there are no contractual legal relations between Jimco and the Lauers. One of the purposes of the Louisiana Private Works Act (Act), La.R.S. 9:4801 et seq., is to create a privilege in favor of subcontractors, which attaches to the owner’s property, and, thus, protects the subcontractors. Marshall Achord Electrical Contractor, Inc. v. Zeagler, 527 So.2d 51 (La.App. 3rd Cir.1988). Pursuant to La.R.S. 9:4802(A)(3) and (B), Jimco had a claim (cause of action) against the Lauers secured by a privilege on the subdivision for the purchase price of the concrete furnished in developing the subdivision. Pursuant to La.R.S. 9:4823(A)(1), Jimco’s claim and privilege was extinguished if not preserved in the manner prescribed in La.R.S. 9:4822. Because no notice of the Lauer-Paving general contract was filed in accordance with La.R.S. 9:4811 and no notice of termination of the work was filed, the procedure for Jimco to use to preserve its claim and privilege is set forth in La.R.S. 9:4822(C)(2) and (I) as follows:

C. Those persons granted a claim and privilege by R.S. 9:4802 for work arising out of a general contract, notice of which is not filed, and other persons granted a privilege under R.S. 9:4801 or a claim and privilege under R.S. 9:4802 shall file a statement of their respective claims and privileges within sixty days after:
[[Image here]]
(2) The substantial completion or abandonment of the work, if a notice of termination is not filed.
[[Image here]]
I. A work is abandoned by the owner if he terminates the work and notifies persons engaged in its performance that he no longer desires to continue it or he otherwise objectively and in good faith manifests the abandonment or discontinuance of the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nu-Lite Electrical Wholesalers, LLC v. Alfred Palma Inc.
878 So. 2d 660 (Louisiana Court of Appeal, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
546 So. 2d 881, 1989 La. App. LEXIS 1340, 1989 WL 70430, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jimco-inc-v-paving-contractors-inc-lactapp-1989.