Jim Topolski D/B/A American Deck & Sunroom Company v. Mary Johnson

Court of Appeals of Kentucky·Decided May 30, 2024·No. 2023 CA 000998·Unknown

Opinion

RENDERED: MAY 31, 2024; 10:00 A.M.

NOT TO BE PUBLISHED

Commonwealth of Kentucky

Court of Appeals

NO. 2023-CA-0998-MR

JIM TOPOLSKI D/B/A AMERICAN DECK & SUNROOM COMPANY APPELLANT

APPEAL FROM FAYETTE CIRCUIT COURT v. HONORABLE THOMAS L. TRAVIS, JUDGE ACTION NO. 17-CI-00023

MARY JOHNSON APPELLEE

OPINION

REVERSING AND REMANDING

** ** ** ** **

BEFORE: THOMPSON, CHIEF JUDGE; A. JONES AND LAMBERT, JUDGES.

THOMPSON, CHIEF JUDGE: Jim Topolski, d/b/a American Deck & Sunroom Company, appeals from a judgment of the Fayette Circuit court ordering him to pay over eight thousand dollars to Mary Johnson for breach of contract. We reverse and remand because the judgment was unclear on one issue and additional findings are necessary.

FACTS AND PROCEDURAL HISTORY Appellee contracted with Appellant to construct a deck onto her home. The plans for the deck included a ramp from the ground onto the deck for access and a fire pit. Appellee claimed that the fire pit was to be built in and the ramp was to be wheelchair accessible. After the deck was completed, there was no fire pit and the ramp was not suitable for a wheelchair. Appellant claimed that there was never a discussion regarding the ramp being suitable for a wheelchair. Appellant also claimed that the fire pit could not be built into the deck due to the materials Appellee chose to build the deck out of.

The underlying suit came about because Appellee refused to pay Appellant a final payment of $7,212.00. Appellant sued for breach of contract. He also sought attorney fees based on language in the contract allowing him to collect such. Appellee countersued for breach of contract and fraud. A bench trial was ultimately held. At the trial, Appellant, Appellee, and an expert hired by Appellee all testified. The trial court concluded that Appellant breached the contract by not building a built-in fire pit, by not building a handicapped accessible ramp, and by not obtaining a building permit. The court awarded Appellee $15,863.08. This was the amount testified to by Appellee’s expert that it would cost to modify the deck to include a built-in fire pit, handicapped accessible ramp, and other repairs and modifications. The trial court then reduced that award by the $7,212.00

Appellee owed to Appellant. The court also declined to award either party attorney fees. Appellant then filed a motion to alter, amend, or vacate; however, that motion was denied. This appeal followed.

ANALYSIS

Appellant argues on appeal that the trial court erred in not enforcing the contract as written because it was unambiguous. He also argues that the court erred by finding that he breached the contract by not building a wheelchair accessible ramp and built-in fire pit. He argues that the contract did not mention that the ramp was to be wheelchair accessible or that the fire pit was to be built in.

The interpretation of a contract, including determining whether a contract is ambiguous, is a question of law for the courts and is subject to de novo review.

In the absence of ambiguity, a written instrument will be enforced strictly according to its terms, and a court will interpret the contract’s terms by assigning language its ordinary meaning and without resort to extrinsic evidence. Courts will find that a contract is ambiguous where a reasonable person would find it susceptible to different or inconsistent interpretations.

If there is no ambiguity in the contract, a reviewing court must determine the intention of the parties from the four corners of that instrument. Further, [i]n the absence of ambiguity a written instrument will be enforced strictly according to its terms, and a court will interpret the contract’s terms by assigning language its ordinary meaning and without resort to extrinsic evidence. The fact that a party may have intended different results is inadequate to construe a contract at variance with its plain and unambiguous terms.

Superior Steel, Inc. v. Ascent at Roebling’s Bridge, LLC, 540 S.W.3d 770, 783-84 (Ky. 2017) (internal quotation marks and citations omitted). “Where a contract is ambiguous or silent on a vital matter, a court may consider parol and extrinsic evidence involving the circumstances surrounding execution of the contract, the subject matter of the contract, the objects to be accomplished, and the conduct of the parties.” Cantrell Supply, Inc. v. Liberty Mut. Ins. Co., 94 S.W.3d 381, 385 (Ky. App. 2002) (citations omitted). “However, once a court determines that a contract is ambiguous, areas of dispute concerning the extrinsic evidence are factual issues and construction of the contract become subject to resolution by the fact-finder.” Id. The trial court’s findings of fact are then reviewed under the clearly erroneous standard.

The Court of Appeals . . . [is] entitled to set aside the trial court’s findings only if those findings are clearly erroneous. And, the dispositive question that we must answer, therefore, is whether the trial court’s findings of fact are clearly erroneous, i.e., whether or not those findings are supported by substantial evidence.

“[S]ubstantial evidence” is “[e]vidence that a reasonable mind would accept as adequate to support a conclusion”

and evidence that, when “taken alone or in the light of all the evidence, . . . has sufficient probative value to induce conviction in the minds of reasonable men.” Regardless of conflicting evidence, the weight of the evidence, or the fact that the reviewing court would have reached a contrary finding, “due regard shall be given to the opportunity of the trial court to judge the credibility of the witnesses” because judging the credibility of witnesses and weighing evidence are tasks within the

exclusive province of the trial court. Thus, “[m]ere doubt as to the correctness of [a] finding [will] not justify [its]

reversal,” and appellate courts should not disturb trial court findings that are supported by substantial evidence.

Moore v. Asente, 110 S.W.3d 336, 353-54 (Ky. 2003) (footnotes and citations omitted).

Here, the court held that Appellee had a “reasonable expectation” that the fire pit would be built in and appropriate materials would be used. The court also held that Appellee had a “reasonable expectation” that the ramp would be wheelchair accessible. The court held that by not building these two features as such, Appellant breached the contract. The court did not use the term “ambiguous” in its judgment, but by using the “reasonable expectation” language and allowing extrinsic evidence to be presented about the contract, the trial court was concluding the terms of the contract were ambiguous.

We agree with the trial court. The contract was ambiguous because it did not specify the type of fire pit that would be included, whether built in or free standing. In addition, the contract did not indicate if the ramp was handicapped accessible or simply being used in lieu of stairs as a method of entering and exiting the deck. The court’s determination that the contract was ambiguous was correct and the court’s use of extrinsic evidence was appropriate.

The court also heard evidence from both parties as to the terms of the contract and found Appellee’s evidence more credible. Appellee provided

substantial evidence to the court that her interpretation of the contract was the correct one. She testified as to her conversations with Appellant regarding the deck and provided text messages that bolstered her testimony. The court found Appellant’s testimony more credible, as was its prerogative, and ruled in her favor. There was no error.

Free access — add to your briefcase to read the full text and ask questions with AI

Jim Topolski D/B/A American Deck & Sunroom Company v. Mary Johnson, (Ky. Ct. App. 2024).

Jim Topolski D/B/A American Deck & Sunroom Company v. Mary Johnson (Jim Topolski D/B/A American Deck & Sunroom Company v. Mary Johnson) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Huff Contracting v. Sark
12 S.W.3d 704 (Court of Appeals of Kentucky, 2000)
Moore v. Asente
110 S.W.3d 336 (Kentucky Supreme Court, 2003)
Cantrell Supply, Inc. v. Liberty Mutual Insurance Co.
94 S.W.3d 381 (Court of Appeals of Kentucky, 2002)
Energy Home, Division of Southern Energy Homes, Inc. v. Peay
406 S.W.3d 828 (Kentucky Supreme Court, 2013)
Superior Steel, Inc. v. Ascent at Roebling's Bridge, LLC
540 S.W.3d 770 (Missouri Court of Appeals, 2017)