J.I. Hass Co. v. Gilbane Building Co.

881 F.2d 89, 1989 U.S. App. LEXIS 11389, 1989 WL 87835
CourtCourt of Appeals for the Third Circuit
DecidedAugust 8, 1989
DocketNos. 88-5465, 88-5523
StatusPublished
Cited by2 cases

This text of 881 F.2d 89 (J.I. Hass Co. v. Gilbane Building Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.I. Hass Co. v. Gilbane Building Co., 881 F.2d 89, 1989 U.S. App. LEXIS 11389, 1989 WL 87835 (3d Cir. 1989).

Opinion

[90]*90OPINION OF THE COURT

A. LEON HIGGINBOTHAM, Jr., Circuit Judge.

This is both an appeal and a cross-appeal from the judgment of the district court awarding the plaintiff-appellant quantum meruit compensation pursuant to a jury verdict. The plaintiff-appellant contends that the district court erred in its determination of the prejudgment interest due under the award. The defendant-cross-appellant appeals from the district court’s judgment on the merits of this case, contending that the district court misapplied the law and committed reversible trial errors. Upon our review of the record before us and the legal precepts involved, we find for the cross-appellant. Accordingly, we will reverse the district court’s judgment and remand for a new trial.

I.

This action arises out of a contractual dispute between a prime contractor and subcontractor, both of whom were involved in the construction of a brewery for the Miller Brewing Company (“Miller”) in Trenton, Ohio. The Gilbane Building Company of Rhode Island (“Gilbane”), one of Miller’s prime contractors, entered into a subcontract with the J.I. Hass Company, Inc. of New Jersey (“Hass”), a painting contractor. This subcontract, dated March 24, 1981, was written and executed by both parties and required Hass to perform painting work in certain buildings in the construction project.1 The subcontract also contained language, standard in the construction trade, allowing Gilbane to direct Hass to perform extra work through the issuance of change orders that increased the subcontract's scope. Under these change orders, Hass was to receive additional compensation in exchange.

Section 7(b) of the parties’ subcontract provided for the performance of extra work and the payment thereof as follows:

(b) No changes shall be made in the work except upon the written order of the Contractor; the amount to be paid by the Contractor or allowed by the Subcontractor by virtue of said changes to be stated in said orders. In the event of any additions, the amount of compensation to be paid, as so ordered, shall be determined as follows:
(1) By such applicable unit prices as set forth in the contract, or
(2) If no such unit prices are set forth, then by a lump sum mutually agreed upon by the Architect, General Contractor and Subcontractor, or
(3) If no such unit prices are set forth, and if the parties cannot agree upon a lump sum, then by the actual net cost in money to the Subcontractor of materials and labor ... plus compensation of 5% for overhead and 10% for profit.

Appendix (“App.”) at 3378.

Pursuant to § 7(b), change order no. 1 was entered on June 1, 1981. Under that change order, Hass agreed to paint more facilities for an additional $753,000. App. at 3466. After Hass had begun performing under change order no. 1, however, a dispute arose between Gilbane and Hass as to whether certain painting of the buildings’ “mechanical systems” 2 fell within the change order’s scope. Gilbane directed Hass to perform the work that was disputed. Hass subsequently performed some of the work under protest, submitting a claim for compensation pursuant to the extra work provisions of the subcontract. Gilbane adhered, however, to its interpretation of change order no. 1 as providing Hass with full compensation for the extra work, and rejected Hass’ claim for additional compensation.

[91]*91On May 13, 1983, Hass commenced this action against Gilbane in the United States District Court for New Jersey, which had diversity jurisdiction pursuant to 28 U.S.C. § 1332(a)(1) (1982). Hass not only advanced a claim for compensation for the contested extra work, but also sought, in the first count of its complaint, rescission of the base subcontract on the ground that no contract had formed between the parties. The matter proceeded to trial, and was submitted to the jury upon instructions and written interrogatories. The first interrogatory put to the jury asked:

1. Has plaintiff proven that there was no contract between plaintiff Hass and defendant Gilbane?

App. at 159.

At the end of the first day of deliberations, the jury submitted the following communication to the district court:

Regarding] question number 1. We agree that the base contract existed and we agree that there was no meeting of the minds on change order number 1. Confusion arises as to the wording of question number 1. Based on what we agree on, is the answer yes or no to question number 1?

App. at 3239.

Over Gilbane’s objection, the district court responded to the jury’s question as follows:

Considering the evidence and the Court’s instructions as a whole and considering all of the work together, you must determine as a whole whether Hass has proven that there was no contract between the plaintiff Hass and the defendant Gil-bane.

App. at 3251-52.

Thereafter, the jury returned with a verdict answering the first interrogatory in the affirmative — i.e., that there was no contract between Hass and Gilbane. Consequently, the jury awarded Hass $1,461,-872.63 in quantum meruit compensation, the amount owed on Hass’ total cost claim,3 including a 21% mark-up for overhead and profit. The jury also found that Gilbane was entitled to a credit of $242,251 against Hass for a “fair allowance for any defects or omissions in ... Hass' performance of the work.” App. at 161.

Gilbane subsequently moved for judgment notwithstanding the verdict and, alternatively, for a new trial, remittitur, or reduction in the money judgment. The court denied Gilbane’s first three motions but granted a $31,000 reduction in the award of damages. On May 25, 1988, the court entered judgment nunc pro tunc against Gilbane in the amount of $1,188,-621.63 plus $291,908 in pre-judgment interest for a total sum of $1,480,529.63.

On June 9, 1988, Gilbane filed its notice of appeal as to the final judgment of the district court, and on June 22, 1988, Hass filed its notice of appeal as to the district court’s determination of pre-judgment interest due under the award. In addition, we granted leave on January 17, 1989 for the Building Contractors Association of New Jersey (“BCA”) to file a brief in this appeal as an amicus curiae. We have jurisdiction pursuant to 28 U.S.C. § 1291 (1982).

II.

Gilbane’s principal argument on appeal is that there was a valid subcontract between the parties as a matter of law, irrespective of the dispute as to the scope of work under change order no. 1. On that basis, Gilbane contends that the district court erred in denying its motion for a directed verdict dismissing the first count of Hass’ complaint and its motion for a judgment notwithstanding the verdict or, alternatively, for a new trial. Gilbane also contends that the district court erred in denying its motion for a new trial on the basis that the district court, through its supplemental jury instruction, had erroneously rejected the jury’s initial determination of the exist

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
881 F.2d 89, 1989 U.S. App. LEXIS 11389, 1989 WL 87835, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ji-hass-co-v-gilbane-building-co-ca3-1989.